Question

On March 1, 2017, Pharoah Construction Company contracted to construct a factory building for Fabrik Manufacturing...

On March 1, 2017, Pharoah Construction Company contracted to construct a factory building for Fabrik Manufacturing Inc. for a total contract price of $8,390,000. The building was completed by October 31, 2019. The annual contract costs incurred, estimated costs to complete the contract, and accumulated billings to Fabrik for 2017, 2018, and 2019 are given below: 2017 2018 2019

2017 2018 2019

Contract costs incurred during the year $3,003,300 $2,179,700 $2,117,000

Estimated costs to complete the contract at 12/31 3,386,700 2,117,000 –0–

Billings to Fabrik during the year 3,240,000 3,460,000 1,690,000

(a) Using the percentage-of-completion method, prepare schedules to compute the profit or loss to be recognized as a result of this contract for the years ended December 31, 2017, 2018, and 2019.

(b) Using the completed-contract method, prepare schedules to compute the profit or loss to be recognized as a result of this contract for the years ended December 31, 2017, 2018, and 2019.

Homework Answers

Answer #1

For any clarifications please comment.

Know the answer?
Your Answer:

Post as a guest

Your Name:

What's your source?

Earn Coins

Coins can be redeemed for fabulous gifts.

Not the answer you're looking for?
Ask your own homework help question
Similar Questions
On May 1, 2017, Collin Company contracted to construct a factory building for a total contract...
On May 1, 2017, Collin Company contracted to construct a factory building for a total contract price of $9,600,000. The building was completed by May 31, 2019. The annual contract costs incurred, estimated costs to complete the contract, and accumulated billings to Fabrik for 2017, 2018, and 2019 are given below. 2017 2018 2019 Contract costs incurred during the year $3,400,000 $2,400,000 $2,900,000 Estimated costs to complete the contract at 12/31 4,600,000 3,100,000 -0- Billings 1,200,000 4,100,000 4,300,000 Instructions(a) Using...
On July 1, 2017, Torvill Construction Company Inc. contracted to build an office building for Gumbel...
On July 1, 2017, Torvill Construction Company Inc. contracted to build an office building for Gumbel Corp. for a total contract price of $1,900,000. On July 1, Torvill estimated that it would take between 2 and 3 years to complete the building. On December 31, 2019, the building was deemed substantially completed. Following are accumulated contract costs incurred, estimated costs to complete the contract, and accumulated billings to Gumbel for 2017, 2018, and 2019. At 12/31/17 At 12/31/18 At 12/31/19...
Problem 18-10 On March 1, 2020, Pearl Construction Company contracted to construct a factory building for...
Problem 18-10 On March 1, 2020, Pearl Construction Company contracted to construct a factory building for Fabrik Manufacturing Inc. for a total contract price of $8,360,000. The building was completed by October 31, 2022. The annual contract costs incurred, estimated costs to complete the contract, and accumulated billings to Fabrik for 2020, 2021, and 2022 are given below: 2020 2021 2022 Contract costs incurred during the year $2,615,800 $2,633,000 $2,041,200 Estimated costs to complete the contract at 12/31 3,764,200 2,041,200...
Curtiss Construction Company, Inc., entered into a fixed-price contract with Axelrod Associates on July 1, 2018,...
Curtiss Construction Company, Inc., entered into a fixed-price contract with Axelrod Associates on July 1, 2018, to construct a four-story office building. At that time, Curtiss estimated that it would take between two and three years to complete the project. The total contract price for construction of the building is $4,540,000. Curtiss concludes that the contract does not qualify for revenue recognition over time. The building was completed on December 31, 2020. Estimated percentage of completion, accumulated contract costs incurred,...
Curtiss Construction Company, Inc., entered into a fixed-price contract with Axelrod Associates on July 1, 2018,...
Curtiss Construction Company, Inc., entered into a fixed-price contract with Axelrod Associates on July 1, 2018, to construct a four-story office building. At that time, Curtiss estimated that it would take between two and three years to complete the project. The total contract price for construction of the building is $4,540,000. Curtiss concludes that the contract does not qualify for revenue recognition over time. The building was completed on December 31, 2020. Estimated percentage of completion, accumulated contract costs incurred,...
Edwards Company contracted on 4/1/17 to construct a building for $4,800,000. The project was completed in...
Edwards Company contracted on 4/1/17 to construct a building for $4,800,000. The project was completed in 2019. Additional data follow: 2017 2018 2019 Costs incurred to date $1,120,000 $2,700,000 $3,800,000 Estimated cost to complete 2,080,000 900,000 — Billings to date 1,000,000 3,800,000 4,800,000 Collections to date 800,000 2,600,000 4,400,000 Instructions (a) Calculate the income recognized by Edwards under the percentage-of-completion method of accounting in each of the years 2017, 2018, and 2019. (b) Prepare all necessary entries for the year...
Ayayai Construction Company began operations on January 1, 2020. During the year, Ayayai Construction entered into...
Ayayai Construction Company began operations on January 1, 2020. During the year, Ayayai Construction entered into a contract with Lundquist Corp. to construct a manufacturing facility. At that time, Ayayai estimated that it would take 5 years to complete the facility at a total cost of $4,498,000. The total contract price for construction of the facility is $6,045,000. During the year, Ayayai incurred $1,184,040 in construction costs related to the construction project. The estimated cost to complete the contract is...
On June 1, 2020, Roman Construction Company Inc. contracted to build an office building for Sicily...
On June 1, 2020, Roman Construction Company Inc. contracted to build an office building for Sicily Corp. for a total contract price of $2,600,000. On July 1, Roman estimated that it would take between 2 and 3 years to complete the building. On December 31, 2022, the building was substantially completed. Following are accumulated contract costs incurred, estimated costs to complete the contract, and accumulated billings to Sicily 2020, 2021, and 2022. 2020 2021 2022 Costs incurred to date $600,000...
McCombs Contractors received a contract to construct a mental health facility for $2,500. Construction was begun...
McCombs Contractors received a contract to construct a mental health facility for $2,500. Construction was begun in 2017 and completed in 2018. Cost and other data are presented below:                                                                         2017                2018 Costs incurred during the year                         $1,500 $1,300 Estimated costs to complete                              1,200 0 Billings during the year                                    1,200 1,300 Cash collections during the year                        1,000 1,500 Compute the amount of revenue and gross profit recognized during 2017 and 2018. Assume that McCombs recognizes revenue on this contract over...
In 2018, the Westgate Construction Company entered into a contract to construct a road for Santa...
In 2018, the Westgate Construction Company entered into a contract to construct a road for Santa Clara County for $10,000,000. The road was completed in 2020. Information related to the contract is as follows: 2018 2019 2020 Cost incurred during the year $ 2,580,000 $ 4,042,000 $ 2,175,800 Estimated costs to complete as of year-end 6,020,000 1,978,000 0 Billings during the year 2,060,000 4,562,000 3,378,000 Cash collections during the year 1,830,000 4,200,000 3,970,000 Westgate recognizes revenue over time according to...
ADVERTISEMENT
Need Online Homework Help?

Get Answers For Free
Most questions answered within 1 hours.

Ask a Question
ADVERTISEMENT