Question

Cinnabar Construction Company has consistently used the input method based on costs incurred to recognize revenue...

Cinnabar Construction Company has consistently used the input method based on costs incurred to recognize revenue from a performance obligation satisfied over time. During Year 1, Cinnabar entered into a fixed-price contract to construct an office building for $10 million. Information relating to the contract is as follows:

December 31

Year 1

Year 2

Progress to completion

20%

60%

Estimated total costs

at completion

$7,500,000

$8,000,000

Gross profit recognized

(cumulative)

500,000

1,200,000

Contract costs incurred during Year 2 were

  • A.$3,500,000

  • B.$3,300,000

  • C.$3,200,000

  • D.$4,800,000

Homework Answers

Answer #1
Please give positive ratings so I can keep answering. It would help me a lot. Please comment if you have any query. Thanks!
Cinnabar Construction Company
Year 1 Year 2
Fixed-price contract 10,000,000.00 10,000,000.00
Progress to completion 20% 60%
Revenue recognized     2,000,000.00     6,000,000.00
Less: Gross profit recognized (cumulative)        500,000.00     1,200,000.00
Costs incurred (cumulative)     1,500,000.00     4,800,000.00
Contract costs incurred during Year 2     3,300,000.00
Costs incurred (cumulative) Year 2 less Costs incurred (cumulative) Year 1
So answer is option B.
Know the answer?
Your Answer:

Post as a guest

Your Name:

What's your source?

Earn Coins

Coins can be redeemed for fabulous gifts.

Not the answer you're looking for?
Ask your own homework help question
Similar Questions
Redwood Construction Company uses the percentage-of-completion method of accounting for long-term construction contracts. During 2021, Redwood...
Redwood Construction Company uses the percentage-of-completion method of accounting for long-term construction contracts. During 2021, Redwood began work on a $4,300,000 fixed-fee construction contract, which was completed in 2024. Cost Incurred Estimated Additional Cost to Complete 2021 $800,000 $3,200,000 2022 $1,000,000 $2,200,000 2023 $936,000 $1,064,000 For the year 2023, Redwood should have recognized gross profit on this contract of: A)500,000 B)300,000 C)225,00 D)135,000
Tamarisk Construction Company has entered into a contract beginning January 1, 2017, to build a parking...
Tamarisk Construction Company has entered into a contract beginning January 1, 2017, to build a parking complex. It has been estimated that the complex will cost $601,000 and will take 3 years to construct. The complex will be billed to the purchasing company at $903,000. The following data pertain to the construction period. 2017 2018 2019 Costs to date $270,450 $492,820 $613,000 Estimated costs to complete 330,550 108,180 –0– Progress billings to date 273,000 550,000 903,000 Cash collected to date...
Novak Construction Company uses the percentage-of-completion method of accounting. In 2020, Novak began work under contract...
Novak Construction Company uses the percentage-of-completion method of accounting. In 2020, Novak began work under contract #E2-D2, which provided for a contract price of $2,170,000. Other details follow: 2020 2021 Costs incurred during the year $615,810 $1,422,000 Estimated costs to complete, as of December 31 963,190 –0– Billings during the year 426,000 2,170,000 Collections during the year 343,000 1,520,000 (a) New attempt is in progress. Some of the new entries may impact the last attempt grading.Your answer is incorrect. What...
Jackson Construction has entered into a contract to build a large taco factory for $220,000. Costs...
Jackson Construction has entered into a contract to build a large taco factory for $220,000. Costs incurred and estimated costs to complete at year-end for the life of the contract are as follows: First year Second year Third year Costs during year 40,000 80,000 50,000 Estimated costs to complete 120,000 80,000 -- How much gross profit should be recognized a the end of each year, assuming Jackson recognizes revenue over time according to percentage of completion?
Long Construction Company uses the percentage-of-completion method of accounting for long-term construction contracts. During 2021, Long...
Long Construction Company uses the percentage-of-completion method of accounting for long-term construction contracts. During 2021, Long began work on a $400 million fixed-fee construction contract, which was completed in 2024. Cost incurred and estimated costs to complete at year-end for the life of the contract are as follows ($ in millions): Cost Incurred Estimated Costs to Complete as of December 31 2021 $60 $240 2022 $84 $176 For the year 2022, Long should have recognized gross profit on this contract...
Sallys construction. is a construction company and recognizes revenue, costs, and gross profit at project completion....
Sallys construction. is a construction company and recognizes revenue, costs, and gross profit at project completion. At the start of Year 1, Kip enters a contract to build an office building for $100 million. The project is completed by the end of Year 2. The following additional information is available for this project (amounts in millions): YEAR 1 YEAR 2 Costs incurred during each year $20 $70 Costs expected in future $60 0 sallys Year 2 revenue will be:
Wildhorse Construction Company uses the percentage-of-completion method of accounting. In 2020, Wildhorse began work under contract...
Wildhorse Construction Company uses the percentage-of-completion method of accounting. In 2020, Wildhorse began work under contract #E2-D2, which provided for a contract price of $2,165,000. Other details follow: 2020 2021 Costs incurred during the year $590,520 $1,409,000 Estimated costs to complete, as of December 31 1,005,480 –0– Billings during the year 428,000 2,165,000 Collections during the year 349,000 1,509,000 What portion of the total contract price would be recognized as revenue in 2020? In 2021? Revenue recognized in 2020 $...
Windham Construction Company uses the percentage of completion method of accounting. In 2018 Windham started work...
Windham Construction Company uses the percentage of completion method of accounting. In 2018 Windham started work on a two-year contract with a total price of $15,000,000. Data for 2018 and 2019 are presented below: (Follow GAAP)                                                                  2018                            2019                       Costs incurred to date             $7,200,000                  $12,050,000             Estimated costs to complete   4,800,000                         - 0 -             Billings during the year          6,000,000                      9,000,000             Collections during the year     4,200,000                      8,900,000 (a)       How much...
Ivanhoe Construction Company uses the percentage-of-completion method of accounting. In 2021, Ivanhoe began work on a...
Ivanhoe Construction Company uses the percentage-of-completion method of accounting. In 2021, Ivanhoe began work on a contract it had received which provided for a contract price of $39500000. Other details follow: 2021 Costs incurred during the year $18800000 Estimated costs to complete as of December 31 12800000 Billings during the year 17500000 Collections during the year 9700000 What should be the gross profit recognized in 2021? $7900000 $4700000 $20700000 $1566667
Nash Construction Company uses the percentage-of-completion method of accounting. In 2017, Nash began work under contract...
Nash Construction Company uses the percentage-of-completion method of accounting. In 2017, Nash began work under contract #E2-D2, which provided for a contract price of $2,234,000. Other details follow: 2017 2018 Costs incurred during the year $615,980 $1,420,000 Estimated costs to complete, as of December 31 1,005,020 –0– Billings to date 413,000 2,234,000 Collections during the year 351,000 1,530,000 (a) What portion of the total contract price would be recognized as revenue in 2017? In 2018? Revenue recognized in 2017 $...
ADVERTISEMENT
Need Online Homework Help?

Get Answers For Free
Most questions answered within 1 hours.

Ask a Question
ADVERTISEMENT