Question

Redwood Construction Company uses the percentage-of-completion method of accounting for long-term construction contracts. During 2021, Redwood...

Redwood Construction Company uses the percentage-of-completion method of accounting for long-term construction contracts. During 2021, Redwood began work on a $4,300,000 fixed-fee construction contract, which was completed in 2024.

Cost Incurred

Estimated Additional Cost to Complete

2021

$800,000

$3,200,000

2022

$1,000,000

$2,200,000

2023

$936,000

$1,064,000

For the year 2023, Redwood should have recognized gross profit on this contract of:

A)500,000 B)300,000 C)225,00 D)135,000

Homework Answers

Answer #1

Correct answer will be c) 225000

Detail working for your refrence

Statement showing computation of Gross Profit recognizze over time assuming percebtage of completion method
Percentages of completion
Choose numerator ÷ Choose denominator = % complete to date
Actual costs to date Estimated total costs
2021 $800,000 ÷ $4,000,000 = 20.00%
(800000+3200000)
2022 $1,800,000 ÷ $4,000,000 = 45.00%
(1800000+2200000)
2023 2736000 3800000 72.00%
(2736000+1064000)
2021
To date (A) Recognized in prior years (B) Recognized in 2021 (A-B)
Construction revenue $860,000 $0 $860,000
(4300000*20%
Less: Construction expense $800,000 $0 $800,000
Gross profit (loss) $60,000 $0 $60,000
2022
To date (A) Recognized in prior years (B) Recognized in 2022 (A-B)
Construction revenue $1,935,000 $860,000 $1,075,000
(4300000*45%
Less: Construction expense $1,800,000 $800,000 $1,000,000
Gross profit (loss) $135,000 $60,000 $75,000
2023
To date (A) Recognized in prior years (B) Recognized in 2023 (A-B)
Construction revenue $3,096,000 $1,935,000 $1,161,000
(4300000*72%)
Less: Construction expense $2,736,000 $1,800,000 $936,000
Gross profit (loss) $360,000 $135,000 $225,000
Know the answer?
Your Answer:

Post as a guest

Your Name:

What's your source?

Earn Coins

Coins can be redeemed for fabulous gifts.

Not the answer you're looking for?
Ask your own homework help question
Similar Questions
Long Construction Company uses the percentage-of-completion method of accounting for long-term construction contracts. During 2021, Long...
Long Construction Company uses the percentage-of-completion method of accounting for long-term construction contracts. During 2021, Long began work on a $400 million fixed-fee construction contract, which was completed in 2024. Cost incurred and estimated costs to complete at year-end for the life of the contract are as follows ($ in millions): Cost Incurred Estimated Costs to Complete as of December 31 2021 $60 $240 2022 $84 $176 For the year 2022, Long should have recognized gross profit on this contract...
Ivanhoe Construction Company uses the percentage-of-completion method of accounting. In 2021, Ivanhoe began work on a...
Ivanhoe Construction Company uses the percentage-of-completion method of accounting. In 2021, Ivanhoe began work on a contract it had received which provided for a contract price of $39500000. Other details follow: 2021 Costs incurred during the year $18800000 Estimated costs to complete as of December 31 12800000 Billings during the year 17500000 Collections during the year 9700000 What should be the gross profit recognized in 2021? $7900000 $4700000 $20700000 $1566667
Wildhorse Construction Company uses the percentage-of-completion method of accounting. In 2020, Wildhorse began work under contract...
Wildhorse Construction Company uses the percentage-of-completion method of accounting. In 2020, Wildhorse began work under contract #E2-D2, which provided for a contract price of $2,165,000. Other details follow: 2020 2021 Costs incurred during the year $590,520 $1,409,000 Estimated costs to complete, as of December 31 1,005,480 –0– Billings during the year 428,000 2,165,000 Collections during the year 349,000 1,509,000 What portion of the total contract price would be recognized as revenue in 2020? In 2021? Revenue recognized in 2020 $...
In 2021, the Westgate Construction Company entered into a contract to construct a road for Santa...
In 2021, the Westgate Construction Company entered into a contract to construct a road for Santa Clara County for $10,000,000. The road was completed in 2023. Information related to the contract is as follows: 2021 2022 2023 Cost incurred during the year $ 2,072,000 $ 2,738,000 $ 2,849,000 Estimated costs to complete as of year-end 5,328,000 2,590,000 0 Billings during the year 2,160,000 2,650,000 5,190,000 Cash collections during the year 1,880,000 2,700,000 5,420,000 Westgate recognizes revenue over time according to...
Novak Construction Company uses the percentage-of-completion method of accounting. In 2020, Novak began work under contract...
Novak Construction Company uses the percentage-of-completion method of accounting. In 2020, Novak began work under contract #E2-D2, which provided for a contract price of $2,170,000. Other details follow: 2020 2021 Costs incurred during the year $615,810 $1,422,000 Estimated costs to complete, as of December 31 963,190 –0– Billings during the year 426,000 2,170,000 Collections during the year 343,000 1,520,000 (a) New attempt is in progress. Some of the new entries may impact the last attempt grading.Your answer is incorrect. What...
Georgia Co. began a construction project in 2021 with a contract price of $162 million to...
Georgia Co. began a construction project in 2021 with a contract price of $162 million to be received when the project is completed in 2023. During 2021, Georgia incurred $30 million of costs and estimates an additional $82 million of costs to complete the project. Georgia recognizes revenue over time and for this project recognizes revenue over time according to the percentage of the project that has been completed.    In 2022, Georgia incurred additional costs of $59 million and...
On February 1, 2021, Arrow Construction Company entered into a three-year construction contract to build a...
On February 1, 2021, Arrow Construction Company entered into a three-year construction contract to build a bridge for a price of $8,210,000. During 2021, costs of $2,070,000 were incurred with estimated costs of $4,070,000 yet to be incurred. Billings of $2,570,000 were sent, and cash collected was $2,320,000. In 2022, costs incurred were $2,570,000 with remaining costs estimated to be $3,705,000. 2022 billings were $2,820,000 and $2,545,000 cash was collected. The project was completed in 2023 after additional costs of...
In 2021, the Westgate Construction Company entered into a contract to construct a road for Santa...
In 2021, the Westgate Construction Company entered into a contract to construct a road for Santa Clara County for $10,000,000. The road was completed in 2023. Information related to the contract is as follows: 2021 2022 2023 Cost incurred during the year $ 2,400,000 $ 3,600,000 $ 2,200,000 Estimated costs to complete as of year-end 5,600,000 2,000,000 0 Billings during the year 2,000,000 4,000,000 4,000,000 Cash collections during the year 1,800,000 3,600,000 4,600,000 Westgate recognizes revenue over time according to...
Indiana Co. began a construction project in 2021 with a contract price of $165 million to...
Indiana Co. began a construction project in 2021 with a contract price of $165 million to be received when the project is completed in 2023. During 2021, Indiana incurred $30 million of costs and estimates an additional $81 million of costs to complete the project. Indiana recognizes revenue over time and for this project recognizes revenue over time according to the percentage of the project that has been completed. Suppose that, in 2022, Indiana incurred additional costs of $65 million...
Indiana Co. began a construction project in 2021 with a contract price of $165 million to...
Indiana Co. began a construction project in 2021 with a contract price of $165 million to be received when the project is completed in 2023. During 2021, Indiana incurred $32 million of costs and estimates an additional $87 million of costs to complete the project. Indiana recognizes revenue over time and for this project recognizes revenue over time according to the percentage of the project that has been completed. In 2022, Indiana incurred additional costs of $52 million and estimated...