Question

A future construction project has the following activity relationships and activity time estimates (in days): Activity...

A future construction project has the following activity relationships and activity time estimates (in days):

Activity Immediate Predecessor To Tm Tp
A None 4 5 6
B None 3 6 21
C B 1 4 7
D A 2 5 8
E C, D 3 9 27
F C 3 6 15
G E, F 2 4 6
H F, G 2 2 2
  • Leave 2-decimal if not exact, do not round up, for example, 4.3268... will be kept as 4.32
  1. Please calculate the “expected finish time” and “variance” for each activity. What is the expected finish time of activity C?   What is the activity variance of activity D?  
  2. Use “expected finish time” of each activity to construct the network. What is the critical path of the project? (no space permitted between letters, acceptable format: ABCD) What is the expected project completion time in days?  What is the variance of project completion time?  
  3. Use “expected finish time” to decide ES, EF, LS, LF of each activity. What is the LS time of activity F?   What is the slack time of activity D?

Homework Answers

Answer #1

Answer Table:

Activity Immediate Predecessor To Tm Tp Te Variance ES EF LS LF Slack
A None 4 5 6 5 0.11 0 5 2 7 2
B None 3 6 21 8 9.00 0 8 0 8 0
C B 1 4 7 4 1.00 8 12 8 12 0
D A 2 5 8 5 1.00 5 10 7 12 2
E C, D 3 9 27 11 16.00 12 23 12 23 0
F C 3 6 15 7 4.00 12 19 16 23 4
G E, F 2 4 6 4 0.44 23 27 23 27 0
H F, G 2 2 2 2 0.00 27 29 27 29 0

Expected Finish time (Te) of C = 4

Activity variance of activity D = 1

Network:

Critical path = BCEGH

Expected project completion time = 29 days

Variance of the project completion time = Sum of variances of critical activities = 26.44

LS time of activity F is 16 days

Slack time of activity D = 2 days

Explanation:

For each activity:

Expected time, Te = (To+4*Tm+Tp)/6

Variance = (Tp - To)/6

ES, EF, LS, LF of each activity

ES or Earliest Start Time = EF or Earliest Finish time of the predecessor of the corresponding activity

if an activity has more than 1 predecessor than the maximum of the EF of the predecessors is considered as the ES for the corresponding activity.

EF = ES+ Expected time

The ES and EF are calculated from the start to end activities of the network.

Example: Activities A and B do not have any predecessors, hence can be started at 0 time. So the ES is 0 for both of them.

Activity C has one predecessor which is B. So, the ES = EF of B = 8

E has two predecessors, C and D.The ES of activity E = Max of (EF of Activity C and D) = MAX(12,10) = 12

LS or Late Start time = LF or Late Finish Time - Duration of the corresponding project.

LF = LS of the successor

The LF and LS are calculated from the end to start the activity. Hence the activity with the highest EF becomes the end activity and the EF becomes the LF.

If an activity has more than one successor, the minimum of the LS values is considered for the LF.

Example: Activity H has the highest EF time. This means this activity finishes last. Hence the latest finish for the project is 29 days.

LF of Activity H = 29 days

Activity H has two predecessors F and G. Hence the LS of H becomes the LF of both F and G which is 29-expected time of H = 29-2 = 27

But Activity F is the predecessor of two activities G and H. So, the LF = Min (LS of G, LS of H) = Min (23,27) = 23

Slack = LF - EF or LS - ES

If slack is 0, the activity is a critical activity and all the zero slack activities constitute the critical path.

Know the answer?
Your Answer:

Post as a guest

Your Name:

What's your source?

Earn Coins

Coins can be redeemed for fabulous gifts.

Not the answer you're looking for?
Ask your own homework help question
Similar Questions
Consider the following table: ACTIVITY    PREC. ACT.            TIME   ESTIMATES     (days)      &nbsp
Consider the following table: ACTIVITY    PREC. ACT.            TIME   ESTIMATES     (days)          to           tml                tp                                 te     A                     -----                        1                      2                      3                           B                      A                           2                      4                      6     C                      B                            1                      4                      7     D                      B                            3                      4                      5     E                      C                            1                      3                      5     F                      D, E                       2                      3                      4 1) Construct a PERT network. [NOTE: This is the most crucial part of the exercise. Make sure you have the correct network before proceeding to the next sections.] 2) By using ES, EF, LF, LS, find the slack of each activity and the critical path. 3) Find the completion time and the standard deviation (σ) for the project— round off the standard deviation to the nearest...
Given the following information for a project, answer the following questions: Activity Predecessor Activity Time (days)...
Given the following information for a project, answer the following questions: Activity Predecessor Activity Time (days) A - 6 B - 8 C A, B 5 D B 4 E C 7 F C, D 3 G D 6 H E, F, G 5 Fill in the following table. Activity ES EF LS LF Slack CP A 0 No B Yes C Yes D No E Yes F No G 18 14 20 No H 25 20 25 Yes Draw...
Assume that activity F has the following times: Early start time (ES) = 7 days Early...
Assume that activity F has the following times: Early start time (ES) = 7 days Early finish time (EF) = 13 days Latest start time (LS) = 15 days Latest finish time (LF) = 21 days Which of the following statements is TRUE about activity F? Activity F takes 14 days to complete Activity F is on the critical path Activity F has 8 days of slack time Activity F is the first activity of the project None of the...
Activity Immediate Predecessor Optimistic Time Most-likely time Pessimistic Time A None 3 6 9 B A...
Activity Immediate Predecessor Optimistic Time Most-likely time Pessimistic Time A None 3 6 9 B A 3 5 7 C A 4 7 12 D B 4 8 10 E C 5 10 16 F D, E 3 4 5 G D, E 3 6 8 H F 5 6 10 I G 5 8 11 J H, I 3 3 3 (a). What is the expected time for each activity? (2 points) (b.) What is the variance for each...
Consider a project having the following six activities:                                  
Consider a project having the following six activities:                                                      Immediate                                                  Max        Crash cost             Activity                           Predecessors           Time (weeks)             Crash*    per week                   A                                none                                    6                          6                N/A                   B                                none                                    5                          2               $500                   C                                A                                       3                          2             $1000                   D                                A, B                                    4                          2             $2000                   E                                 C, D                                    5                          2             $1250                   F                                D                                       6                          2             $1000                                                                                                 *Shortest possible time for the task Draw the project network and list the...
The following information is known about a project: a. Draw a network diagram b. Calculate the...
The following information is known about a project: a. Draw a network diagram b. Calculate the ES, EF, LS, LF and slack time and find the critical path for this project Activity Activity Time (days) Immediate Predecessor A 12 B 9 C 10 A D 10 A,B E 24 B F 10 A G 35 C H 40 D I 15 A J 4 E,G,H K 6 F,I,J
1. A landscaping upgrade project consists of following activities. Times are given in weeks. Activity Immediate...
1. A landscaping upgrade project consists of following activities. Times are given in weeks. Activity Immediate Predecessor Activity Time A - 5 B A 8 C A 7 D - 6 E B, D, C 8 F D 3 G D 3 a. Draw the network diagram and find the ES, EF, LS, LF, and slack for each activity. b. Construct an early-start-date Gantt chart for the project. c. As a project manager, where would you focus your attention, given...
Given the following network and activity time estimates, determine earliest and latest activity times, slack, the...
Given the following network and activity time estimates, determine earliest and latest activity times, slack, the expected project completion time and variance, and the probability that the project will be completed in 28 days or less. TIME ESTIMATES (DAYS) ACTIVITY ACTIVITY PREDECESSOR a m b A - 5  8 17 B - 7 10 13 C A 3  5  7 D A 1  3  5 E B, C 4  6  8 F B, C 3  3  3 G D,E 3  ...
Use the following data for problems 34, 35, and 36 Activity Activity Predecessor Time (days) A...
Use the following data for problems 34, 35, and 36 Activity Activity Predecessor Time (days) A -- 4 B -- 12 C A, B 15 D A, B 8 E A, B 6 F C, D, E 14 G C, D, E 3 H F, G 6 The expected completion time for the project above is? 27 days 68 days 47 days 30 days The critical path for the project is? B, C, F, H B, C, F, G, H...
Given is a CPM project network diagram as shown below. Activity Start A B C D...
Given is a CPM project network diagram as shown below. Activity Start A B C D E F G H End days 0 2 6 8 3 4 2 3 2 0 a) The Project Completion time = ___ days. b) The Earliest Start time, ES, of Activity G = ____ days. c) The Latest Finish time, LF, of Acitivity C = ____ days. d) The critical activities are = ____ (ex. Fill in answer as: ABCD)
ADVERTISEMENT
Need Online Homework Help?

Get Answers For Free
Most questions answered within 1 hours.

Ask a Question
ADVERTISEMENT