The board of directors for Apache Construction Corp. is meeting to choose between the completed-contract method and the percentage-of-completion method of accounting for long-term contracts in the company's financial statements. You have been engaged to assist Apache’s controller in the preparation of a presentation to be given at the board meeting. The controller provides you with the following information:
· Apache commenced doing business on January 1, 2020.
· Construction activities for the year ended December 31, 2020, were as follows:
Project |
Total contract Price |
Billings through 12/31/20 |
Cash collections through 12/31/20 |
A |
$ 615,000 |
$ 340,000 |
$ 310,000 |
B |
450,000 |
135,000 |
135,000 |
C |
475,000 |
475,000 |
390,000 |
D |
600,000 |
240,000 |
160,000 |
E |
480,000 |
400,000 |
400,000 |
$ 2,620,000 |
$ 1,590,000 |
$ 1,395,000 |
Project |
Contract costs incurred through 12/31/20 |
Estimated additional costs to complete contracts |
A |
$ 510,000 |
$ 120,000 |
B |
130,000 |
260,000 |
C |
350,000 |
-0- |
D |
370,000 |
290,000 |
E |
320,000 |
80,000 |
$ 1,680,000 |
$ 750,000 |
· Each contract is with a different customer.
· Any work remaining to be done on the contracts is expected to be completed in 2021.
Required
1. Prepare a schedule by project, calculating the amount of gross profit (or loss) for the 2020 calendar year, which would be reported under:
a. The completed-contract method.
b. The percentage-of-completion method (based on estimated costs).
2. Prepare the general journal entry to record revenue and gross profit on project B for 2020, assuming that the percentage-of-completion method is used.
3. Indicate the balances that would appear in the statement of financial position at December 31, 2020 for the following accounts for Project D, assuming that the percentage-of-completion method is used.
a. Accounts Receivable
b. Billings on Construction in Process
c. Construction in Process
How would the balances in the accounts discussed in part 3 above change (if at all) for Project D, if the completed-contract method is used?
1… | |||||||||
Project | Contract costs incurred through 12/31/20 | Estimated additional costs to complete contracts | % complete= costs incurred/(Cost incurred+Estd. Addl.costs to complete | Total contract price(revenue) | Revenue recognised under (100%) completed contract method | Gross profit for 2020 reported under CC method=revenue recognised-Costs incurred | Revenue recognised under % of completion method=Total contract price*% complete | Gross profit for 2020reported under % of completion method=revenue recognised-Costs incurred todate | |
1 | 2=Given | 3=Given | 4 | 5 | 6=Given | 7=6*5 | 8=7-2 | 9=6*5 | 10=9-2 |
A | 510000 | 120000 | 510000/(510000+120000)= | 80.95% | 615000 | 0 | NA | 497857.14 | -12142.86 |
B | 130000 | 260000 | 130000/(130000+260000)= | 33.33% | 450000 | 0 | NA | 150000.00 | 20000.00 |
C | 350000 | 0 | 350000/(350000+0)= | 100.00% | 475000 | 475000 | 125000 | 475000.00 | 125000.00 |
D | 370000 | 290000 | 370000/(370000+290000)= | 56.06% | 600000 | 0 | NA | 336363.64 | -33636.36 |
E | 320000 | 80000 | 320000/(320000+80000)= | 80.00% | 480000 | 0 | NA | 384000.00 | 64000.00 |
1680000 | 750000 | 1680000/(1680000+750000)= | 69.14% | 2620000 | 475000 | 125000 | 1843220.78 | 163220.78 |
2. Project B | Debit | Credit |
Construction expense | 130000 | |
Construction-in-process | 20000 | |
Construction revenue | 150000 | |
(net for gross profit--as revenue recognised is more than costs recognised) | ||
3. For project D | ||
Journal entries under % of completion method will be: | ||
Construction in Process | 370000 | |
Cash | 370000 | |
(to record incurring costs) | ||
Accounts receivable | 240000 | |
Billings on Construction in Process | 240000 | |
(to record billing) | ||
Cash | 160000 | |
Accounts receivable | 160000 | |
(to record reciving payments) | ||
Construction expense | 370000 | |
Construction-in-process | 33636.36 | |
Construction revenue | 336363.6 | |
(to recognise revenues, costs, & gross loss) | ||
So, from the above, balances as at Dec 31, 2020, against the following a/cs will be | ||
a. Accounts Receivable | 80000 Dr. | |
b.Billings on Construction in Process | 240000 Cr. | |
c.Construction in Process | 33636.36 Cr. | |
the balances as at Dec 31, 2020, against the following a/cs under completed contract method for Project D --will be | ||
a. Accounts Receivable | 80000 Dr. | |
b.Billings on Construction in Process | 240000 Cr. | |
c.Construction in Process | 370000 Dr. | |
only c will change, as no revenue is recognised yet) |
Get Answers For Free
Most questions answered within 1 hours.