Question

In spring 2014, Eva Engineering Company signed a contract with the city of Springfield, to construct...

In spring 2014, Eva Engineering Company signed a contract with the city of Springfield, to construct a new city hall. Eva expects to construct the building within two years and incur expenses of $120 million, which means the company earns a $40 million profit on the contract. The city of Springfield paid $40 million when the contract was signed, $80 million within the next six months, and the final $40 million exactly one year from the signing of the contract. Eva incurred $48 million in costs during 2014 and rest in 2015 to complete the contract on time.

Using the percentage-of-completion method how much revenue should Eva recognize in 2014? What profit from the Springfield contract, will the company report each year? Show all computations.

Revenue:   

2014:

2015:

Profit:   

2014:

2015:

b. Please list at least 3 ways that management can manage their earnings with this construction cost method.

1.

2.

3.

Homework Answers

Answer #1
All amount in $ millions

2014

2015

Cost incurred

48

72

Divided by: Total cost

120

120

Percentage-of-completion

40%

60%

Contracted Sales

160

160

Multiply by: Percentage-of-completion

40%

60%

Revenue recognized during year

64

96

Revenue recognized during year

64

96

Less: cost incurred

48

72

Profit

16

24

Please list at least 3 ways that management can manage their earnings with this construction cost method.

Sales Basis

Installment (on basis of cash collection)

Percentage of Completion

Cost Recoverability Method

Know the answer?
Your Answer:

Post as a guest

Your Name:

What's your source?

Earn Coins

Coins can be redeemed for fabulous gifts.

Not the answer you're looking for?
Ask your own homework help question
Similar Questions
Please answer this In spring of2000, Parmac Engineering Co. signed a $240 million contract to construct...
Please answer this In spring of2000, Parmac Engineering Co. signed a $240 million contract to construct a new city hall. The city paid $60 million when the contract was signed, will pay $120 million within the next six months, and the final $60 million exactly one year from the signing of the contract. Parmac expects to construct the building within two years and incur expenses of $180 million. Parmac incurred $72 million in costs during 2017, and rest of the...
Hardhat Contractors received a contract to construct a bridge for $4,500,000. Construction was begun in 2014...
Hardhat Contractors received a contract to construct a bridge for $4,500,000. Construction was begun in 2014 and completed in 2015. Cost and other data are presented below: 2014 2015 Costs incurred during the year 1,500,000 2,700,000 Estimated costs to complete 2,500,000 - Billings during the year 1,900,000 2,500,000 Cash collections during that year 1,700,000 2,600,000 Assume that Hardhat Contractors uses the percentage-of-completion method for revenue recognition. Compute the amount of gross profit recognized during 2014 and 2015. 2014 2015 Contract...
Using Percentage-of-Completion and Completed Contract Methods Halsey Building Company signed a contract to build an office...
Using Percentage-of-Completion and Completed Contract Methods Halsey Building Company signed a contract to build an office building for $60,000,000. The scheduled construction costs follow. Year Cost 2016 $12,000,000 2017 18,000,000 2018 10,000,000 Total $40,000,000 The building is completed in 2018. For each year, compute the revenue, expense, and gross profit reported for this construction project using each of the following methods. a. Percentage-of-completion method 2016 2017 2018 Revenue $Answer $Answer $Answer Expense $Answer $Answer $Answer Gross Profit $Answer $Answer $Answer...
On Jan 1st, 2019, ACDC Co. signed a contract to construct a bridge to be completed...
On Jan 1st, 2019, ACDC Co. signed a contract to construct a bridge to be completed by the end of 2021. The cataract price is $2,500,000. ACDC Co provides the following information for the project progress. Details 2019 2020 2021 Cost incurred to date $600,000 $1,400,000 $2,100,000 Estimated cost to complete $900,000 $600,000 $0 Customer billings $500,000 $600,000 $350,000 Cash collections $400,000 $500,000 $300,000 Assuming that ACDC uses the percentage of completion method, the cost incurred (used) in 2020 is...
Circle the correct answer symbol 6.Imar Construction company signed a contract to build new bridge at...
Circle the correct answer symbol 6.Imar Construction company signed a contract to build new bridge at a contract price of $5,000,000 and total estimated cost of $4,000,000 the project will be completed within 4 years, the cost incurred to date for each period is, first year $1,000,000- second year $2,500,000- third year $3,200,000 and fourth year $4,100,000 while the estimasted cost to, complete the project for each each period is, first year $3,000,000- second year $1,700,000- third year $1,000,000 and...
1. On November 1, 2018, Taylor signed a one-year contract to provide handyman services on an...
1. On November 1, 2018, Taylor signed a one-year contract to provide handyman services on an as-needed basis to King Associates, with the contract to start immediately. King agreed to pay Taylor $5,400 for the one-year period. Taylor is confident that King will pay that amount, but payment is not scheduled to occur until 2019. Taylor should recognize revenue in 2018 in the amount of Multiple Choice a. $900 b. $2,700 c. $0 d. $5,400 2. Mary signed up and...
Cinnabar Construction Company has consistently used the input method based on costs incurred to recognize revenue...
Cinnabar Construction Company has consistently used the input method based on costs incurred to recognize revenue from a performance obligation satisfied over time. During Year 1, Cinnabar entered into a fixed-price contract to construct an office building for $10 million. Information relating to the contract is as follows: December 31 Year 1 Year 2 Progress to completion 20% 60% Estimated total costs at completion $7,500,000 $8,000,000 Gross profit recognized (cumulative) 500,000 1,200,000 Contract costs incurred during Year 2 were A.$3,500,000...
TreeHold Corp. designs and builds custom equipment for logging companies across Canada. The company is publicly...
TreeHold Corp. designs and builds custom equipment for logging companies across Canada. The company is publicly traded and has a May 31 year end. On February 18, 2020, TreeHold signed a contract with Coastal Harvesting Ltd. to design and build 25 custom harvesters (equipment) that can harvest wood at the steep grades found along much of the Pacific coast timber stands. The following events took place in 2020: 1. February 18: Officials from freehold and Coastal sign the contract. The...
Using the model proposed by Lafley and Charan, analyze how Apigee was able to drive innovation....
Using the model proposed by Lafley and Charan, analyze how Apigee was able to drive innovation. case:    W17400 APIGEE: PEOPLE MANAGEMENT PRACTICES AND THE CHALLENGE OF GROWTH Ranjeet Nambudiri, S. Ramnarayan, and Catherine Xavier wrote this case solely to provide material for class discussion. The authors do not intend to illustrate either effective or ineffective handling of a managerial situation. The authors may have disguised certain names and other identifying information to protect confidentiality. This publication may not be...
What tools could AA leaders have used to increase their awareness of internal and external issues?...
What tools could AA leaders have used to increase their awareness of internal and external issues? ???ALASKA AIRLINES: NAVIGATING CHANGE In the autumn of 2007, Alaska Airlines executives adjourned at the end of a long and stressful day in the midst of a multi-day strategic planning session. Most headed outside to relax, unwind and enjoy a bonfire on the shore of Semiahmoo Spit, outside the meeting venue in Blaine, a seaport town in northwest Washington state. Meanwhile, several members of...
ADVERTISEMENT
Need Online Homework Help?

Get Answers For Free
Most questions answered within 1 hours.

Ask a Question
ADVERTISEMENT