Question

Given the following information for a project, answer the following questions: Activity Predecessor Activity Time (days)...

  1. Given the following information for a project, answer the following questions:

Activity

Predecessor

Activity Time (days)

A

-

6

B

-

8

C

A, B

5

D

B

4

E

C

7

F

C, D

3

G

D

6

H

E, F, G

5

  1. Fill in the following table.

Activity

ES

EF

LS

LF

Slack

CP

A

0

No

B

Yes

C

Yes

D

No

E

Yes

F

No

G

18

14

20

No

H

25

20

25

Yes

  1. Draw the network diagram using the 6-cell node.
  2. What is the critical path?
  3. What are the slack times (in days) for activities not on the CP?

Homework Answers

Know the answer?
Your Answer:

Post as a guest

Your Name:

What's your source?

Earn Coins

Coins can be redeemed for fabulous gifts.

Not the answer you're looking for?
Ask your own homework help question
Similar Questions
The following information is known about a project: a. Draw a network diagram b. Calculate the...
The following information is known about a project: a. Draw a network diagram b. Calculate the ES, EF, LS, LF and slack time and find the critical path for this project Activity Activity Time (days) Immediate Predecessor A 12 B 9 C 10 A D 10 A,B E 24 B F 10 A G 35 C H 40 D I 15 A J 4 E,G,H K 6 F,I,J
A future construction project has the following activity relationships and activity time estimates (in days): Activity...
A future construction project has the following activity relationships and activity time estimates (in days): Activity Immediate Predecessor To Tm Tp A None 4 5 6 B None 3 6 21 C B 1 4 7 D A 2 5 8 E C, D 3 9 27 F C 3 6 15 G E, F 2 4 6 H F, G 2 2 2 Leave 2-decimal if not exact, do not round up, for example, 4.3268... will be kept as...
Use the following data for problems 34, 35, and 36 Activity Activity Predecessor Time (days) A...
Use the following data for problems 34, 35, and 36 Activity Activity Predecessor Time (days) A -- 4 B -- 12 C A, B 15 D A, B 8 E A, B 6 F C, D, E 14 G C, D, E 3 H F, G 6 The expected completion time for the project above is? 27 days 68 days 47 days 30 days The critical path for the project is? B, C, F, H B, C, F, G, H...
1. A landscaping upgrade project consists of following activities. Times are given in weeks. Activity Immediate...
1. A landscaping upgrade project consists of following activities. Times are given in weeks. Activity Immediate Predecessor Activity Time A - 5 B A 8 C A 7 D - 6 E B, D, C 8 F D 3 G D 3 a. Draw the network diagram and find the ES, EF, LS, LF, and slack for each activity. b. Construct an early-start-date Gantt chart for the project. c. As a project manager, where would you focus your attention, given...
Activity Immediate Predecessor Optimistic Time Most-likely time Pessimistic Time A None 3 6 9 B A...
Activity Immediate Predecessor Optimistic Time Most-likely time Pessimistic Time A None 3 6 9 B A 3 5 7 C A 4 7 12 D B 4 8 10 E C 5 10 16 F D, E 3 4 5 G D, E 3 6 8 H F 5 6 10 I G 5 8 11 J H, I 3 3 3 (a). What is the expected time for each activity? (2 points) (b.) What is the variance for each...
Consider the following table: ACTIVITY    PREC. ACT.            TIME   ESTIMATES     (days)      &nbsp
Consider the following table: ACTIVITY    PREC. ACT.            TIME   ESTIMATES     (days)          to           tml                tp                                 te     A                     -----                        1                      2                      3                           B                      A                           2                      4                      6     C                      B                            1                      4                      7     D                      B                            3                      4                      5     E                      C                            1                      3                      5     F                      D, E                       2                      3                      4 1) Construct a PERT network. [NOTE: This is the most crucial part of the exercise. Make sure you have the correct network before proceeding to the next sections.] 2) By using ES, EF, LF, LS, find the slack of each activity and the critical path. 3) Find the completion time and the standard deviation (σ) for the project— round off the standard deviation to the nearest...
The next set of questions use the following example: A network consists of the activities in...
The next set of questions use the following example: A network consists of the activities in the following list. Times are given in weeks. Activity Preceding Time A -- 8 B -- 3 C A 7 D A,B 3 E C 4 F D 6 Draw the network diagram. Calculate the ES, EF, LS, LF, and Slack for each activity. Find the total project completion time. What is the slack of activity B? 8 0 3 2 7
The following activities are part of a project to be scheduled using CPM: ACTIVITY IMMEDIATE PREDECESSOR...
The following activities are part of a project to be scheduled using CPM: ACTIVITY IMMEDIATE PREDECESSOR TIME (WEEKS) A — 7 B A 6 C A 2 D C 4 E B D 3 F D 4 G E F 6 a. Draw the network b. What is the critical path c. How many weeks will it take to complete the project d. Identify the early start, early finish, late start, and late finish for each activity in the project...
The next set of questions use the following example: A network consists of the activities in...
The next set of questions use the following example: A network consists of the activities in the following list. Times are given in weeks. CAN ONLY BE ONE OF THE OPTIONS it's not 5 I tried that. Activity Preceding Time A -- 8 B -- 3 C A 7 D A,B 3 E C 4 F D 6 Draw the network diagram. Calculate the ES, EF, LS, LF, and Slack for each activity. Find the total project completion time. What...
Assume that activity F has the following times: Early start time (ES) = 7 days Early...
Assume that activity F has the following times: Early start time (ES) = 7 days Early finish time (EF) = 13 days Latest start time (LS) = 15 days Latest finish time (LF) = 21 days Which of the following statements is TRUE about activity F? Activity F takes 14 days to complete Activity F is on the critical path Activity F has 8 days of slack time Activity F is the first activity of the project None of the...
ADVERTISEMENT
Need Online Homework Help?

Get Answers For Free
Most questions answered within 1 hours.

Ask a Question
ADVERTISEMENT