Question

Fred Ridgeway has been given the responsibility of managing a training and development program. The project...

Fred Ridgeway has been given the responsibility of managing a training and development program. The project has progressed over the past several months, Fred would like to know the current status of the project with regard to schedule and budget by developing an appropriate table. The relevant data is provided below. ACTIVITY PERCENTAGE COMPLETED BUDGETED COST ACTUAL COST A 100 $10,000 $13,000 B 100 $14,000 $12,000 C 100 $5,000 $6,000 D 100 $6,000 $6,000 E 60 $14,000 $9,000 F 10 $13,000 $800 G 80 $4,000 $3,600 H 15 $6,000 $375 a) What is the difference between value of the work completed for Activity A and the actual cost of Activity A?

(A positive value means the actual cost exceeds the value of the work completed)

b) What is the difference between value of the work completed for Activity B and the actual cost of Activity B?

c) What is the difference between value of the work completed for Activity C and the actual cost of Activity C?

d) What is the difference between value of the work completed for Activity D and the actual cost of Activity D?

e) What is the difference between value of the work completed for Activity E and the actual cost of Activity E?

f) What is the difference between value of the work completed for Activity F and the actual cost of Activity F?

g) What is the difference between value of the work completed for Activity G and the actual cost of Activity G?

h) What is the difference between value of the work completed for Activity H and the actual cost of Activity H?

i) Currently the total project is: overbudget by $1,975; underbudget by $1,975; overbudget by $8,025; or underbudget by $8,025

Homework Answers

Know the answer?
Your Answer:

Post as a guest

Your Name:

What's your source?

Earn Coins

Coins can be redeemed for fabulous gifts.

Not the answer you're looking for?
Ask your own homework help question
Similar Questions
The Mohawk Discount Store is designing a management training program for individuals at its corporate headquarters....
The Mohawk Discount Store is designing a management training program for individuals at its corporate headquarters. The company wants to design the program so that trainees can complete it as quickly as possible. Important precedence relationships must be maintained between assignments or activities in the program. For example, a trainee cannot serve as an assistant to the store manager until the trainee has obtained experience in the credit department and at least one sales department. The following activities are the...
London Fletcher of Fabriscan Diagnostic, is the project manager. He measured the following information with commutative...
London Fletcher of Fabriscan Diagnostic, is the project manager. He measured the following information with commutative completed times for four periods of the project. Completed% Activity ID Activity Predecessors Estimated Duration(Weeks) Budget ($) Actual Spend ($) 1 2 3 4 Crash time Crash cost$ A 7          7,000                       9,000 20 40 100 100 6             8,000 B A 2          5,000                       5,000 20 60 100 100 1             7,000 C A 4          9,000                       6,000 0 40...
A partially solved PERT problem is detailed in the table below. Times are given in weeks....
A partially solved PERT problem is detailed in the table below. Times are given in weeks. Activity Immediate Predecessor(s) Optimistic Most Likely Pessimistic A -- 8 10 15 B -- 7 8 9 C A 5 6 10 D A 3 3 3 E B,D 1 5 9 F B,D 4 7 10 G C 3 8 10 H E 5 7 9 I E 4 5 8 J F 2 5 8 K H, I 1 3 6 a)...
Given the following information for a project, answer the following questions: Activity Predecessor Activity Time (days)...
Given the following information for a project, answer the following questions: Activity Predecessor Activity Time (days) A - 6 B - 8 C A, B 5 D B 4 E C 7 F C, D 3 G D 6 H E, F, G 5 Fill in the following table. Activity ES EF LS LF Slack CP A 0 No B Yes C Yes D No E Yes F No G 18 14 20 No H 25 20 25 Yes Draw...
A project manager, in preparation for the construction of roads, has identified the activities and their...
A project manager, in preparation for the construction of roads, has identified the activities and their durations to prepare a difficult stretch of motorway (as in the following table). Activity Duration (days) Preceding activities A 5 - B 10 - C 1 - D 8 B E 10 B F 9 B G 3 A,D H 7 A,D J 3 F K 8 E,H L 4 C,J (a) How long the project will take? (b) State the critical activities. (c)...
Following information is available about a project. Activity Activity Time (weeks) Immediate Predecessor(s) K 4 -...
Following information is available about a project. Activity Activity Time (weeks) Immediate Predecessor(s) K 4 - B 4 - C 5 - D 4 - E 6 K F 2 B,C,D G 4 E.F H 6 F Compute slack for each activity. Activity Slack K B C D E F G H
A future construction project has the following activity relationships and activity time estimates (in days): Activity...
A future construction project has the following activity relationships and activity time estimates (in days): Activity Immediate Predecessor To Tm Tp A None 4 5 6 B None 3 6 21 C B 1 4 7 D A 2 5 8 E C, D 3 9 27 F C 3 6 15 G E, F 2 4 6 H F, G 2 2 2 Leave 2-decimal if not exact, do not round up, for example, 4.3268... will be kept as...
Data for a project is given below: Activity Duration (months) Precedence Budget or Plnd. Cost Percent...
Data for a project is given below: Activity Duration (months) Precedence Budget or Plnd. Cost Percent Completed A 3.00 - 15000 1.00 B 1.00 A 5000 0.00 C 2.00 A 10000 1.00 D 3.00 A 21000 0.50 E 2.00 B,C 32000 0.00 F 1.00 C 5000 0.00 G 1.00 C 5500 0.00 The project started on June 1st. The project has a planned duration of 7 months. Data below are planned cost and actual cost (spent) from June to November:...
Prepare a table in Excel showing the time-phased budget for the project. Assume the budgeted cost...
Prepare a table in Excel showing the time-phased budget for the project. Assume the budgeted cost is linearly distributed over the duration of the activity, e.g., if the budgeted cost of a Task is $100 and the duration of the Task is 2 weeks, then budgeted cost/week=100/2= $50. All calculations should be done within the Excel spreadsheet. Task Predecessor Budget Cost ($) Duration (weeks) A - $              1,500 4 B A $              1,350 2 C A $              1,260 3 D...
Embassy Club Condominium, located on the west coast of Florida, is undertaking a summer renovation of...
Embassy Club Condominium, located on the west coast of Florida, is undertaking a summer renovation of its main building. The project is scheduled to begin May 1, and a September 1 (17-week) completion date is desired. The condominium manager identified the following renovation activities and their estimated times: Immediate Activity Predecessor Time A — 3 B — 4 C — 2 D A, B, C 2 E A, D 8 F C, D 7 G D, E 5 H F...
ADVERTISEMENT
Need Online Homework Help?

Get Answers For Free
Most questions answered within 1 hours.

Ask a Question
ADVERTISEMENT