Question

The board of directors for Apache Construction Corp. is meeting to choose between the completed-contract method...

The board of directors for Apache Construction Corp. is meeting to choose between the completed-contract method and the percentage-of-completion method of accounting for long-term contracts in the company's financial statements. You have been engaged to assist Apache’s controller in the preparation of a presentation to be given at the board meeting. The controller provides you with the following information:

·        Apache commenced doing business on January 1, 2020.

·        Construction activities for the year ended December 31, 2020, were as follows:

Project

Total contract

Price

Billings through

12/31/20        

Cash collections through

12/31/20

A

$ 615,000

$ 340,000

$ 310,000

B

450,000

135,000

135,000

C

475,000

475,000

390,000

D

600,000

240,000

160,000

E

480,000

400,000

400,000

$ 2,620,000

$ 1,590,000

$ 1,395,000

        

Project

Contract costs incurred through 12/31/20

Estimated additional costs to complete contracts

A

$ 510,000

$ 120,000

B

130,000

260,000

C

350,000

-0-

D

370,000

290,000

E

320,000

80,000

$ 1,680,000

$ 750,000

·        Each contract is with a different customer.

·        Any work remaining to be done on the contracts is expected to be completed in 2021.

Required

1.      Prepare a schedule by project, calculating the amount of gross profit (or loss) for the 2020 calendar year, which would be reported under:                                                  

a.      The completed-contract method.

b.      The percentage-of-completion method (based on estimated costs).

2.      Prepare the general journal entry to record revenue and gross profit on project B for 2020, assuming that the percentage-of-completion method is used.                               

3.      Indicate the balances that would appear in the statement of financial position at December 31, 2020 for the following accounts for Project D, assuming that the percentage-of-completion method is used.                                                                                                      

a.      Accounts Receivable

b.      Billings on Construction in Process

c.      Construction in Process

How would the balances in the accounts discussed in part 3 above change (if at all) for Project D, if the completed-contract method is used?          

Homework Answers

Answer #1
1…
Project Contract costs incurred through 12/31/20 Estimated additional costs to complete contracts % complete= costs incurred/(Cost incurred+Estd. Addl.costs to complete Total contract price(revenue) Revenue recognised under (100%) completed contract method Gross profit for 2020 reported under CC method=revenue recognised-Costs incurred Revenue recognised under % of completion method=Total contract price*% complete Gross profit for 2020reported under % of completion method=revenue recognised-Costs incurred todate
1 2=Given 3=Given 4 5 6=Given 7=6*5 8=7-2 9=6*5 10=9-2
A 510000 120000 510000/(510000+120000)= 80.95% 615000 0 NA 497857.14 -12142.86
B 130000 260000 130000/(130000+260000)= 33.33% 450000 0 NA 150000.00 20000.00
C 350000 0 350000/(350000+0)= 100.00% 475000 475000 125000 475000.00 125000.00
D 370000 290000 370000/(370000+290000)= 56.06% 600000 0 NA 336363.64 -33636.36
E 320000 80000 320000/(320000+80000)= 80.00% 480000 0 NA 384000.00 64000.00
1680000 750000 1680000/(1680000+750000)= 69.14% 2620000 475000 125000 1843220.78 163220.78
2. Project B Debit Credit
Construction expense 130000
Construction-in-process 20000
Construction revenue 150000
(net for gross profit--as revenue recognised is more than costs recognised)
3. For project D
Journal entries under % of completion method will be:
Construction in Process 370000
Cash 370000
(to record incurring costs)
Accounts receivable 240000
Billings on Construction in Process 240000
(to record billing)
Cash 160000
Accounts receivable 160000
(to record reciving payments)
Construction expense 370000
Construction-in-process 33636.36
Construction revenue 336363.6
(to recognise revenues, costs, & gross loss)
So, from the above, balances as at Dec 31, 2020, against the following a/cs will be
a. Accounts Receivable 80000 Dr.
b.Billings on Construction in Process 240000 Cr.
c.Construction in Process 33636.36 Cr.
the balances as at Dec 31, 2020, against the following a/cs under completed contract method for Project D --will be
a. Accounts Receivable 80000 Dr.
b.Billings on Construction in Process 240000 Cr.
c.Construction in Process 370000 Dr.
only c will change, as no revenue is recognised yet)
Know the answer?
Your Answer:

Post as a guest

Your Name:

What's your source?

Earn Coins

Coins can be redeemed for fabulous gifts.

Not the answer you're looking for?
Ask your own homework help question
Similar Questions
The board of directors of Ogle Construction Company is meeting to choose between the completed contract...
The board of directors of Ogle Construction Company is meeting to choose between the completed contract method and the percentage-of-completion method of accounting for long-term contracts in the company's financial statements. You have been engaged to assist Ogle's controller in the preparation of a presentation to be given at the board meeting. The controller provides you with the following information: 1. Ogle commenced doing business on January 1, 2018. 2. Construction activities for the year ended December 31, 2018, were...
Q 6.      The board of directors of Essex Multi-Construction Corp. is meeting to choose between the...
Q 6.      The board of directors of Essex Multi-Construction Corp. is meeting to choose between the completed-contract method and the percentage-of-completion method of accounting for long-term contracts in the company's financial statements. You have been engaged to assist Essex’s controller in the preparation of a presentation to be given at the board meeting. The controller provides you with the following information: 1.    Essex commenced doing business on January 1, 2019. 2.    Construction activities for the year ended December 31, 2019,...
Curtiss Construction Company, Inc., entered into a fixed-price contract with Axelrod Associates on July 1, 2018,...
Curtiss Construction Company, Inc., entered into a fixed-price contract with Axelrod Associates on July 1, 2018, to construct a four-story office building. At that time, Curtiss estimated that it would take between two and three years to complete the project. The total contract price for construction of the building is $4,540,000. Curtiss concludes that the contract does not qualify for revenue recognition over time. The building was completed on December 31, 2020. Estimated percentage of completion, accumulated contract costs incurred,...
On June 15, 2020, Lion Construction signed a $ 360,000 contract to build a small building....
On June 15, 2020, Lion Construction signed a $ 360,000 contract to build a small building. Lion estimated that the total cost would be $ 320,000. Construction started immediately because the required completion date was August 31, 2021. Lion’s relevant data relating to this construction project were as follows:      2020             2021 Actual costs incurred $ 120,000      $ 204,000 Estimated costs to complete 200,000               -0- Progress billings 112,000        248,000 Collections 110,000        250,000 Instructions (show all supporting calculations) Calculate how much...
In 2013, Long Construction Corporation began construction work under a three-year contract. The contract price is...
In 2013, Long Construction Corporation began construction work under a three-year contract. The contract price is $2,400,000. Long uses the percentage-of-completion method for financial reporting purposes. The financial statement presentation relating to this contract at December 31, 2013, is as follows:   Balance Sheet   Accounts receivable (from construction progress billings) $ 38,000        Construction in progress $ 160,000        Less: Billings on construction contract (150,000 )        Cost of uncompleted contracts in excess of billings 10,000 Income Statement   Income (before tax) on the contract...
In February 2020, Sandhill Construction signed a contract and commenced construction on a parking garage. The...
In February 2020, Sandhill Construction signed a contract and commenced construction on a parking garage. The total contract price was $90.4 million and was expected to be completed in July 2022 at a total estimated cost of $82.4 million. Payment by the customer was to be made in several stages, based on significant events and dates throughout the construction timeline. Based on the terms of the contract with the customer, control over the parking garage (i.e. ownership) does not transfer...
On February 1, 2021, Arrow Construction Company entered into a three-year construction contract to build a...
On February 1, 2021, Arrow Construction Company entered into a three-year construction contract to build a bridge for a price of $8,210,000. During 2021, costs of $2,070,000 were incurred with estimated costs of $4,070,000 yet to be incurred. Billings of $2,570,000 were sent, and cash collected was $2,320,000. In 2022, costs incurred were $2,570,000 with remaining costs estimated to be $3,705,000. 2022 billings were $2,820,000 and $2,545,000 cash was collected. The project was completed in 2023 after additional costs of...
Curtis Co. entered into a long-term contract in 2020. The contract price was $2,250,000. The following...
Curtis Co. entered into a long-term contract in 2020. The contract price was $2,250,000. The following data pertain to the first two years that the contract was in process. 2020                              2021               Costs incurred to date                                    $   570,000                  $1,557,500    Estimated costs to complete as of 12/31       1,330,000                         667,500 Billings to date                                                     650,000                     1,250,000    Cash collections to date                                     600,000                     1,150,000 1. Using the percentage-of-completion method: A. Compute gross profit to be reported in each...
Curtiss Construction Company, Inc., entered into a fixed-price contract with Axelrod Associates on July 1, 2018,...
Curtiss Construction Company, Inc., entered into a fixed-price contract with Axelrod Associates on July 1, 2018, to construct a four-story office building. At that time, Curtiss estimated that it would take between two and three years to complete the project. The total contract price for construction of the building is $4,540,000. Curtiss concludes that the contract does not qualify for revenue recognition over time. The building was completed on December 31, 2020. Estimated percentage of completion, accumulated contract costs incurred,...
On June 1, 2020, Roman Construction Company Inc. contracted to build an office building for Sicily...
On June 1, 2020, Roman Construction Company Inc. contracted to build an office building for Sicily Corp. for a total contract price of $2,600,000. On July 1, Roman estimated that it would take between 2 and 3 years to complete the building. On December 31, 2022, the building was substantially completed. Following are accumulated contract costs incurred, estimated costs to complete the contract, and accumulated billings to Sicily 2020, 2021, and 2022. 2020 2021 2022 Costs incurred to date $600,000...