On Jan 1st, 2019, ACDC Co. signed a contract to construct a bridge to be completed by the end of 2021. The cataract price is $2,500,000. ACDC Co provides the following information for the project progress.
Details |
2019 |
2020 |
2021 |
Cost incurred to date |
$600,000 |
$1,400,000 |
$2,100,000 |
Estimated cost to complete |
$900,000 |
$600,000 |
$0 |
Customer billings |
$500,000 |
$600,000 |
$350,000 |
Cash collections |
$400,000 |
$500,000 |
$300,000 |
Assuming that ACDC uses the percentage of completion method, the cost incurred (used) in 2020 is
Select one:
a. $700,000
b. $600,000
c. $800,000
d. $1,400,000
Assuming that ACDC uses the cost-recovery method, the company record gross profit (loss) in 2019 of
Select one:
a. $400,000
b. $350,000
c. $50,000
d. $0
Assuming that ACDC uses the percentage of completion method, the percentage of completion for 2019 is
Select one:
a. 40%
b. 75%
c. 30%
d. 100%
assuming that ACDC uses the percentage of completion method, Gross Profit (loss) for the year 2020 is
Select one:
a. $(50,000)
b. $350,000
c. $500,000
d. $400,000
1.
Costs incurrred in 2020 = Total costs incurred till 2020 - Total costs incurred in 2019
= 1400000 - 600000
= 800000
C
2.
Cost in 2019 was $600000
Cost % = 600000 / 2100000 = 30%
Revenue for 2019 = 2500000*30% = 750000
There is gross Profit in 2019, So GP = 750000-600000 = $150000
3.
% completion 2019 = Cost of completion in 2019 / Total cost
= 600000 / 2100000
= 28.57% OR 30%
C
4.
costs incurred in Year 2020 = $800000
Revenue realised = 66.67%*2500000 - 30%*2500000
= 1666667 - 750000
= 916667
Gross Profit = $116667
Get Answers For Free
Most questions answered within 1 hours.