Question

Q 6.      The board of directors of Essex Multi-Construction Corp. is meeting to choose between the...

Q 6.      The board of directors of Essex Multi-Construction Corp. is meeting to choose between the completed-contract method and the percentage-of-completion method of accounting for long-term contracts in the company's financial statements. You have been engaged to assist Essex’s controller in the preparation of a presentation to be given at the board meeting. The controller provides you with the following information:

1.    Essex commenced doing business on January 1, 2019.

2.    Construction activities for the year ended December 31, 2019, were as follows:

Project

Total Contract Price

Contract cost incurred through 31-12-2019

Estimated additional cost to complete contract

A

$615,000

$510,000

$120,000

B

$450,000

$130,000

$260,000

C

$475,000

$350,000

0

D

$600,000

$370,000

$290,000

E

$480,000

$320,000

$80,000

Total:

$2,620,000

$1,680,000

$750,000

3.    Each contract is with a different customer.

4.    Any work remaining to be done on the contracts is expected to be completed in 2020.

Instructions

a)    Prepare a schedule by project, calculating the amount of gross profit (or loss) for the 2019 calendar year, which would be reported under the percentage-of-completion method for each of the project. Show all relevant calculations.                                                                                                           Marks: 7

b)    Prepare the general journal entry to record revenue and gross profit on project B for 2019, assuming that the percentage-of-completion method is used.                                                               Marks: 2

Homework Answers

Answer #1
a
A B C D E
Contract price 615000 450000 475000 600000 480000
Contract costs incurred 510000 130000 350000 370000 320000
Additional costs to complete 120000 260000 0 290000 80000
Total Cost 630000 390000 350000 660000 400000
Total Gross profit or (Loss) -15000 60000 125000 -60000 80000
The amount reported as income (loss) under the percentage-of-completion method for 2019 is:
Project
A -15000
B 20000 (60000*130000/390000)
C 125000
D -60000
E 64000 80000*320000/400000
b
General Journal Debit Credit
Construction in process 20000
Construction expenses 130000
Revenue from Long-term Contracts 150000
Know the answer?
Your Answer:

Post as a guest

Your Name:

What's your source?

Earn Coins

Coins can be redeemed for fabulous gifts.

Not the answer you're looking for?
Ask your own homework help question
Similar Questions
The board of directors for Apache Construction Corp. is meeting to choose between the completed-contract method...
The board of directors for Apache Construction Corp. is meeting to choose between the completed-contract method and the percentage-of-completion method of accounting for long-term contracts in the company's financial statements. You have been engaged to assist Apache’s controller in the preparation of a presentation to be given at the board meeting. The controller provides you with the following information: ·        Apache commenced doing business on January 1, 2020. ·        Construction activities for the year ended December 31, 2020, were as follows: Project...
The board of directors of Ogle Construction Company is meeting to choose between the completed contract...
The board of directors of Ogle Construction Company is meeting to choose between the completed contract method and the percentage-of-completion method of accounting for long-term contracts in the company's financial statements. You have been engaged to assist Ogle's controller in the preparation of a presentation to be given at the board meeting. The controller provides you with the following information: 1. Ogle commenced doing business on January 1, 2018. 2. Construction activities for the year ended December 31, 2018, were...
Long Construction Company uses the percentage-of-completion method of accounting for long-term construction contracts. During 2021, Long...
Long Construction Company uses the percentage-of-completion method of accounting for long-term construction contracts. During 2021, Long began work on a $400 million fixed-fee construction contract, which was completed in 2024. Cost incurred and estimated costs to complete at year-end for the life of the contract are as follows ($ in millions): Cost Incurred Estimated Costs to Complete as of December 31 2021 $60 $240 2022 $84 $176 For the year 2022, Long should have recognized gross profit on this contract...
On June 15, 2018, Sanderson Construction entered into a long-term construction contract to build a baseball...
On June 15, 2018, Sanderson Construction entered into a long-term construction contract to build a baseball stadium in Washington, D.C., for $330 million. The expected completion date is April 1, 2020, just in time for the 2020 baseball season. Costs incurred and estimated costs to complete at year-end for the life of the contract are as follows ($ in millions): 2018 2019 2020 Costs incurred during the year $ 90 $ 70 $ 45 Estimated costs to complete as of...
On March 1, 2017, Pharoah Construction Company contracted to construct a factory building for Fabrik Manufacturing...
On March 1, 2017, Pharoah Construction Company contracted to construct a factory building for Fabrik Manufacturing Inc. for a total contract price of $8,390,000. The building was completed by October 31, 2019. The annual contract costs incurred, estimated costs to complete the contract, and accumulated billings to Fabrik for 2017, 2018, and 2019 are given below: 2017 2018 2019 2017 2018 2019 Contract costs incurred during the year $3,003,300 $2,179,700 $2,117,000 Estimated costs to complete the contract at 12/31 3,386,700...
Redwood Construction Company uses the percentage-of-completion method of accounting for long-term construction contracts. During 2021, Redwood...
Redwood Construction Company uses the percentage-of-completion method of accounting for long-term construction contracts. During 2021, Redwood began work on a $4,300,000 fixed-fee construction contract, which was completed in 2024. Cost Incurred Estimated Additional Cost to Complete 2021 $800,000 $3,200,000 2022 $1,000,000 $2,200,000 2023 $936,000 $1,064,000 For the year 2023, Redwood should have recognized gross profit on this contract of: A)500,000 B)300,000 C)225,00 D)135,000
Curtiss Construction Company, Inc., entered into a fixed-price contract with Axelrod Associates on July 1, 2018,...
Curtiss Construction Company, Inc., entered into a fixed-price contract with Axelrod Associates on July 1, 2018, to construct a four-story office building. At that time, Curtiss estimated that it would take between two and three years to complete the project. The total contract price for construction of the building is $4,540,000. Curtiss concludes that the contract does not qualify for revenue recognition over time. The building was completed on December 31, 2020. Estimated percentage of completion, accumulated contract costs incurred,...
On February 1, 2021, Arrow Construction Company entered into a three-year construction contract to build a...
On February 1, 2021, Arrow Construction Company entered into a three-year construction contract to build a bridge for a price of $8,210,000. During 2021, costs of $2,070,000 were incurred with estimated costs of $4,070,000 yet to be incurred. Billings of $2,570,000 were sent, and cash collected was $2,320,000. In 2022, costs incurred were $2,570,000 with remaining costs estimated to be $3,705,000. 2022 billings were $2,820,000 and $2,545,000 cash was collected. The project was completed in 2023 after additional costs of...
Curtiss Construction Company, Inc., entered into a fixed-price contract with Axelrod Associates on July 1, 2018,...
Curtiss Construction Company, Inc., entered into a fixed-price contract with Axelrod Associates on July 1, 2018, to construct a four-story office building. At that time, Curtiss estimated that it would take between two and three years to complete the project. The total contract price for construction of the building is $4,540,000. Curtiss concludes that the contract does not qualify for revenue recognition over time. The building was completed on December 31, 2020. Estimated percentage of completion, accumulated contract costs incurred,...
Martinez Construction Company began work on a $419,500 construction contract in 2020. During 2020, Martinez incurred...
Martinez Construction Company began work on a $419,500 construction contract in 2020. During 2020, Martinez incurred costs of $282,500, billed its customer for $232,500, and collected $181,000. At December 31, 2020, the estimated additional costs to complete the project total $164,140. Prepare Martinez’s journal entry to record profit or loss, if any, using (a) the percentage-of-completion method and (b) the completed-contract method. (Credit account titles are automatically indented when amount is entered. Do not indent manually. If no entry is...