1. On November 1, 2018, Taylor signed a one-year contract to provide handyman services on an as-needed basis to King Associates, with the contract to start immediately. King agreed to pay Taylor $5,400 for the one-year period. Taylor is confident that King will pay that amount, but payment is not scheduled to occur until 2019. Taylor should recognize revenue in 2018 in the amount of
Multiple Choice
a. $900
b. $2,700
c. $0
d. $5,400
2.
Mary signed up and paid $1,140 for a 6 month ceramics course on June 1st with Choplet Ceramics. As of August 1st, Choplet’s accounting records would indicate:
Multiple Choice
a. $380 of revenue, $760 of accounts receivable
b. $380 of revenue, $760 of deferred revenue
c. $1,140 of revenue, $1,140 of cash
d. $760 of revenue, $380 of accounts receivable
3.
JRE2 Inc. entered into a contract to install a pipeline for a
fixed price of $2,395,000. JRE2 recognizes revenue upon contract
completion.
Cost incurred | Estimated Cost to Complete | |||||
2017 | $ | 276,000 | $ | 1,680,000 | ||
2018 | 1,730,000 | 630,000 | ||||
2019 | 580,000 | 0 | ||||
In 2018, JRE2 would report gross profit (loss) of:
Multiple Choice
a. $0.
b. $(432,000).
c. $(241,000).
d. $(291,000).
4.
JRE2 Inc. entered into a contract to install a pipeline for a
fixed price of $2,305,000. JRE2 recognizes revenue upon contract
completion.
Cost incurred | Estimated Cost to Complete | |||||
2017 | $ | 264,000 | $ | 1,620,000 | ||
2018 | 1,670,000 | 577,000 | ||||
2019 | 520,000 | 0 | ||||
In 2019, JRE2 would report gross profit (loss) of:
Multiple Choice
a. $(149,000).
b. $108,000.
c. $19,000.
d. $57,000.
5.
Indiana Co. began a construction project in 2018 with a contract
price of $161 million to be received when the project is completed
in 2020. During 2018, Indiana incurred $40 million of costs and
estimates an additional $89 million of costs to complete the
project. Indiana recognizes revenue over time and for this project
recognizes revenue over time according to the percentage of the
project that has been completed.
Indiana:
Multiple Choice
a. Recognized $40.00 million loss on the project in 2018.
b. Recognized no gross profit or loss on the project in 2018.
c. Recognized $72.00 million loss on the project in 2018.
d. Recognized $9.92 million gross profit on the project in 2018.
6.
Indiana Co. began a construction project in 2018 with a contract
price of $164 million to be received when the project is completed
in 2020. During 2018, Indiana incurred $35 million of costs and
estimates an additional $88 million of costs to complete the
project. Indiana recognizes revenue over time and for this project
recognizes revenue over time according to the percentage of the
project that has been completed.
In 2019, Indiana incurred additional costs of $52 million and
estimated an additional $37 million in costs to complete the
project. Indiana (Do not round your percentage
calculated):
Multiple Choice
a. Recognized $40.00 million gross profit on the project in 2019.
b. Recognized $4.00 million gross profit on the project in 2019.
c. Recognized $16.40 million gross profit on the project in 2019.
d. Recognized $38.50 million gross profit on the project in 2019.
7.
Indiana Co. began a construction project in 2018 with a contract
price of $163 million to be received when the project is completed
in 2020. During 2018, Indiana incurred $36 million of costs and
estimates an additional $87 million of costs to complete the
project. Indiana recognizes revenue over time and for this project
recognizes revenue over time according to the percentage of the
project that has been completed.
Suppose that, in 2019, Indiana incurred additional costs of $66
million and estimated an additional $53 million in costs to
complete the project. Indiana (Do not round your percentage
calculated):
Multiple Choice
a. Recognized $6.44 million gross profit on the project in 2019.
b. Recognized $6.44 million loss on the project in 2019.
c. Recognized $9.44 million gross profit on the project in 2019.
d. Recognized $3.00 million loss on the project in 2019.
Dear student, only one question is allowed at a time. I am answering the first question
1)
As per revenue recognition principle, revenue should be recognized only when they are realized or realizable (certainty of receipt is confirmed) and are earned (as in the present scenario, revenue is earned with lapse of time), without any botheration of receipt of cash
So, as per above definition, revenue should be recognized in the present scenario as there is certainty of receipt and it should be recognized for the expired period of contract, that is November to December
So, amount that should be recognized
= Total amount received / Contract period x Expired period
= $5,400 / 12 x 2
= $900
So, as per above discussion, option a is the correct option
Get Answers For Free
Most questions answered within 1 hours.