Question

On June 15, 2018, Sanderson Construction entered into a long-term construction contract to build a baseball...

On June 15, 2018, Sanderson Construction entered into a long-term construction contract to build a baseball stadium in Washington, D.C., for $330 million. The expected completion date is April 1, 2020, just in time for the 2020 baseball season. Costs incurred and estimated costs to complete at year-end for the life of the contract are as follows ($ in millions):

2018 2019 2020
Costs incurred during the year $ 90 $ 70 $ 45
Estimated costs to complete as of December 31 160 40


Required:
1. Compute the revenue and gross profit will Sanderson report in its 2018, 2019, and 2020 income statements related to this contract assuming Sanderson recognizes revenue over time according to percentage of completion.
2. Compute the revenue and gross profit will Sanderson report in its 2018, 2019, and 2020 income statements related to this contract assuming this project does not qualify for revenue recognition over time.
3. Suppose the estimated costs to complete at the end of 2019 are $160 million instead of $40 million. Compute the amount of revenue and gross profit or loss to be recognized in 2019 assuming Sanderson recognizes revenue over time according to percentage of completion.

Requirement 1.

Percentages of completion
Choose numerator ÷ Choose denominator = % complete to date
2018 ÷ =
2019 ÷ =
2020
2018
To date Recognized in prior years Recognized in 2021
Construction revenue
Construction expense
Gross profit (loss)
2019
To date Recognized in prior years Recognized in 2022
Construction revenue
Construction expense
Gross profit (loss)
2020
To date Recognized in prior years Recognized in 2023
Construction revenue
Construction expense
Gross profit (loss)

Requirement 2.

Year Revenue recognized Gross Profit (Loss) recognized
2018 million million
2019 million million
2020 million million

Requirement 3.

Percentages of completion
Choose numerator ÷ Choose denominator = % complete to date
2019 ÷ =
2019
To date Recognized in prior Years Recognized in 2019
Construction revenue
Construction expense
Gross profit (loss)

Homework Answers

Answer #1
Statement showing computation of Gross Profit recognizze over time assuming percebtage of completion method
Percentages of completion
Choose numerator ÷ Choose denominator = % complete to date
Actual costs to date Estimated total costs
2018 $90 ÷ $250 = 36.00%
(90+160)
2019 $160 ÷ $200 = 80.00%
(90+70) (90+70+40)
2020 100.00%
2018
To date (A) Recognized in prior years (B) Recognized in 2018 (A-B)
Construction revenue $119 $0 $119
(330X36%)
Less: Construction expense $90 $0 $90
Gross profit (loss) $29 $0 $29
2019
To date (A) Recognized in prior years (B) Recognized in 2019 (A-B)
Construction revenue $264 $119 $145
(330*80%) Prevoius Year
Less: Construction expense $160 $90 $70
(90+70) Prevoius Year
Gross profit (loss) $104 $29 $75
2020
To date (A) Recognized in prior years (B) Recognized in 2020 (A-B)
Construction revenue $330 $264 $66
Contract Value
Less: Construction expense $205 $160 $45
(90+70+45) Prevoius Year)
Gross profit (loss) $125 $104 $21
2. Statement showing revenue and gross profit assuming this project does not qualify for revenue recognition over time. ( $ in Million)
Year Revenue recognized Gross Profit (Loss) recognized
2018 $0 $0
2019 $0 $0
2020 $330 $125
(330-205)
Part-3 : Computation of Revenue and gross profit or loss to be recognized in 2019 (using the percentage of completion )
Percentages of completion
Choose numerator ÷ Choose denominator = % complete to date
Actual costs to date Estimated total costs
2019 $160 ÷ $320 = 50.00%
2020 (160+160) 100.00%
2019
To date Recognized in prior years Recognized in 2019
Construction revenue $165 $119 $46
(330*50%)
Less:Construction expense $160 $90 $70
(90+70)
Gross profit (loss) $5 $29 ($24)
Know the answer?
Your Answer:

Post as a guest

Your Name:

What's your source?

Earn Coins

Coins can be redeemed for fabulous gifts.

Not the answer you're looking for?
Ask your own homework help question
Similar Questions
Curtiss Construction Company, Inc., entered into a fixed-price contract with Axelrod Associates on July 1, 2018,...
Curtiss Construction Company, Inc., entered into a fixed-price contract with Axelrod Associates on July 1, 2018, to construct a four-story office building. At that time, Curtiss estimated that it would take between two and three years to complete the project. The total contract price for construction of the building is $4,540,000. Curtiss concludes that the contract does not qualify for revenue recognition over time. The building was completed on December 31, 2020. Estimated percentage of completion, accumulated contract costs incurred,...
Curtiss Construction Company, Inc., entered into a fixed-price contract with Axelrod Associates on July 1, 2018,...
Curtiss Construction Company, Inc., entered into a fixed-price contract with Axelrod Associates on July 1, 2018, to construct a four-story office building. At that time, Curtiss estimated that it would take between two and three years to complete the project. The total contract price for construction of the building is $4,540,000. Curtiss concludes that the contract does not qualify for revenue recognition over time. The building was completed on December 31, 2020. Estimated percentage of completion, accumulated contract costs incurred,...
In 2018, the Westgate Construction Company entered into a contract to construct a road for Santa...
In 2018, the Westgate Construction Company entered into a contract to construct a road for Santa Clara County for $10,000,000. The road was completed in 2020. Information related to the contract is as follows: 2018 2019 2020 Cost incurred during the year $ 2,580,000 $ 4,042,000 $ 2,175,800 Estimated costs to complete as of year-end 6,020,000 1,978,000 0 Billings during the year 2,060,000 4,562,000 3,378,000 Cash collections during the year 1,830,000 4,200,000 3,970,000 Westgate recognizes revenue over time according to...
In 2018, the Westgate Construction Company entered into a contract to construct a road for Santa...
In 2018, the Westgate Construction Company entered into a contract to construct a road for Santa Clara County for $10,000,000. The road was completed in 2020. Information related to the contract is as follows: 2018 2019 2020 Cost incurred during the year $ 2,580,000 $ 4,042,000 $ 2,175,800 Estimated costs to complete as of year-end 6,020,000 1,978,000 0 Billings during the year 2,060,000 4,562,000 3,378,000 Cash collections during the year 1,830,000 4,200,000 3,970,000 Westgate recognizes revenue over time according to...
In 2018, the Westgate Construction Company entered into a contract to construct a road for Santa...
In 2018, the Westgate Construction Company entered into a contract to construct a road for Santa Clara County for $10,000,000. The road was completed in 2020. Information related to the contract is as follows: 2018 2019 2020 Cost incurred during the year $ 2,581,000 $ 2,347,000 $ 3,049,200 Estimated costs to complete as of year-end 6,319,000 2,772,000 0 Billings during the year 2,090,000 2,838,000 5,072,000 Cash collections during the year 1,845,000 2,900,000 5,255,000 Westgate recognizes revenue over time according to...
In 2018, the Westgate Construction Company entered into a contract to construct a road for Santa...
In 2018, the Westgate Construction Company entered into a contract to construct a road for Santa Clara County for $10,000,000. The road was completed in 2020. Information related to the contract is as follows: 2018 2019 2020 Cost incurred during the year $ 2,490,000 $ 3,984,000 $ 2,008,600 Estimated costs to complete as of year-end 5,810,000 1,826,000 0 Billings during the year 2,030,000 4,444,000 3,526,000 Cash collections during the year 1,815,000 3,900,000 4,285,000 Westgate recognizes revenue over time according to...
1. On November 1, 2018, Taylor signed a one-year contract to provide handyman services on an...
1. On November 1, 2018, Taylor signed a one-year contract to provide handyman services on an as-needed basis to King Associates, with the contract to start immediately. King agreed to pay Taylor $5,400 for the one-year period. Taylor is confident that King will pay that amount, but payment is not scheduled to occur until 2019. Taylor should recognize revenue in 2018 in the amount of Multiple Choice a. $900 b. $2,700 c. $0 d. $5,400 2. Mary signed up and...
A construction company entered into a fixed-price contract to build an office building for $12 million....
A construction company entered into a fixed-price contract to build an office building for $12 million. Construction costs incurred during the first year were $4 million and estimated costs to complete at the end of the year were $6 million. The company recognizes revenue over time according to percentage of completion. How much revenue and gross profit or loss will appear in the company’s income statement in the first year of the contract?
Indiana Co. began a construction project in 2018 with a contract price of $162 million to...
Indiana Co. began a construction project in 2018 with a contract price of $162 million to be received when the project is completed in 2020. During 2018 Indiana Incurred $32 million of costs and estimates and additional $85 million of costs to complete the project. Indiana recognizes revenue over time and for this project recognizes revenue over time according to the percentage of the project that has been completed. Supposed that in 2019, Indiana Incurred additional costs of $63 million...
Jackson Construction has entered into a contract to build a large taco factory for $220,000. Costs...
Jackson Construction has entered into a contract to build a large taco factory for $220,000. Costs incurred and estimated costs to complete at year-end for the life of the contract are as follows: First year Second year Third year Costs during year 40,000 80,000 50,000 Estimated costs to complete 120,000 80,000 -- How much gross profit should be recognized a the end of each year, assuming Jackson recognizes revenue over time according to percentage of completion?