Question

1. On November 1, 2018, Taylor signed a one-year contract to provide handyman services on an...

1. On November 1, 2018, Taylor signed a one-year contract to provide handyman services on an as-needed basis to King Associates, with the contract to start immediately. King agreed to pay Taylor $5,400 for the one-year period. Taylor is confident that King will pay that amount, but payment is not scheduled to occur until 2019. Taylor should recognize revenue in 2018 in the amount of

Multiple Choice

a. $900

b. $2,700

c. $0

d. $5,400

2.

Mary signed up and paid $1,140 for a 6 month ceramics course on June 1st with Choplet Ceramics. As of August 1st, Choplet’s accounting records would indicate:

Multiple Choice

a. $380 of revenue, $760 of accounts receivable

b. $380 of revenue, $760 of deferred revenue

c. $1,140 of revenue, $1,140 of cash

d. $760 of revenue, $380 of accounts receivable

3.

JRE2 Inc. entered into a contract to install a pipeline for a fixed price of $2,395,000. JRE2 recognizes revenue upon contract completion.

Cost incurred Estimated Cost to Complete
2017 $ 276,000 $ 1,680,000
2018 1,730,000 630,000
2019 580,000 0


In 2018, JRE2 would report gross profit (loss) of:

Multiple Choice

a. $0.

b. $(432,000).

c. $(241,000).

d. $(291,000).

4.

JRE2 Inc. entered into a contract to install a pipeline for a fixed price of $2,305,000. JRE2 recognizes revenue upon contract completion.

Cost incurred Estimated Cost to Complete
2017 $ 264,000 $ 1,620,000
2018 1,670,000 577,000
2019 520,000 0


In 2019, JRE2 would report gross profit (loss) of:

Multiple Choice

a. $(149,000).

b. $108,000.

c. $19,000.

d. $57,000.

5.

Indiana Co. began a construction project in 2018 with a contract price of $161 million to be received when the project is completed in 2020. During 2018, Indiana incurred $40 million of costs and estimates an additional $89 million of costs to complete the project. Indiana recognizes revenue over time and for this project recognizes revenue over time according to the percentage of the project that has been completed.

Indiana:

Multiple Choice

a. Recognized $40.00 million loss on the project in 2018.

b. Recognized no gross profit or loss on the project in 2018.

c. Recognized $72.00 million loss on the project in 2018.

d. Recognized $9.92 million gross profit on the project in 2018.

6.

Indiana Co. began a construction project in 2018 with a contract price of $164 million to be received when the project is completed in 2020. During 2018, Indiana incurred $35 million of costs and estimates an additional $88 million of costs to complete the project. Indiana recognizes revenue over time and for this project recognizes revenue over time according to the percentage of the project that has been completed.

In 2019, Indiana incurred additional costs of $52 million and estimated an additional $37 million in costs to complete the project. Indiana (Do not round your percentage calculated):

Multiple Choice

a. Recognized $40.00 million gross profit on the project in 2019.

b. Recognized $4.00 million gross profit on the project in 2019.

c. Recognized $16.40 million gross profit on the project in 2019.

d. Recognized $38.50 million gross profit on the project in 2019.

7.

Indiana Co. began a construction project in 2018 with a contract price of $163 million to be received when the project is completed in 2020. During 2018, Indiana incurred $36 million of costs and estimates an additional $87 million of costs to complete the project. Indiana recognizes revenue over time and for this project recognizes revenue over time according to the percentage of the project that has been completed.

Suppose that, in 2019, Indiana incurred additional costs of $66 million and estimated an additional $53 million in costs to complete the project. Indiana (Do not round your percentage calculated):

Multiple Choice

a. Recognized $6.44 million gross profit on the project in 2019.

b. Recognized $6.44 million loss on the project in 2019.

c. Recognized $9.44 million gross profit on the project in 2019.

d. Recognized $3.00 million loss on the project in 2019.

Homework Answers

Answer #1

Dear student, only one question is allowed at a time. I am answering the first question

1)

As per revenue recognition principle, revenue should be recognized only when they are realized or realizable (certainty of receipt is confirmed) and are earned (as in the present scenario, revenue is earned with lapse of time), without any botheration of receipt of cash

So, as per above definition, revenue should be recognized in the present scenario as there is certainty of receipt and it should be recognized for the expired period of contract, that is November to December

So, amount that should be recognized

= Total amount received / Contract period x Expired period

= $5,400 / 12 x 2

= $900

So, as per above discussion, option a is the correct option

Know the answer?
Your Answer:

Post as a guest

Your Name:

What's your source?

Earn Coins

Coins can be redeemed for fabulous gifts.

Not the answer you're looking for?
Ask your own homework help question
Similar Questions
Indiana Co. began a construction project in 2021 with a contract price of $164 million to...
Indiana Co. began a construction project in 2021 with a contract price of $164 million to be received when the project is completed in 2023. During 2021, Indiana incurred $36 million of costs and estimates an additional $88 million of costs to complete the project. Indiana recognizes revenue over time and for this project recognizes revenue over time according to the percentage of the project that has been completed. Multiple Choice: A) Recognized $36.00 million loss on the project in...
Indiana Co. began a construction project in 2018 with a contract price of $162 million to...
Indiana Co. began a construction project in 2018 with a contract price of $162 million to be received when the project is completed in 2020. During 2018 Indiana Incurred $32 million of costs and estimates and additional $85 million of costs to complete the project. Indiana recognizes revenue over time and for this project recognizes revenue over time according to the percentage of the project that has been completed. Supposed that in 2019, Indiana Incurred additional costs of $63 million...
Indiana Co. began a construction project in 2021 with a contract price of $165 million to...
Indiana Co. began a construction project in 2021 with a contract price of $165 million to be received when the project is completed in 2023. During 2021, Indiana incurred $30 million of costs and estimates an additional $81 million of costs to complete the project. Indiana recognizes revenue over time and for this project recognizes revenue over time according to the percentage of the project that has been completed. Suppose that, in 2022, Indiana incurred additional costs of $65 million...
Indiana Co. began a construction project in 2021 with a contract price of $165 million to...
Indiana Co. began a construction project in 2021 with a contract price of $165 million to be received when the project is completed in 2023. During 2021, Indiana incurred $32 million of costs and estimates an additional $87 million of costs to complete the project. Indiana recognizes revenue over time and for this project recognizes revenue over time according to the percentage of the project that has been completed. In 2022, Indiana incurred additional costs of $52 million and estimated...
Indiana Co. began a construction project in 2021 with a contract price of $164 million to...
Indiana Co. began a construction project in 2021 with a contract price of $164 million to be received when the project is completed in 2023. During 2021, Indiana incurred $30 million of costs and estimates an additional $83 million of costs to complete the project. Indiana recognizes revenue over time and for this project recognizes revenue over time according to the percentage of the project that has been completed. In 2022, Indiana incurred additional costs of $50 million and estimated...
Georgia Co. began a construction project in 2021 with a contract price of $162 million to...
Georgia Co. began a construction project in 2021 with a contract price of $162 million to be received when the project is completed in 2023. During 2021, Georgia incurred $30 million of costs and estimates an additional $82 million of costs to complete the project. Georgia recognizes revenue over time and for this project recognizes revenue over time according to the percentage of the project that has been completed.    In 2022, Georgia incurred additional costs of $59 million and...
On June 15, 2018, Sanderson Construction entered into a long-term construction contract to build a baseball...
On June 15, 2018, Sanderson Construction entered into a long-term construction contract to build a baseball stadium in Washington, D.C., for $330 million. The expected completion date is April 1, 2020, just in time for the 2020 baseball season. Costs incurred and estimated costs to complete at year-end for the life of the contract are as follows ($ in millions): 2018 2019 2020 Costs incurred during the year $ 90 $ 70 $ 45 Estimated costs to complete as of...
Curtiss Construction Company, Inc., entered into a fixed-price contract with Axelrod Associates on July 1, 2018,...
Curtiss Construction Company, Inc., entered into a fixed-price contract with Axelrod Associates on July 1, 2018, to construct a four-story office building. At that time, Curtiss estimated that it would take between two and three years to complete the project. The total contract price for construction of the building is $4,540,000. Curtiss concludes that the contract does not qualify for revenue recognition over time. The building was completed on December 31, 2020. Estimated percentage of completion, accumulated contract costs incurred,...
Curtiss Construction Company, Inc., entered into a fixed-price contract with Axelrod Associates on July 1, 2018,...
Curtiss Construction Company, Inc., entered into a fixed-price contract with Axelrod Associates on July 1, 2018, to construct a four-story office building. At that time, Curtiss estimated that it would take between two and three years to complete the project. The total contract price for construction of the building is $4,540,000. Curtiss concludes that the contract does not qualify for revenue recognition over time. The building was completed on December 31, 2020. Estimated percentage of completion, accumulated contract costs incurred,...
In 2018, the Westgate Construction Company entered into a contract to construct a road for Santa...
In 2018, the Westgate Construction Company entered into a contract to construct a road for Santa Clara County for $10,000,000. The road was completed in 2020. Information related to the contract is as follows: 2018 2019 2020 Cost incurred during the year $ 2,580,000 $ 4,042,000 $ 2,175,800 Estimated costs to complete as of year-end 6,020,000 1,978,000 0 Billings during the year 2,060,000 4,562,000 3,378,000 Cash collections during the year 1,830,000 4,200,000 3,970,000 Westgate recognizes revenue over time according to...
ADVERTISEMENT
Need Online Homework Help?

Get Answers For Free
Most questions answered within 1 hours.

Ask a Question
ADVERTISEMENT