McCombs Contractors received a contract to construct a mental
health facility for $2,500. Construction was begun...
McCombs Contractors received a contract to construct a mental
health facility for $2,500. Construction was begun in 2017 and
completed in 2018. Cost and other data are presented below:
2017
2018
Costs incurred during the
year
$1,500
$1,300
Estimated costs to
complete
1,200
0
Billings during the
year
1,200
1,300
Cash collections during the
year
1,000
1,500
Compute the amount of revenue and gross profit recognized
during 2017 and 2018.
Assume that McCombs recognizes revenue on this contract over...
In 2021, the Southgate Construction Company entered into a
contract to construct a bridge for $12,000,000....
In 2021, the Southgate Construction Company entered into a
contract to construct a bridge for $12,000,000. The bridge was
completed in 2023. Information related to the contract is as
follows: 2021 2022 2023 Cost incurred during the year $1,840,000
$3,760,000 $4,500,000 Estimated costs to complete as of year-end
$6,160,000 $4,400,000 $0 Billings during the year $3,000,000
$4,000,000 $5,000,000 Cash collections during thee year $2,600,000
$3,900,000 $5,100,000 Southgate recognizes revenue using the
completed contract method. What amount will Southgate show on...
Beavis Construction Company was the low bidder on a construction
project to build an earthen dam...
Beavis Construction Company was the low bidder on a construction
project to build an earthen dam for $1,800,000. The project was
begun in 2015 and completed in 2016. Cost and other data are
presented below:
2012
2013
Costs
incurred during the year
$
450,000
$1,100,000
Estimated costs to complete
1,050,000
0
Billings
during the year
400,000
1,400,000
Cash collections during the year
300,000
1,500,000
Assume that Beavis recognizes revenue on this contract over time
according to...
On February 1, 2020, Bramble Contractors agreed to construct a
building at a contract price of...
On February 1, 2020, Bramble Contractors agreed to construct a
building at a contract price of $5,820,000. Bramble estimated total
construction costs would be $4,016,000 and the project would be
finished in 2022. Information relating to the costs and billings
for this contract is as follows:
2020 2021 2022
Total costs incurred to date. $1,506,000 $2,652,000
$4,610,000
Estimated costs to complete. 2,510,000 1,768,000 -0-
Customer billings to date 2,220,000 4,016,000 5,620,000
Collections to date 2,020,000 3,520,000 5,520,000
Fill in the...
Circle the correct answer symbol
6.Imar Construction company signed a contract to build new
bridge at...
Circle the correct answer symbol
6.Imar Construction company signed a contract to build new
bridge at a contract price of $5,000,000 and total estimated cost
of $4,000,000 the project will be completed within 4 years, the
cost incurred to date for each period is, first year $1,000,000-
second year $2,500,000- third year $3,200,000 and fourth year
$4,100,000 while the estimasted cost to, complete the project for
each each period is, first year $3,000,000- second year $1,700,000-
third year $1,000,000 and...
In 2021, the Westgate Construction Company entered into a
contract to construct a road for Santa...
In 2021, the Westgate Construction Company entered into a
contract to construct a road for Santa Clara County for
$10,000,000. The road was completed in 2023. Information related to
the contract is as follows:
2021
2022
2023
Cost incurred during the year
$
2,072,000
$
2,738,000
$
2,849,000
Estimated costs to complete as of year-end
5,328,000
2,590,000
0
Billings during the year
2,160,000
2,650,000
5,190,000
Cash collections during the year
1,880,000
2,700,000
5,420,000
Westgate recognizes revenue over time according to...
Imar Construction company signed a contract to build
new bridge at a contract price of $5,000,000...
Imar Construction company signed a contract to build
new bridge at a contract price of $5,000,000 and total estimated
cost of $4,000,000 the project will be completed within 4 years,
the cost incurred to date for each period is, first year
$1,000,000- second year $2,500,000- third year $3,200,000 and
fourth year $4,100,000 while the estimasted cost to, complete the
project for each each period is, first year $3,000,000- second year
$1,700,000- third year $1,000,000 and fourth year is $0, based...
Tamarisk Construction Company has entered into a contract
beginning January 1, 2017, to build a parking...
Tamarisk Construction Company has entered into a contract
beginning January 1, 2017, to build a parking complex. It has been
estimated that the complex will cost $601,000 and will take 3 years
to construct. The complex will be billed to the purchasing company
at $903,000. The following data pertain to the construction
period.
2017
2018
2019
Costs to date
$270,450
$492,820
$613,000
Estimated costs to complete
330,550
108,180
–0–
Progress billings to date
273,000
550,000
903,000
Cash collected to date...
During 2020, Blossom Company started a construction job with a
contract price of $1,610,000. The job...
During 2020, Blossom Company started a construction job with a
contract price of $1,610,000. The job was completed in 2022. The
following information is available.
2020
2021
2022
Costs incurred to date
$393,900
$760,380
$1,059,000
Estimated costs to complete
616,100
341,620
–0–
Billings to date
299,000
905,000
1,610,000
Collections to date
268,000
818,000
1,421,000
(a)
Compute the amount of gross profit to be recognized each year,
assuming the percentage-of-completion method is used.
Gross profit recognized in 2020
$enter a dollar...