Question

The board of directors of Ogle Construction Company is meeting to choose between the completed contract...

The board of directors of Ogle Construction Company is meeting to choose between the completed contract method and the percentage-of-completion method of accounting for long-term contracts in the company's financial statements. You have been engaged to assist Ogle's controller in the preparation of a presentation to be given at the board meeting. The controller provides you with the following information:

1. Ogle commenced doing business on January 1, 2018.

2. Construction activities for the year ended December 31, 2018, were as follows:

Project Total contact Price Billings Through 12/31/18 Cash Collections through 12/31/18
A $500,000 $340,000 $310,000
B $720,000 $210,000 $210,000
Project Contract Costs Incurred Through 12/31/18 Estimated additional costs to complete contracts
A $424,000 $101,000
B $195,000 $455,000

3. Each contract is with a different customer

4. Any work remaining to be done on the contracts is expected to be completed in 2019

Instructions:

(a) Prepare a schedule by project, computing the amount of income (or loss) before selling, general, and administrative expenses for the year ended December 31, 2018, which would be reported under:

  (1) The completed-contract method

(2) The percentage-of-completion method (based on estimated costs)

(B) prepare the journal entry(ies) to record revenue and gross profit on project B (second project) for 2018, assuming that the percentage-of-completion method is used.

(c) indicate the balances that would appear in the balance sheet at December 31, 2018 for the following accounts for project A, assuming that the percentage-of-completion method is used

-accounts receivable

-billings on construction in process

-construction in process

(d) How would the balances in the accounts discussed in part (c) change (if at all) for project B, if the completed-contract method is used?

Homework Answers

Answer #1
Working:
Amounts in Dollars
Project A Project B
Cost Incurred 424000 195000
Addition estimited Cost 101000 455000
Total Cost (Cost Incurred + Additional Estimated Cost) 525000 650000
Percentage Completion (Cost Incurred/Total Cost Calculated)      80.76 30
Contract Price 500000 720000
Revenue Recognizable (Contract Price * Percentage Completion) 403810 216000
Billing 340000 310000
Cash Collected 310000 210000
Receivables Balance as on Dec 31, 2018 (Billing and Cash Collected) 30000 100000
a. Statement of Gain(Loss) for the year ending December 31, 2018
Amount in Dollars
Completed Contract Method Percentage of Completion Method:
Project A Project B Total Project A Project B Total
Revenue 0 0 0        4,03,810        2,16,000               6,19,810
Less: Expense 0 0 0        4,24,000        1,95,000               6,19,000
Gain/Loss on Construction Project 0 0 0          -20,190            21,000                        810
1 As shown above, under Completed contract method, revenue and expense will be recognised only when project is complete and as the project will be completed in coming year 2019, the construction expense and revenue will be recognised in 2019. Till then, all expenses incurred will be debited in Construction in Process Account and Billing amount will be credited in Billing for construction in Process Account
2 As shown in above table
b. Journal Entries for Project B, assuming Percentage of Completion Method:
Account Debit Credit Narration
Constuction in Process Account 195000 Expense Incurred
Bank 195000
Receivables 310000 Billing
Billing for Construction in Process 310000
Bank 210000 Cash Received
Receivables 210000
Construction Expense 195000 Gain/Loss on Construction
Construction Revenue             2,16,000
Construction in Process      21,000
c. Balances in Balance Sheet for the Project A at December 31,2018, assuming Percentage of Completion Method:
Debit Credit Comments
Accounts Receivables 30000 Computed in Working above
Billing for Construction in Process 340000 Billed Amount
Construction in Process 403810 Expense Incurred less Loss on Construction Project
d. Balances in Balance Sheet for the Project B at December 31,2018, assuming Completed Contract Method:
Debit Credit Comments
Accounts Receivables 100000 Computed in Working above
Billing for Construction in Process 310000 Billed Amount
Construction in Process 195000 Expense Incurred
Know the answer?
Your Answer:

Post as a guest

Your Name:

What's your source?

Earn Coins

Coins can be redeemed for fabulous gifts.

Not the answer you're looking for?
Ask your own homework help question
Similar Questions
The board of directors for Apache Construction Corp. is meeting to choose between the completed-contract method...
The board of directors for Apache Construction Corp. is meeting to choose between the completed-contract method and the percentage-of-completion method of accounting for long-term contracts in the company's financial statements. You have been engaged to assist Apache’s controller in the preparation of a presentation to be given at the board meeting. The controller provides you with the following information: ·        Apache commenced doing business on January 1, 2020. ·        Construction activities for the year ended December 31, 2020, were as follows: Project...
Q 6.      The board of directors of Essex Multi-Construction Corp. is meeting to choose between the...
Q 6.      The board of directors of Essex Multi-Construction Corp. is meeting to choose between the completed-contract method and the percentage-of-completion method of accounting for long-term contracts in the company's financial statements. You have been engaged to assist Essex’s controller in the preparation of a presentation to be given at the board meeting. The controller provides you with the following information: 1.    Essex commenced doing business on January 1, 2019. 2.    Construction activities for the year ended December 31, 2019,...
On March 1, 2017, Pharoah Construction Company contracted to construct a factory building for Fabrik Manufacturing...
On March 1, 2017, Pharoah Construction Company contracted to construct a factory building for Fabrik Manufacturing Inc. for a total contract price of $8,390,000. The building was completed by October 31, 2019. The annual contract costs incurred, estimated costs to complete the contract, and accumulated billings to Fabrik for 2017, 2018, and 2019 are given below: 2017 2018 2019 2017 2018 2019 Contract costs incurred during the year $3,003,300 $2,179,700 $2,117,000 Estimated costs to complete the contract at 12/31 3,386,700...
Curtiss Construction Company, Inc., entered into a fixed-price contract with Axelrod Associates on July 1, 2018,...
Curtiss Construction Company, Inc., entered into a fixed-price contract with Axelrod Associates on July 1, 2018, to construct a four-story office building. At that time, Curtiss estimated that it would take between two and three years to complete the project. The total contract price for construction of the building is $4,540,000. Curtiss concludes that the contract does not qualify for revenue recognition over time. The building was completed on December 31, 2020. Estimated percentage of completion, accumulated contract costs incurred,...
On February 1, 2021, Arrow Construction Company entered into a three-year construction contract to build a...
On February 1, 2021, Arrow Construction Company entered into a three-year construction contract to build a bridge for a price of $8,210,000. During 2021, costs of $2,070,000 were incurred with estimated costs of $4,070,000 yet to be incurred. Billings of $2,570,000 were sent, and cash collected was $2,320,000. In 2022, costs incurred were $2,570,000 with remaining costs estimated to be $3,705,000. 2022 billings were $2,820,000 and $2,545,000 cash was collected. The project was completed in 2023 after additional costs of...
In 2013, Long Construction Corporation began construction work under a three-year contract. The contract price is...
In 2013, Long Construction Corporation began construction work under a three-year contract. The contract price is $2,400,000. Long uses the percentage-of-completion method for financial reporting purposes. The financial statement presentation relating to this contract at December 31, 2013, is as follows:   Balance Sheet   Accounts receivable (from construction progress billings) $ 38,000        Construction in progress $ 160,000        Less: Billings on construction contract (150,000 )        Cost of uncompleted contracts in excess of billings 10,000 Income Statement   Income (before tax) on the contract...
Curtiss Construction Company, Inc., entered into a fixed-price contract with Axelrod Associates on July 1, 2018,...
Curtiss Construction Company, Inc., entered into a fixed-price contract with Axelrod Associates on July 1, 2018, to construct a four-story office building. At that time, Curtiss estimated that it would take between two and three years to complete the project. The total contract price for construction of the building is $4,540,000. Curtiss concludes that the contract does not qualify for revenue recognition over time. The building was completed on December 31, 2020. Estimated percentage of completion, accumulated contract costs incurred,...
Multiple Choice Question 103 Oriole Construction is constructing an office building under contract for Cannon Company...
Multiple Choice Question 103 Oriole Construction is constructing an office building under contract for Cannon Company and uses the percentage-of-completion method. The contract calls for progress billings and payments of $1100000 each quarter. The total contract price is $13200000 and Oriole estimates total costs of $17300000. Oriole estimates that the building will take 3 years to complete, and commences construction on January 2, 2018. At December 31, 2019, Oriole Construction estimates that it is 75% complete with the building; however,...
Seasons Construction is constructing an office building under contract for Cannon Company and uses the percentage-of-completion...
Seasons Construction is constructing an office building under contract for Cannon Company and uses the percentage-of-completion method. The contract calls for progress billings and payments of $1,550,000 each quarter. The total contract price is $18,600,000 and Seasons estimates total costs of $17,750,000. Seasons estimates that the building will take 3 years to complete, and commences construction on January 2, 2021. Seasons Construction completes the remaining 25% of the building construction on December 31, 2023, as scheduled. At that time the...
On May 1, 2017, Collin Company contracted to construct a factory building for a total contract...
On May 1, 2017, Collin Company contracted to construct a factory building for a total contract price of $9,600,000. The building was completed by May 31, 2019. The annual contract costs incurred, estimated costs to complete the contract, and accumulated billings to Fabrik for 2017, 2018, and 2019 are given below. 2017 2018 2019 Contract costs incurred during the year $3,400,000 $2,400,000 $2,900,000 Estimated costs to complete the contract at 12/31 4,600,000 3,100,000 -0- Billings 1,200,000 4,100,000 4,300,000 Instructions(a) Using...