Company A signed a fixed-price $6,500,000 contract to construct a building. At the end of Year 1,Company A had incurred $1,000,000 in total costs, and expected to incur $3,500,000 in additional costs to complete the building. By the end of Year 2, Company A had incurred total-costs-to-date of $3,000,000 and expected to incur $1,500,000 in cost to complete the building. How much profit should Company A recognize in Year 2 under the cost-to-cost method?
a. $125,000
b. $250,000
c. $375,000
d. $500,000
e. None of the above