Question

On Jan 1st, 2019, ACDC Co. signed a contract to construct a bridge to be completed...

On Jan 1st, 2019, ACDC Co. signed a contract to construct a bridge to be completed by the end of 2021. The cataract price is $2,500,000. ACDC Co provides the following information for the project progress.

Details

2019

2020

2021

Cost incurred to date

$600,000

$1,400,000

$2,100,000

Estimated cost to complete

$900,000

$600,000

$0

Customer billings

$500,000

$600,000

$350,000

Cash collections

$400,000

$500,000

$300,000

Assuming that ACDC uses the percentage of completion method, the cost incurred (used) in 2020 is

Select one:

a. $700,000

b. $600,000

c. $800,000

d. $1,400,000

Assuming that ACDC uses the cost-recovery method, the company record gross profit (loss) in 2019 of

Select one:

a. $400,000

b. $350,000

c. $50,000

d. $0

Assuming that ACDC uses the percentage of completion method, the percentage of completion for 2019 is

Select one:

a. 40%

b. 75%

c. 30%

d. 100%

assuming that ACDC uses the percentage of completion method, Gross Profit (loss) for the year 2020 is

Select one:

a. $(50,000)

b. $350,000

c. $500,000

d. $400,000

Homework Answers

Answer #1

1.

Costs incurrred in 2020 = Total costs incurred till 2020 - Total costs incurred in 2019

= 1400000 - 600000

= 800000

C

2.

Cost in 2019 was $600000

Cost % = 600000 / 2100000 = 30%

Revenue for 2019 = 2500000*30% = 750000

There is gross Profit in 2019, So GP = 750000-600000 = $150000

3.

% completion 2019 = Cost of completion in 2019 / Total cost

= 600000 / 2100000

= 28.57% OR 30%

C

4.

costs incurred in Year 2020 = $800000

Revenue realised = 66.67%*2500000 - 30%*2500000

= 1666667 - 750000

= 916667

Gross Profit = $116667

Know the answer?
Your Answer:

Post as a guest

Your Name:

What's your source?

Earn Coins

Coins can be redeemed for fabulous gifts.

Not the answer you're looking for?
Ask your own homework help question
Similar Questions
The board of directors for Apache Construction Corp. is meeting to choose between the completed-contract method...
The board of directors for Apache Construction Corp. is meeting to choose between the completed-contract method and the percentage-of-completion method of accounting for long-term contracts in the company's financial statements. You have been engaged to assist Apache’s controller in the preparation of a presentation to be given at the board meeting. The controller provides you with the following information: ·        Apache commenced doing business on January 1, 2020. ·        Construction activities for the year ended December 31, 2020, were as follows: Project...
In 2018, the Westgate Construction Company entered into a contract to construct a road for Santa...
In 2018, the Westgate Construction Company entered into a contract to construct a road for Santa Clara County for $10,000,000. The road was completed in 2020. Information related to the contract is as follows: 2018 2019 2020 Cost incurred during the year $ 2,580,000 $ 4,042,000 $ 2,175,800 Estimated costs to complete as of year-end 6,020,000 1,978,000 0 Billings during the year 2,060,000 4,562,000 3,378,000 Cash collections during the year 1,830,000 4,200,000 3,970,000 Westgate recognizes revenue over time according to...
On June 15, 2020, Lion Construction signed a $ 360,000 contract to build a small building....
On June 15, 2020, Lion Construction signed a $ 360,000 contract to build a small building. Lion estimated that the total cost would be $ 320,000. Construction started immediately because the required completion date was August 31, 2021. Lion’s relevant data relating to this construction project were as follows:      2020             2021 Actual costs incurred $ 120,000      $ 204,000 Estimated costs to complete 200,000               -0- Progress billings 112,000        248,000 Collections 110,000        250,000 Instructions (show all supporting calculations) Calculate how much...
1. On November 1, 2018, Taylor signed a one-year contract to provide handyman services on an...
1. On November 1, 2018, Taylor signed a one-year contract to provide handyman services on an as-needed basis to King Associates, with the contract to start immediately. King agreed to pay Taylor $5,400 for the one-year period. Taylor is confident that King will pay that amount, but payment is not scheduled to occur until 2019. Taylor should recognize revenue in 2018 in the amount of Multiple Choice a. $900 b. $2,700 c. $0 d. $5,400 2. Mary signed up and...
Curtis Co. entered into a long-term contract in 2020. The contract price was $2,250,000. The following...
Curtis Co. entered into a long-term contract in 2020. The contract price was $2,250,000. The following data pertain to the first two years that the contract was in process. 2020                              2021               Costs incurred to date                                    $   570,000                  $1,557,500    Estimated costs to complete as of 12/31       1,330,000                         667,500 Billings to date                                                     650,000                     1,250,000    Cash collections to date                                     600,000                     1,150,000 1. Using the percentage-of-completion method: A. Compute gross profit to be reported in each...
On February 1, 2020, a company agreed to construct a building at a contract price of...
On February 1, 2020, a company agreed to construct a building at a contract price of $40,000. The company estimated the project would be finished in 2022. Information relating to the costs and billings for this contract is as follows:                                                     2020             2021           2022 Total costs incurred to date        $8,000        $10,000         $22,000 Estimated costs to complete      12,000          6,000            -0- Customer billings to date           8,000          18,000         28,000 Collections to date                     5,000           15,000         26,000 If the company uses the percentage-of-completion method, the gross profit to be recognized in 2021 is___________________________ .
PRACTICAL QUESTION                                       &nb
PRACTICAL QUESTION                                                                                          Tiger Construction Ltd signs a contract on 1 May 2018 to build a theme park. The construction is scheduled to commence on 1 July 2018 and the estimated date of completion is 30 June 2021. The total contract price is $5m and the cost of the park is initially estimated at $4.5m. The following data relates to the construction period: For the year ended 30 June 2019 2020 2021 $ $ $ Costs to date 1,700,000 3,000,000 4,800,000...
On June 15, 2018, Sanderson Construction entered into a long-term construction contract to build a baseball...
On June 15, 2018, Sanderson Construction entered into a long-term construction contract to build a baseball stadium in Washington, D.C., for $330 million. The expected completion date is April 1, 2020, just in time for the 2020 baseball season. Costs incurred and estimated costs to complete at year-end for the life of the contract are as follows ($ in millions): 2018 2019 2020 Costs incurred during the year $ 90 $ 70 $ 45 Estimated costs to complete as of...
Kiner, Inc. began work in 2018 on a contract for €21,000,000. Other data are as follows:...
Kiner, Inc. began work in 2018 on a contract for €21,000,000. Other data are as follows: 2018     2019 Costs incurred to date €9,000,000 €14,000,000 Estimated costs to complete 6,000,000 — Billings to date 7,000,000 21,000,000 Collections to date 5,000,000 18,000,000 8. If Kiner uses the percentage-of-completion method, the gross profit to be recognized in 2018 is A. €3,600,000. B. €4,000,000. C. €5,400,000. D. €6,000,000. 9. If Kiner uses the cost-recovery method, the gross profit to be recognized in 2019 is...
During 2019, Almon Inc. started a construction job with a contract price of $8000. The job...
During 2019, Almon Inc. started a construction job with a contract price of $8000. The job was completed in 2019 and information for the three years of construction is as follows: 2019 2020 2021 TOTAL costs incurred to date (ie sum of all costs, for all years, incurred at the end of the year) $2,000 $4,500 $7,600 Estimated costs to complete (as estimated at year end) 5,000 2900 -0- Billings to date 2,200 6,000 8,000 Collections to date 1,600 4,800...