Question

Company A signed a fixed-price $6,500,000 contract to construct a building. At the end of Year...

Company A signed a fixed-price $6,500,000 contract to construct a building. At the end of Year 1,Company A had incurred $1,000,000 in total costs, and expected to incur $3,500,000 in additional costs to complete the building. By the end of Year 2, Company A had incurred total-costs-to-date of $3,000,000 and expected to incur $1,500,000 in cost to complete the building. How much profit should Company A recognize in Year 2 under the cost-to-cost method?

a. $125,000

b. $250,000

c. $375,000

d. $500,000

e. None of the above

Please help to show the working for better understanding.

Homework Answers

Know the answer?
Your Answer:

Post as a guest

Your Name:

What's your source?

Earn Coins

Coins can be redeemed for fabulous gifts.

Not the answer you're looking for?
Ask your own homework help question
Similar Questions
Imar Construction company signed a contract to build new bridge at a contract price of $5,000,000...
Imar Construction company signed a contract to build new bridge at a contract price of $5,000,000 and total estimated cost of $4,000,000 the project will be completed within 4 years, the cost incurred to date for each period is, first year $1,000,000- second year $2,500,000- third year $3,200,000 and fourth year $4,100,000 while the estimasted cost to, complete the project for each each period is, first year $3,000,000- second year $1,700,000- third year $1,000,000 and fourth year is $0, based...
In spring 2014, Eva Engineering Company signed a contract with the city of Springfield, to construct...
In spring 2014, Eva Engineering Company signed a contract with the city of Springfield, to construct a new city hall. Eva expects to construct the building within two years and incur expenses of $120 million, which means the company earns a $40 million profit on the contract. The city of Springfield paid $40 million when the contract was signed, $80 million within the next six months, and the final $40 million exactly one year from the signing of the contract....
Indiana Inc. entered into a contract to construct a building in three years for a fixed...
Indiana Inc. entered into a contract to construct a building in three years for a fixed price of $2,200,000. Indiana recognizes revenue over time according to the percentage of the project that has been completed. Cost incurred in 2015 is $250,000 and estimated cost to complete is $1,750,000. Cost incurred in 2016 is $1,500,000 and estimated cost to complete is $250,000. In 2016, Indiana would report (rounded to the nearest thousand) gross profit (loss) of:
On February 1, 2010, Marcos Contractors agreed to construct a building at a contract price of...
On February 1, 2010, Marcos Contractors agreed to construct a building at a contract price of $3,000,000. Marcos estimated total construction costs would be $2,000,000 and the project would be finished in 2012. Information relating to the costs and billings for this contract is as follows: ? 2010?? 2011?? 2012? Total costs incurred to date?$ 750,000?$1,320,000?$2,300,000 Estimated costs to complete?1,250,000? 880,000?-0- Customer billings to date?1,100,000? 2,000,000?3,000,000 Collections to date?1,000,000? 1,750,000?2,950,000 1: Prepare all entries for 2010, 2011, and 2012 for...
On February 1, 2010, Marcos Contractors agreed to construct a building at a contract price of...
On February 1, 2010, Marcos Contractors agreed to construct a building at a contract price of $3,000,000. Marcos estimated total construction costs would be $2,000,000 and the project would be finished in 2012. Information relating to the costs and billings for this contract is as follows: ? 2010?? 2011?? 2012? Total costs incurred to date?$ 750,000?$1,320,000?$2,300,000 Estimated costs to complete?1,250,000? 880,000?-0- Customer billings to date?1,100,000? 2,000,000?3,000,000 Collections to date?1,000,000? 1,750,000?2,950,000 1: Prepare Statement of Financial Position ends of 2010, 2012...
On June 15, 2020, Lion Construction signed a $ 360,000 contract to build a small building....
On June 15, 2020, Lion Construction signed a $ 360,000 contract to build a small building. Lion estimated that the total cost would be $ 320,000. Construction started immediately because the required completion date was August 31, 2021. Lion’s relevant data relating to this construction project were as follows:      2020             2021 Actual costs incurred $ 120,000      $ 204,000 Estimated costs to complete 200,000               -0- Progress billings 112,000        248,000 Collections 110,000        250,000 Instructions (show all supporting calculations) Calculate how much...
Please answer this In spring of2000, Parmac Engineering Co. signed a $240 million contract to construct...
Please answer this In spring of2000, Parmac Engineering Co. signed a $240 million contract to construct a new city hall. The city paid $60 million when the contract was signed, will pay $120 million within the next six months, and the final $60 million exactly one year from the signing of the contract. Parmac expects to construct the building within two years and incur expenses of $180 million. Parmac incurred $72 million in costs during 2017, and rest of the...
Circle the correct answer symbol 6.Imar Construction company signed a contract to build new bridge at...
Circle the correct answer symbol 6.Imar Construction company signed a contract to build new bridge at a contract price of $5,000,000 and total estimated cost of $4,000,000 the project will be completed within 4 years, the cost incurred to date for each period is, first year $1,000,000- second year $2,500,000- third year $3,200,000 and fourth year $4,100,000 while the estimasted cost to, complete the project for each each period is, first year $3,000,000- second year $1,700,000- third year $1,000,000 and...
ABC Properties Ltd. has a contract to build a hotel for $3,000,000 to be received in...
ABC Properties Ltd. has a contract to build a hotel for $3,000,000 to be received in equal installments over 4 years. A reliable estimate of total cost of this contract is $1,500,000. During the first year, ABC will incur $400,000 in cost. During the second year, $500,000 of costs will be incurred. And then $300,000 will be incurred in the last two years. The company is quite sure that the project will be completed on time. According to the US...
A construction company entered into a fixed-price contract to build an office building for $12 million....
A construction company entered into a fixed-price contract to build an office building for $12 million. Construction costs incurred during the first year were $4 million and estimated costs to complete at the end of the year were $6 million. The company recognizes revenue over time according to percentage of completion. How much revenue and gross profit or loss will appear in the company’s income statement in the first year of the contract?