Question

Prepare a table in Excel showing the time-phased budget for the project. Assume the budgeted cost...

Prepare a table in Excel showing the time-phased budget for the project. Assume the budgeted cost is linearly distributed over the duration of the activity, e.g., if the budgeted cost of a Task is $100 and the duration of the Task is 2 weeks, then budgeted cost/week=100/2= $50.
All calculations should be done within the Excel spreadsheet.

Task Predecessor Budget Cost ($) Duration (weeks)
A - $              1,500 4
B A $              1,350 2
C A $              1,260 3
D A $                 950 2
E C, D $              1,650 5
F B, E $              1,200 4
G E $                 700 2
H F, G $              1,770 3

Homework Answers

Answer #1

The Fomula used is =QUOTIENT(E2,G2)

Know the answer?
Your Answer:

Post as a guest

Your Name:

What's your source?

Earn Coins

Coins can be redeemed for fabulous gifts.

Not the answer you're looking for?
Ask your own homework help question
Similar Questions
Using the following information about work package budgets, complete the overall time-phased budget for the following...
Using the following information about work package budgets, complete the overall time-phased budget for the following project. Which weeks have the greatest budget expense? TASK Budget Week 1 Week 2 Week 3 Week 4 Week 5 Week 6 Week 7 Week 8 A 5 3 2 B 8 1 4 3 1 C 12 2 7 3 D 7 3 3 1 E 14 5 5 2 2 F 6 1 2 3 Plan 52 4 8 Cumulative 4 12
Use the following data for question below. Activity Normal Time (weeks) Crash Time (weeks) Normal Cost...
Use the following data for question below. Activity Normal Time (weeks) Crash Time (weeks) Normal Cost Total Cost with Crashing Pred 1 Pred 2 A 10 7 $200 $400 B 15 10 $250 $600 C 13 8 $600 $1,500 A B D 14 10 $800 $1,200 A B E 8 4 $1,000 $3,000 C D F 12 6 $1,200 $1,800 C D G 7 6 $700 $1,400 E F H 5 3 $500 $900 E F If the project must...
Consider the table below, which includes time and activity data for a Small IT Project. All...
Consider the table below, which includes time and activity data for a Small IT Project. All duration estimates or estimated times are in days. Perform a critical path analysis for this project. Activity Duration (Days) Predecessor A 8 - B 10 A C 18 A D 4 A E 28 B, D F 2 C, E G 32 E H 18 B I 12 F J 2 H, G, I Draw a network diagram representing the project. MS PowerPoint or...
Problem #5 An IT project requires 6 activities. The table below displays the expected time and...
Problem #5 An IT project requires 6 activities. The table below displays the expected time and budgeted cost for each activity. Activity Expected time (weeks) Budgeted Cost Immediate Predecessors A 3 $2,000 None B 4 $6,000 None C 2 $7,000 A D 5 $9,000 B E 3 $3,000 C F 6 $8,000 B,D Develop a budget for the 15 weeks of the project using LS times.
Ralph wants to build a new two (2) car garage. The contractor Ralph hired provided the...
Ralph wants to build a new two (2) car garage. The contractor Ralph hired provided the following schedule and cost estimate. What is the budget at completion (BAC) for Ralph’s garage? At the end of week 1, the contractor completed 80% of the footing, framing, and siding. He spent 3,000 on concrete, lumber and vinyl siding. He also paid 1,500 in wages to laborers to complete the footing, framing, and siding. what is the earned value (EV) for Task A...
London Fletcher of Fabriscan Diagnostic, is the project manager. He measured the following information with commutative...
London Fletcher of Fabriscan Diagnostic, is the project manager. He measured the following information with commutative completed times for four periods of the project. Completed% Activity ID Activity Predecessors Estimated Duration(Weeks) Budget ($) Actual Spend ($) 1 2 3 4 Crash time Crash cost$ A 7          7,000                       9,000 20 40 100 100 6             8,000 B A 2          5,000                       5,000 20 60 100 100 1             7,000 C A 4          9,000                       6,000 0 40...
Do the following crashing problem “from scratch” Develop the time reduction and cost per unit time...
Do the following crashing problem “from scratch” Develop the time reduction and cost per unit time columns in the table. Units: Time is in days, cost is in $. Activity Immediate predecessor(s) Time Cost Crash Time Crash Cost Time Reduction Cost to Crash A -- 10 5000 10 5000 B A 12 1200 11 1300 C A 11 3600 9 4800 D B 5 300 4 600 E C 8 1000 6 2000 F E 9 2400 7 5400 G...
1. It is time for Jung So Min Corp. to begin its annual budget preparation for...
1. It is time for Jung So Min Corp. to begin its annual budget preparation for its upcoming fiscal year, which ends on December 31, 2021. They are in need of temporary assistance in their accounting office, and have hired you to carry out the task of preparing the budgets. Jung So Min prepares quarterly budgets, and then from this information prepares an annual budget. To assist you in this task, Jung So Min has gathered the following information: 1)...
Mega Mart Store is a discount department store badly in need of renovation. To avoid loss...
Mega Mart Store is a discount department store badly in need of renovation. To avoid loss of sales and disruption of customer shopping habits, Mega Mart wants to complete this renovation without closing the store itself, by temporarily co-locating goods from one area of the store into another, creating open spaces for renovation and re-occupation. Mega Mart is divided into four basic areas of goods: Clothing, Electronics, House Wares and Foodstuffs. Each of these areas will need to be temporarily...
Sales, Production, Direct Materials Purchases, and Direct Labor Cost Budgets The budget director of Gourmet Grill...
Sales, Production, Direct Materials Purchases, and Direct Labor Cost Budgets The budget director of Gourmet Grill Company requests estimates of sales, production, and other operating data from the various administrative units every month. Selected information concerning sales and production for July is summarized as follows: a. Estimated sales for July by sales territory: Maine: Backyard Chef 310 units at $700 per unit Master Chef 150 units at $1,200 per unit Vermont: Backyard Chef 240 units at $750 per unit Master...
ADVERTISEMENT
Need Online Homework Help?

Get Answers For Free
Most questions answered within 1 hours.

Ask a Question
ADVERTISEMENT