Question

Data for a project is given below: Activity Duration (months) Precedence Budget or Plnd. Cost Percent...

Data for a project is given below:

Activity

Duration

(months)

Precedence

Budget or Plnd. Cost

Percent

Completed

A

3.00

-

15000

1.00

B

1.00

A

5000

0.00

C

2.00

A

10000

1.00

D

3.00

A

21000

0.50

E

2.00

B,C

32000

0.00

F

1.00

C

5000

0.00

G

1.00

C

5500

0.00

The project started on June 1st. The project has a planned duration of 7 months.

Data below are planned cost and actual cost (spent) from June to November:

                        Planned                    Actual

Month                        Cost                          Cost

June               5000                           8000

July                5000                           8000

Aug                5000                           5000

Sept               5000                           5000

Oct                  12000                         12000

Nov                23000                         12000

Compute cost and schedule variances.

Compute critical ratio.

Based on current cost performance level, what is the estimated cost in completing the project?

Based on current schedule performance level, how much more time (in months) is needed to complete the project?

Homework Answers

Answer #1

Cost Variances = EV-AC

Results are tabled below:

Thus, we need = 7-5 = 2 more months to complete the project.

Know the answer?
Your Answer:

Post as a guest

Your Name:

What's your source?

Earn Coins

Coins can be redeemed for fabulous gifts.

Not the answer you're looking for?
Ask your own homework help question
Similar Questions
#3) Planned duration of a project is 28 weeks. Budget at completion for the project is...
#3) Planned duration of a project is 28 weeks. Budget at completion for the project is $525,000. The project is in its 25th week. The actual cost (thus far) is $270,000. At this point in the plan, the planned cost was expected to be $261,000. For the work performed to date, the earned value is estimated at $272,000. Compute the following for the project (10 points) a) Cost variance. b) Schedule variance. c) If rest of the project is assumed...
Consider the following data: Initiation Planning Analysis Design Implementation Testing Closure # Months estimated to complete...
Consider the following data: Initiation Planning Analysis Design Implementation Testing Closure # Months estimated to complete 2 6 8 6 18 6 2 Budgeted Cost $ 2000 6000 12000 12000 80000 36000 4000 % work completed 100% 100% 80% 0% 0% 0% 0% Actual Cost $ 4000 8000 16000 20000 We are tracking the amount of work completed after 22 months. For the data given, find the Schedule Performance Index at the end of 22 months. a. 0.47 b. 0.55...
The figure below depicts the schedule for a small project. The budgeted cost is shown within...
The figure below depicts the schedule for a small project. The budgeted cost is shown within the schedule bar for each activity. For the sake of simplicity, assume costs are distributed evenly throughout an activity's duration. For example, Activity A will take four weeks and has a total budgeted cost of $4,000. Consequently, expected expenditures for A will be $1,000 per week. In contrast, Activity B will cost $2,000 per week. Precedence relationships are as follows: A must precede B...
Earned Value Management (EVM) is a project management technique for measuring project performance (schedule, cost mainly)...
Earned Value Management (EVM) is a project management technique for measuring project performance (schedule, cost mainly) and progress in an objective manner in terms of work achieved (Value): The data identified below was listed in a project’s status report. At time of status report: Planned Value of work (PV) = $70,000 Earned Value of work performed (EV) = $50,000 Actual Cost of work performed (AC) = $75,000 Original Planning: Budgeted cost At Completion (BAC) = $110,000 Original length of the...
Suppose that demand data for widgets made by XYZ Inc. is given below. Using an appropriate...
Suppose that demand data for widgets made by XYZ Inc. is given below. Using an appropriate method (level , chase or mixed), plan the production (i.e. specify the production quantities and complete the table below) such that the total cost is made as small as possible. Regular time production capacity is 7000 units per month. They can also produce in overtime up to 5000 units per month. There is no other method of production and the cost of regular time...
Given the following data, develop MRP tables and indicate the Planned order releases for all items....
Given the following data, develop MRP tables and indicate the Planned order releases for all items. A is an MPS item. A needs 4 C's, 2 F’s and 5 G’s. F needs 4 C’s and G needs 2 C’s. (I eliminated scheduled receipts since the problem did not have scheduled receipts.) Period 6 7 8 GR-A 0 100 900 On hand inventory for all items is 300 and lead time for A is 1 period, and LT for all other...
ADVERTISEMENT
Need Online Homework Help?

Get Answers For Free
Most questions answered within 1 hours.

Ask a Question
ADVERTISEMENT