Question

A project manager, in preparation for the construction of roads, has identified the activities and their...

A project manager, in preparation for the construction of roads, has identified the activities and their durations to prepare a difficult stretch of motorway (as in the following table).

Activity

Duration (days)

Preceding activities

A

5

-

B

10

-

C

1

-

D

8

B

E

10

B

F

9

B

G

3

A,D

H

7

A,D

J

3

F

K

8

E,H

L

4

C,J

(a) How long the project will take?

(b) State the critical activities.

(c) If activity A is delayed for 10 days, what is the effect on the project duration?

Homework Answers

Answer #1

a)

AON:

Path and Duration are:

AG = 5+3 = 8

AHK = 5+7+8 = 20

BDG = 10+8+3 = 21

BDHK = 10+8+7+8 = 33

BEK = 10+10+8 = 28

BFJL = 10+9+3+4 = 26

CL = 1+4 = 5

The project time will be equal to highest time taken by a path which is 33 days

b)

Critical activities are those which are in critical path. Critical path is one with the highest time

Hence, critical activities are B,D,H,K

c)

Activity A is part of two path AG and AHK with time of 8 and 20 days respectively. Even if A is delayed by 10 days, the time for these path will change to 18 and 30 days. However, it is still less than time of critical path. So, it will have no effect on the project duration

Know the answer?
Your Answer:

Post as a guest

Your Name:

What's your source?

Earn Coins

Coins can be redeemed for fabulous gifts.

Not the answer you're looking for?
Ask your own homework help question
Similar Questions
Given below are the durations of and the precedence relationships among the activities required to compute...
Given below are the durations of and the precedence relationships among the activities required to compute a project. 1) construct an AOA network of the project 2)what is the critical path? determine the expected duration of the project. 3)compute the standard deviation of the critical path Duration(days) Activity pre-decessor(s) a m b A - 4 7 12 B A 6 9 13 C A 5 7 9 D B,C 3 5 8 E B 7 8 10 F A 2...
A project has 6 activities (labelled A-F), with the following terms: Activity A and B can...
A project has 6 activities (labelled A-F), with the following terms: Activity A and B can start at the same time, however Activity C can only start once Activity A ends Activity D can only start once Activity B and Activity C ends Activity E and Activity F can only start once Activity D ends The following table shows Durations for each activity Activity Duration (weeks) A 5 B 4 C 2 D 7 E 3 F 2 a. Draw...
The project manager of a task force planning the construction of a domed stadium had hoped...
The project manager of a task force planning the construction of a domed stadium had hoped to be able to complete construction prior to the start of the next college football season. After reviewing construction time estimates, it now appears that a certain amount of crashing will be needed to ensure project completion before the season opener. Given the following time and cost estimates, determine a minimum-cost crashing schedule that will shave five weeks off the project length. Note: No...
Francisco is planning a vacation to Germany. A variety of activities must be completed before his...
Francisco is planning a vacation to Germany. A variety of activities must be completed before his departure. The following table describes the relationships between these activities: Immediate Activity Predecessors A - B - C - D A, B E C F D, E G E H F, G I F J I, H Francisco was also able to estimate the activity times as shown in the table below: Activity Time (Days) A 3 B 4 C 5 D 3 E...
Use the following activities and their three duration estimates (in days) to do the following Determine...
Use the following activities and their three duration estimates (in days) to do the following Determine the expected duration of the project – use 2 decimals when determining the duratio Path Activity Optimistic Most Likely Pessimistic a-b-c A 4 5 6 B 7 8 10 C 3 5 9 d-e-f D 7 8 11 E 2 3 4 f 1 4 6
A partially solved PERT problem is detailed in the table below. Times are given in weeks....
A partially solved PERT problem is detailed in the table below. Times are given in weeks. Activity Immediate Predecessor(s) Optimistic Most Likely Pessimistic A -- 8 10 15 B -- 7 8 9 C A 5 6 10 D A 3 3 3 E B,D 1 5 9 F B,D 4 7 10 G C 3 8 10 H E 5 7 9 I E 4 5 8 J F 2 5 8 K H, I 1 3 6 a)...
Activity Completion (Days) Immediate Precedence A. Architectural Design 3 - B. Clearing of Land 6 A...
Activity Completion (Days) Immediate Precedence A. Architectural Design 3 - B. Clearing of Land 6 A C. Fencing of project site 7 A D. Digging of foundation 5 A E. Completion of foundation work 13 B,C F. Raising of pillars and block work. 8 C,D G. Roofing 11 D,F H. Furnishing of the cathedral 6 G,E a. Redraw the network diagram for the construction of the National Cathedral by using the above information provided in the table to complete the...
ACTIVITY DESCRIPTION ACTIVITY PREDECESSOR A Legal and regulatory Authority - B Site Solicitation A C Site...
ACTIVITY DESCRIPTION ACTIVITY PREDECESSOR A Legal and regulatory Authority - B Site Solicitation A C Site Selection and Preparation B D Drilling, Engineering and other Works B, C E Installation of other Equipment, Testing, and Analysis D F Project Commission and Handing over to the community E G Demonstrate safety usage and practices E, F H Preclosure safety analysis F, G 1. create an activity precedence diagram showing the network logic for each project activity you have identified; 2.    prepare...
Activity Depends on Optimistic Duration (Days) Most Likely Duration (days) Pessimistic Duration (Days) A - 7...
Activity Depends on Optimistic Duration (Days) Most Likely Duration (days) Pessimistic Duration (Days) A - 7 10 18 B A 3 8 14 C B 10 14 22 D A 2 5 9 E B,D 7 9 15 F C,D 4 9 19 G B 10 15 29 H C,E,F 2 8 19 I G,H 1 2 7 J I 3 9 18 Refer to the information above: Determine the following for each activity: Expected Duration (round to the nearest...
QUESTION 2. The following table explain the logical relationship of activities of a given project, including...
QUESTION 2. The following table explain the logical relationship of activities of a given project, including the duration in weeks of each activity. Activity Follows Duration (Weeks) M G, F 4 F Start 6 G Start 3 D Start 7 K D, G 5 L K, J 8 J D 3 S L, M, F 4 Finish S Draw the network Perform the forward path as determine the project duration (5 Marks) Perform the back path and determine the critical...
ADVERTISEMENT
Need Online Homework Help?

Get Answers For Free
Most questions answered within 1 hours.

Ask a Question
ADVERTISEMENT