Question

Consider the table below, which includes time and activity data for a Small IT Project. All...

Consider the table below, which includes time and activity data for a Small IT Project. All duration estimates or estimated times are in days. Perform a critical path analysis for this project.

Activity

Duration (Days)

Predecessor

A

8

-

B

10

A

C

18

A

D

4

A

E

28

B, D

F

2

C, E

G

32

E

H

18

B

I

12

F

J

2

H, G, I

  1. Draw a network diagram representing the project. MS PowerPoint or Visio are good tools for this task. (10 points)

  1. Identify and list all of the paths through the network diagram and note how long they are. (4 points)
  1. What is the timeline within which the project can earliest be completed? (3 points)

  1. If D takes 7 days, what will be the impact to the project and the critical path? (2 points)

  1. If G takes an additional 7 days, what will be the impact to the project and the critical path? (2 points)

Homework Answers

Answer #1

As per given table the network diagram is as follows:

And also represented list of possible paths and their costs:

What is the timeline within which the project can earliest be completed?

Answer: 38 days

The shortest path is A-->B-->H-->J. which takes 38 days.

If D takes 7 days, what will be the impact to the project and the critical path?

The shortest path which the project can complete is : A-->B-->H-->J

It does not contain D. So even if D takes 7 days, there will be no impact on project completeion time.

The critical path is nothing but the longest path: A-->B-->E-->G-->J

It does not contain D. So even if D takes 7 days, there will be no impact on critical path.

If G takes an additional 7 days, what will be the impact to the project and the critical path?

If G takes an additional 7 days, the value of G will be = 32+7 = 39

The shortest path which the project can complete is : A-->B-->H-->J

It does not contain G. So even if G takes an additional 7 days, there will be no impact on project completeion time.

The critical path is nothing but the longest path: A-->B-->E-->G-->J

It contains 'G'. So if G takes an additional 7 days, the cost of critical path will change to = 87.

Know the answer?
Your Answer:

Post as a guest

Your Name:

What's your source?

Earn Coins

Coins can be redeemed for fabulous gifts.

Not the answer you're looking for?
Ask your own homework help question
Similar Questions
Given the following information for a project, answer the following questions: Activity Predecessor Activity Time (days)...
Given the following information for a project, answer the following questions: Activity Predecessor Activity Time (days) A - 6 B - 8 C A, B 5 D B 4 E C 7 F C, D 3 G D 6 H E, F, G 5 Fill in the following table. Activity ES EF LS LF Slack CP A 0 No B Yes C Yes D No E Yes F No G 18 14 20 No H 25 20 25 Yes Draw...
1. Given is a PERT project network diagram as shown below: Activity Start A B C...
1. Given is a PERT project network diagram as shown below: Activity Start A B C D E F G H I J K End Time 0 18 24 21 38 28 34 22 20 34 34 16 0    a) The Project Completion time =   b) The Earliest Start time, ES, of Activity F =   c) The Earliest Start time, ES, of Activity K =   d) The Latest Start time, LS, of Activity E =   e) The non-critical activities...
ACTIVITY DESCRIPTION ACTIVITY PREDECESSOR A Legal and regulatory Authority - B Site Solicitation A C Site...
ACTIVITY DESCRIPTION ACTIVITY PREDECESSOR A Legal and regulatory Authority - B Site Solicitation A C Site Selection and Preparation B D Drilling, Engineering and other Works B, C E Installation of other Equipment, Testing, and Analysis D F Project Commission and Handing over to the community E G Demonstrate safety usage and practices E, F H Preclosure safety analysis F, G 1. create an activity precedence diagram showing the network logic for each project activity you have identified; 2.    prepare...
Given is a CPM project network diagram as shown below. Activity Start A B C D...
Given is a CPM project network diagram as shown below. Activity Start A B C D E F G H End days 0 2 6 8 3 4 2 3 2 0 a) The Project Completion time = ___ days. b) The Earliest Start time, ES, of Activity G = ____ days. c) The Latest Finish time, LF, of Acitivity C = ____ days. d) The critical activities are = ____ (ex. Fill in answer as: ABCD)
Given is a CPM project network diagram as shown below. Activity Start A B C D...
Given is a CPM project network diagram as shown below. Activity Start A B C D E F G H End days 0 2 6 8 3 4 2 3 2 0 a) The Project Completion time = ____ days. b) The Earliest Start time, ES, of Activity G = ____ days. c) The Latest Finish time, LF, of Acitivity C = ____ days. d) The critical activities are = ____ (ex. Fill in answer as: ABCD)
The following information is known about a project: a. Draw a network diagram b. Calculate the...
The following information is known about a project: a. Draw a network diagram b. Calculate the ES, EF, LS, LF and slack time and find the critical path for this project Activity Activity Time (days) Immediate Predecessor A 12 B 9 C 10 A D 10 A,B E 24 B F 10 A G 35 C H 40 D I 15 A J 4 E,G,H K 6 F,I,J
Draw the Activity-on-Arrow (AoA) and Activity-on-Node (AoN) networks using the activity dependency table given below and...
Draw the Activity-on-Arrow (AoA) and Activity-on-Node (AoN) networks using the activity dependency table given below and find the critical path(s) Activities Predecessor duration A - 2 B - 10 C A 9 D A,B 7 E A,B 9 F B 5 G C 10 H D,E 1 I D,E,F 2 J F 7 K C,H,I 2 L I,J 2 M I 1 N G,K 5
Consider the following information for a project to add a drive-thru window at Crestview Bank.       Activity...
Consider the following information for a project to add a drive-thru window at Crestview Bank.       Activity Activity Time​ (weeks) Immediate​ Predecessor(s) A 6 − B 1 − C 9 − D 3 ​A, B E 6 B F 4 ​D, C G 5 ​E, C H 9 ​F, G b. Specify the critical path. The critical path is _____ and the project duration is_____ c. Calculate the slack for activities A and D.
Use the following data for problems 34, 35, and 36 Activity Activity Predecessor Time (days) A...
Use the following data for problems 34, 35, and 36 Activity Activity Predecessor Time (days) A -- 4 B -- 12 C A, B 15 D A, B 8 E A, B 6 F C, D, E 14 G C, D, E 3 H F, G 6 The expected completion time for the project above is? 27 days 68 days 47 days 30 days The critical path for the project is? B, C, F, H B, C, F, G, H...
Activity Duration (days) Predecessors Resources A 5 - Jane B 7 A Marry, Kate C 3...
Activity Duration (days) Predecessors Resources A 5 - Jane B 7 A Marry, Kate C 3 A Dennis D 3 B Kate E 8 D William F 10 C Sam G 8 F William H 3 E, G Jane 1. Draw the network diagram and indicate the critical path. 2. Draw the network diagram by specifying Early Start, Early Finish, Late Start, Late Finish, and slacks. 3. Indicate all the activities, duration, start and finish dates, predecessors, resources in a...