A future construction project has the following activity relationships and activity time estimates (in days):
Activity | Immediate Predecessor | To | Tm | Tp |
A | None | 4 | 5 | 6 |
B | None | 3 | 6 | 21 |
C | B | 1 | 4 | 7 |
D | A | 2 | 5 | 8 |
E | C, D | 3 | 9 | 27 |
F | C | 3 | 6 | 15 |
G | E, F | 2 | 4 | 6 |
H | F, G | 2 | 2 | 2 |
Answer Table:
Activity | Immediate Predecessor | To | Tm | Tp | Te | Variance | ES | EF | LS | LF | Slack |
A | None | 4 | 5 | 6 | 5 | 0.11 | 0 | 5 | 2 | 7 | 2 |
B | None | 3 | 6 | 21 | 8 | 9.00 | 0 | 8 | 0 | 8 | 0 |
C | B | 1 | 4 | 7 | 4 | 1.00 | 8 | 12 | 8 | 12 | 0 |
D | A | 2 | 5 | 8 | 5 | 1.00 | 5 | 10 | 7 | 12 | 2 |
E | C, D | 3 | 9 | 27 | 11 | 16.00 | 12 | 23 | 12 | 23 | 0 |
F | C | 3 | 6 | 15 | 7 | 4.00 | 12 | 19 | 16 | 23 | 4 |
G | E, F | 2 | 4 | 6 | 4 | 0.44 | 23 | 27 | 23 | 27 | 0 |
H | F, G | 2 | 2 | 2 | 2 | 0.00 | 27 | 29 | 27 | 29 | 0 |
Expected Finish time (Te) of C = 4
Activity variance of activity D = 1
Network:
Critical path = BCEGH
Expected project completion time = 29 days
Variance of the project completion time = Sum of variances of critical activities = 26.44
LS time of activity F is 16 days
Slack time of activity D = 2 days
Explanation:
For each activity:
Expected time, Te = (To+4*Tm+Tp)/6
Variance = (Tp - To)/6
ES, EF, LS, LF of each activity
ES or Earliest Start Time = EF or Earliest Finish time of the predecessor of the corresponding activity
if an activity has more than 1 predecessor than the maximum of the EF of the predecessors is considered as the ES for the corresponding activity.
EF = ES+ Expected time
The ES and EF are calculated from the start to end activities of the network.
Example: Activities A and B do not have any predecessors, hence can be started at 0 time. So the ES is 0 for both of them.
Activity C has one predecessor which is B. So, the ES = EF of B = 8
E has two predecessors, C and D.The ES of activity E = Max of (EF of Activity C and D) = MAX(12,10) = 12
LS or Late Start time = LF or Late Finish Time - Duration of the corresponding project.
LF = LS of the successor
The LF and LS are calculated from the end to start the activity. Hence the activity with the highest EF becomes the end activity and the EF becomes the LF.
If an activity has more than one successor, the minimum of the LS values is considered for the LF.
Example: Activity H has the highest EF time. This means this activity finishes last. Hence the latest finish for the project is 29 days.
LF of Activity H = 29 days
Activity H has two predecessors F and G. Hence the LS of H becomes the LF of both F and G which is 29-expected time of H = 29-2 = 27
But Activity F is the predecessor of two activities G and H. So, the LF = Min (LS of G, LS of H) = Min (23,27) = 23
Slack = LF - EF or LS - ES
If slack is 0, the activity is a critical activity and all the zero slack activities constitute the critical path.
Get Answers For Free
Most questions answered within 1 hours.