Question

Imar Construction company signed a contract to build new bridge at a contract price of $5,000,000...

Imar Construction company signed a contract to build new bridge at a contract price of $5,000,000 and total estimated cost of $4,000,000 the project will be completed within 4 years, the cost incurred to date for each period is, first year $1,000,000- second year $2,500,000- third year $3,200,000 and fourth year $4,100,000 while the estimasted cost to, complete the project for each each period is, first year $3,000,000- second year $1,700,000- third year $1,000,000 and fourth year is $0, based on above question and using percentage of completion method, what is the required journal entry in second year?

a.
Debit Construction in process $2,500,000, cash 2,500,000.

b.
Debit Construction in process $1,0000,000, Cash $1,000,000.

c.
No entry is required.

d.
Debit Construction in process $1,500,000, credit cash, payable $1,500,000.

Homework Answers

Know the answer?
Your Answer:

Post as a guest

Your Name:

What's your source?

Earn Coins

Coins can be redeemed for fabulous gifts.

Not the answer you're looking for?
Ask your own homework help question
Similar Questions
Circle the correct answer symbol 6.Imar Construction company signed a contract to build new bridge at...
Circle the correct answer symbol 6.Imar Construction company signed a contract to build new bridge at a contract price of $5,000,000 and total estimated cost of $4,000,000 the project will be completed within 4 years, the cost incurred to date for each period is, first year $1,000,000- second year $2,500,000- third year $3,200,000 and fourth year $4,100,000 while the estimasted cost to, complete the project for each each period is, first year $3,000,000- second year $1,700,000- third year $1,000,000 and...
In 2021, the Southgate Construction Company entered into a contract to construct a bridge for $12,000,000....
In 2021, the Southgate Construction Company entered into a contract to construct a bridge for $12,000,000. The bridge was completed in 2023. Information related to the contract is as follows: 2021 2022 2023 Cost incurred during the year $1,840,000 $3,760,000 $4,500,000 Estimated costs to complete as of year-end $6,160,000 $4,400,000 $0 Billings during the year $3,000,000 $4,000,000 $5,000,000 Cash collections during thee year $2,600,000 $3,900,000 $5,100,000 Southgate recognizes revenue using the completed contract method. What amount will Southgate show on...
Hardhat Contractors received a contract to construct a bridge for $4,500,000. Construction was begun in 2014...
Hardhat Contractors received a contract to construct a bridge for $4,500,000. Construction was begun in 2014 and completed in 2015. Cost and other data are presented below: 2014 2015 Costs incurred during the year 1,500,000 2,700,000 Estimated costs to complete 2,500,000 - Billings during the year 1,900,000 2,500,000 Cash collections during that year 1,700,000 2,600,000 Assume that Hardhat Contractors uses the percentage-of-completion method for revenue recognition. Compute the amount of gross profit recognized during 2014 and 2015. 2014 2015 Contract...
PV of cash flow stream A rookie quarterback is negotiating his first NFL contract. His opportunity...
PV of cash flow stream A rookie quarterback is negotiating his first NFL contract. His opportunity cost is 7%. He has been offered three possible 4-year contracts. Payments are guaranteed, and they would be made at the end of each year. Terms of each contract are as follows: 1 2 3 4 Contract 1 $2,500,000 $2,500,000 $2,500,000 $2,500,000 Contract 2 $2,500,000 $3,000,000 $4,000,000 $5,000,000 Contract 3 $7,000,000 $1,500,000 $1,500,000 $1,500,000 As his adviser, which contract would you recommend that he...
A construction firm enters a long-term contract to build a bridge, which was completed in Year...
A construction firm enters a long-term contract to build a bridge, which was completed in Year 4. The expected and actual cash receipts and disbursements for the   project (in millions) are as follows: year Receipts Expenditures 1 3,000 4,000 2 4,000 3,000 3 5,000 2,000 4 8,000 1,000 Total 20,000 10,000 What is the income before taxes during each year under Installment Method of revenue recognition?   
A project to build a new bridge seems to be going very well since the project...
A project to build a new bridge seems to be going very well since the project is well ahead of schedule and costs seem to be running very low. A major milestone has been reached where the first two activities have been totally completed and the third activity is 65% complete. The planners were only expecting to be 55% through the third activity at this time. The first activity involves prepping the site for the bridge. It was expected that...
On December 31, 2019, Shawshank Construction Inc. signs a contract to manufacture a bridge which it...
On December 31, 2019, Shawshank Construction Inc. signs a contract to manufacture a bridge which it anticipates the construction will take three years. The company’s accountants provide the following contract details relating to the project: Contract price: $780 million Estimated construction costs: $600 million Estimated total profit: $180 million During the three-year construction period, Shawshank incurred costs as follows: 2020 $ 60 million 2021 $360 million 2022 $180 million Shawshank uses the cost-to-cost method to recognize revenue. Which of the...
ABC Properties Ltd. has a contract to build a hotel for $3,000,000 to be received in...
ABC Properties Ltd. has a contract to build a hotel for $3,000,000 to be received in equal installments over 4 years. A reliable estimate of total cost of this contract is $1,500,000. During the first year, ABC will incur $400,000 in cost. During the second year, $500,000 of costs will be incurred. And then $300,000 will be incurred in the last two years. The company is quite sure that the project will be completed on time. According to the US...
The Titanic Shipbuilding Company has a noncancelable contract to build a small cargo vessel. Construction involves...
The Titanic Shipbuilding Company has a noncancelable contract to build a small cargo vessel. Construction involves a cash outlay of $270,000 at the end of each of the next two years. At the end of the third year the company will receive payment of $638,000. Assume the IRR of this option exceeds the cost of capital. The company can speed up construction by working an extra shift. In this case there will be a cash outlay of $590,000 at the...
The Titanic Shipbuilding Company has a noncancelable contract to build a small cargo vessel. Construction involves...
The Titanic Shipbuilding Company has a noncancelable contract to build a small cargo vessel. Construction involves a cash outlay of $267,000 at the end of each of the next two years. At the end of the third year the company will receive payment of $625,000. Assume the IRR of this option exceeds the cost of capital. The company can speed up construction by working an extra shift. In this case, there will be a cash outlay of $579,000 at the...