A partially solved PERT problem is detailed in the table below. Times are given in weeks.
Activity |
Immediate Predecessor(s) |
Optimistic |
Most Likely |
Pessimistic |
A |
-- |
8 |
10 |
15 |
B |
-- |
7 |
8 |
9 |
C |
A |
5 |
6 |
10 |
D |
A |
3 |
3 |
3 |
E |
B,D |
1 |
5 |
9 |
F |
B,D |
4 |
7 |
10 |
G |
C |
3 |
8 |
10 |
H |
E |
5 |
7 |
9 |
I |
E |
4 |
5 |
8 |
J |
F |
2 |
5 |
8 |
K |
H, I |
1 |
3 |
6 |
a) Calculate the expected duration (D), and variance of each activity.
b) Calculate ES, EF, LS, LF, S) for each activity.
ET |
Variance |
ES |
EF |
LS |
LF |
S |
|
A |
|||||||
B |
|||||||
C |
|||||||
D |
|||||||
E |
|||||||
F |
|||||||
G |
|||||||
H |
|||||||
I |
|||||||
J |
|||||||
K |
c) Which activities form the critical path?
A) ADEHK
B) ACG
C) ABEK
D) ADEIK
E) BFJ
F) BEHK
d) What is the estimated time of the critical path? ( …… ) weeks |
||
e) If the project is due to be completed in 35 weeks, what is the probability that the project will be completed on the due date? ( … %) ? |
||
f) If the project manager wants at least a 95% probability that the project will be completed on the due date, what is the shortest project due date that will satisfy the manager? ( …… ) weeks |
||
g) Which activity (ies) can be delayed 1.67 weeks without impacting the expected project completion date? A) I B) A C) C D) F and G E) I and J
|
||
h) How many week(s) can you delay the activity J, without impacting the expected project completion date? ( ….. ) weeks |
Get Answers For Free
Most questions answered within 1 hours.