Question

Using Percentage-of-Completion and Completed Contract Methods Halsey Building Company signed a contract to build an office...

Using Percentage-of-Completion and Completed Contract Methods

Halsey Building Company signed a contract to build an office building for $60,000,000. The scheduled construction costs follow.

Year Cost
2016 $12,000,000
2017 18,000,000
2018 10,000,000
Total $40,000,000

The building is completed in 2018.
For each year, compute the revenue, expense, and gross profit reported for this construction project using each of the following methods.

a. Percentage-of-completion method

2016 2017 2018
Revenue $Answer $Answer $Answer
Expense $Answer $Answer $Answer
Gross Profit $Answer $Answer $Answer

b. Completed contract method

2016 2017 2018
Revenue $Answer $Answer $Answer
Expense $Answer $Answer $Answer
Gross Profit $Answer $Answer $Answer

Homework Answers

Know the answer?
Your Answer:

Post as a guest

Your Name:

What's your source?

Earn Coins

Coins can be redeemed for fabulous gifts.

Not the answer you're looking for?
Ask your own homework help question
Similar Questions
Percentage-of-completion method. Arshdeep Builders contracted to build a high-rise for $35,000,000. Construction began in 2018 and...
Percentage-of-completion method. Arshdeep Builders contracted to build a high-rise for $35,000,000. Construction began in 2018 and is expected to be completed in 2020. Data for 2018 and 2019 are: Costs incurred to date Estimated costs to complete Arshdeep uses the percentage-of-completion method. Instructions 2018 $4,500,000 18,000,000 2019 $13,000,000 12,000,000 (a) How much gross profit should be reported for 2018? Show your computation. (b) How much gross profit should be reported for 2019? (c) Make the journal entry to record the...
Seasons Construction is constructing an office building under contract for Cannon Company and uses the percentage-of-completion...
Seasons Construction is constructing an office building under contract for Cannon Company and uses the percentage-of-completion method. The contract calls for progress billings and payments of $1,550,000 each quarter. The total contract price is $18,600,000 and Seasons estimates total costs of $17,750,000. Seasons estimates that the building will take 3 years to complete, and commences construction on January 2, 2021. Seasons Construction completes the remaining 25% of the building construction on December 31, 2023, as scheduled. At that time the...
On June 15, 2020, Lion Construction signed a $ 360,000 contract to build a small building....
On June 15, 2020, Lion Construction signed a $ 360,000 contract to build a small building. Lion estimated that the total cost would be $ 320,000. Construction started immediately because the required completion date was August 31, 2021. Lion’s relevant data relating to this construction project were as follows:      2020             2021 Actual costs incurred $ 120,000      $ 204,000 Estimated costs to complete 200,000               -0- Progress billings 112,000        248,000 Collections 110,000        250,000 Instructions (show all supporting calculations) Calculate how much...
A construction company entered into a fixed-price contract to build an office building for $12 million....
A construction company entered into a fixed-price contract to build an office building for $12 million. Construction costs incurred during the first year were $4 million and estimated costs to complete at the end of the year were $6 million. The company recognizes revenue over time according to percentage of completion. How much revenue and gross profit or loss will appear in the company’s income statement in the first year of the contract?
At the beginning of 2017, Riverbed Construction Company changed from the completed-contract method to recognizing revenue...
At the beginning of 2017, Riverbed Construction Company changed from the completed-contract method to recognizing revenue over time (percentage-of-completion) for financial reporting purposes. The company will continue to use the completed-contract method for tax purposes. For years prior to 2017, pretax income under the two methods was as follows: percentage-of-completion $114,200 and completed-contract $79,700. The tax rate is 35%. Prepare Riverbed’s 2017 journal entry to record the change in accounting principle. Account Titles and Explanation Debit Credit
Circle the correct answer symbol 6.Imar Construction company signed a contract to build new bridge at...
Circle the correct answer symbol 6.Imar Construction company signed a contract to build new bridge at a contract price of $5,000,000 and total estimated cost of $4,000,000 the project will be completed within 4 years, the cost incurred to date for each period is, first year $1,000,000- second year $2,500,000- third year $3,200,000 and fourth year $4,100,000 while the estimasted cost to, complete the project for each each period is, first year $3,000,000- second year $1,700,000- third year $1,000,000 and...
In 2016 the ole construction corp began construction work under a 3 year contract. The contract...
In 2016 the ole construction corp began construction work under a 3 year contract. The contract price was $1,600,000. The Job was completed in 2018.                                                                                 2016                       2017                       2018 Costs incurred to date                                    400000                  935000                  1070000 Estimated costs to complete                       700000                  165000                  0 Billings to date                                                  300000                  900000                  1600000 Collections to date                                           270000                  810000                  1525000 Compute the amount of Gross Profit to be recognized for 2016 and 2017 assuming that ole is required to recognize revenue overtime. Compute the...
Tamarisk Construction Company has entered into a contract beginning January 1, 2017, to build a parking...
Tamarisk Construction Company has entered into a contract beginning January 1, 2017, to build a parking complex. It has been estimated that the complex will cost $601,000 and will take 3 years to construct. The complex will be billed to the purchasing company at $903,000. The following data pertain to the construction period. 2017 2018 2019 Costs to date $270,450 $492,820 $613,000 Estimated costs to complete 330,550 108,180 –0– Progress billings to date 273,000 550,000 903,000 Cash collected to date...
Green Earth Corp. is a construction company that uses the percentage of completion method. They won...
Green Earth Corp. is a construction company that uses the percentage of completion method. They won a contract to build an apartment building in 2019 for $60,000,000. Please record the journal entries relating to each of the events below. Also assume that the company has a December 31 year-end and records adjusting entries only at year-end. a) Actual costs incurred to the end of 2019 were $36,000,000 and all was paid with cash. b) Billings made to the client amounted...
Kiner, Inc. began work in 2018 on a contract for €21,000,000. Other data are as follows:...
Kiner, Inc. began work in 2018 on a contract for €21,000,000. Other data are as follows: 2018     2019 Costs incurred to date €9,000,000 €14,000,000 Estimated costs to complete 6,000,000 — Billings to date 7,000,000 21,000,000 Collections to date 5,000,000 18,000,000 8. If Kiner uses the percentage-of-completion method, the gross profit to be recognized in 2018 is A. €3,600,000. B. €4,000,000. C. €5,400,000. D. €6,000,000. 9. If Kiner uses the cost-recovery method, the gross profit to be recognized in 2019 is...
ADVERTISEMENT
Need Online Homework Help?

Get Answers For Free
Most questions answered within 1 hours.

Ask a Question
ADVERTISEMENT
Active Questions
  • Two teaching methods and their effects on science test scores are being reviewed. A random sample...
    asked 2 minutes ago
  • Please submit an original 50 word response to the summary below: The organization in which I...
    asked 11 minutes ago
  • A community generates 75,000 lb/day of solid waste that is deposited in a municipal landfill. The...
    asked 25 minutes ago
  • Suppose the sale price of a used car can be predicted by a function f(x, y)...
    asked 56 minutes ago
  • Which of the following is the most effective approach to delinquency prevention: psychosocial development or punishment?...
    asked 1 hour ago
  • You are testing the null hypothesis that there is no linear relationship between two​ variables, X...
    asked 1 hour ago
  • Using Microsoft Excel functions: 1. A machine will cost $50,000 to purchase. Annual operating cost will...
    asked 1 hour ago
  • Please, edit for clarity and conciseness, for grammar, capitalization, punctuation, abbreviation, number style, word division, and...
    asked 1 hour ago
  • Suppose your body was able to use chemical energy in gasoline. How far could you pedal...
    asked 2 hours ago
  • Consider why persons with disabilities are considered a vulnerable population. Share with others experiences you may...
    asked 2 hours ago
  • find the explicit particular solution of the initial value problem 2*x^1/2(dy/dx)=(cos^2)*y y(4)=pi/4 differntial equations
    asked 2 hours ago
  • Soma recorded in the table the height of each player on the basketball team Basketball Players’...
    asked 2 hours ago