Question

Problem 5-7 The following activities are part of a project to be scheduled using CPM: ACTIVITY...

Problem 5-7

The following activities are part of a project to be scheduled using CPM:

ACTIVITY IMMEDIATE PREDECESSOR TIME (WEEKS)
A 7
B A 6
C A 2
D C 4
E B D 3
F D 4
G E F 6

b. What is the critical path?

A-C-D-F-G
A-C-D-E-G
A-B-E-G
A-B-D-F-G

c. How many weeks will it take to complete the project?

Number of weeks            

d. How much slack does activity B have?

Slack of activity B             week(s)

Homework Answers

Answer #1
step 1 find early start, and early finish from the start of the project for each activity
step 2 Find Maximum EF and keep it as the LF of last activities. Max of EF's is 23
Activity Duration, D Early start, ES=Max of early finish of preceding activities Early finish, EF = ES + D Late finish, LF= Min of LS of successor activities Late start, LS= LF - D Total slack= LF-EF Critical activity, activities with 0 slack time
A 7 0 7
B 6 7 13
C 2 7 9
D 4 9 13
E 3 13 16
F 4 13 17
G 6 17 23 23
step 3 calculate LS for each activity after calculating its EF
Activity Duration, D Early start, ES=Max of early finish of preceding activities Early finish, EF = ES + D Late finish, LF= Min of LS of successor activities Late start, LS= LF - D Total slack= LF-EF Critical activity, activities with 0 slack time
A 7 0 7 7 0 0 Yes
B 6 7 13 14 8 1 No
C 2 7 9 9 7 0 Yes
D 4 9 13 13 9 0 Yes
E 3 13 16 17 14 1 No
F 4 13 17 17 13 0 Yes
G 6 17 23 23 17 0 Yes

b: A-C-D-F-G is the critical path.

c: it will take 23 weeks

d: B has 1 week of slack

Know the answer?
Your Answer:

Post as a guest

Your Name:

What's your source?

Earn Coins

Coins can be redeemed for fabulous gifts.

Not the answer you're looking for?
Ask your own homework help question
Similar Questions
The following activities are part of a project to be scheduled using CPM: ACTIVITY IMMEDIATE PREDECESSOR...
The following activities are part of a project to be scheduled using CPM: ACTIVITY IMMEDIATE PREDECESSOR TIME (WEEKS) A — 7 B A 6 C A 2 D C 4 E B D 3 F D 4 G E F 6 a. Draw the network b. What is the critical path c. How many weeks will it take to complete the project d. Identify the early start, early finish, late start, and late finish for each activity in the project...
Consider the following information for a project to add a drive-thru window at Crestview Bank.       Activity...
Consider the following information for a project to add a drive-thru window at Crestview Bank.       Activity Activity Time​ (weeks) Immediate​ Predecessor(s) A 6 − B 1 − C 9 − D 3 ​A, B E 6 B F 4 ​D, C G 5 ​E, C H 9 ​F, G b. Specify the critical path. The critical path is _____ and the project duration is_____ c. Calculate the slack for activities A and D.
The activities described by the following table are given for the Howard Corporation in​ Kansas: Activity  ...
The activities described by the following table are given for the Howard Corporation in​ Kansas: Activity   Time (in weeks)   Immediate Predecessor(s)   Activity   Time (in weeks)   Immediate Predecessor(s)   Activity   Time (in weeks)   Immediate Predecessor(s) A 10 - D 6 B G 6 E, F B 6 A E 10   B H 6 D C 3 A F 10 C I 2 G, H b) The activities on the critical path are
Following information is available about a project. Activity Activity Time (weeks) Immediate Predecessor(s) K 4 -...
Following information is available about a project. Activity Activity Time (weeks) Immediate Predecessor(s) K 4 - B 4 - C 5 - D 4 - E 6 K F 2 B,C,D G 4 E.F H 6 F Compute slack for each activity. Activity Slack K B C D E F G H
1. A landscaping upgrade project consists of following activities. Times are given in weeks. Activity Immediate...
1. A landscaping upgrade project consists of following activities. Times are given in weeks. Activity Immediate Predecessor Activity Time A - 5 B A 8 C A 7 D - 6 E B, D, C 8 F D 3 G D 3 a. Draw the network diagram and find the ES, EF, LS, LF, and slack for each activity. b. Construct an early-start-date Gantt chart for the project. c. As a project manager, where would you focus your attention, given...
Given the following information for a project, answer the following questions: Activity Predecessor Activity Time (days)...
Given the following information for a project, answer the following questions: Activity Predecessor Activity Time (days) A - 6 B - 8 C A, B 5 D B 4 E C 7 F C, D 3 G D 6 H E, F, G 5 Fill in the following table. Activity ES EF LS LF Slack CP A 0 No B Yes C Yes D No E Yes F No G 18 14 20 No H 25 20 25 Yes Draw...
For the following network determine: a) The activities on the critical path b) The time for...
For the following network determine: a) The activities on the critical path b) The time for the critical path c) The slack for EVERY activity Activity Immediate Predecessors Time A - 5 B - 6 C A,B 7 D A,B 6 E A,B 8 F C,D,E 4 G C,D,E 3
Consider a project having the following six activities:                                  
Consider a project having the following six activities:                                                      Immediate                                                  Max        Crash cost             Activity                           Predecessors           Time (weeks)             Crash*    per week                   A                                none                                    6                          6                N/A                   B                                none                                    5                          2               $500                   C                                A                                       3                          2             $1000                   D                                A, B                                    4                          2             $2000                   E                                 C, D                                    5                          2             $1250                   F                                D                                       6                          2             $1000                                                                                                 *Shortest possible time for the task Draw the project network and list the...
The estimated times and immediate predecessors for the activities in a project at Paccar Winch are...
The estimated times and immediate predecessors for the activities in a project at Paccar Winch are given in the following table. Assume that the activity times are independent Activity Immediate Predecessor Time (Weeks) a m b A - 9 10 11 B - 4 10 16 C A 9 10 11 D B 5 8 11 a) Calculate the expected time and variance for each activity. b) What is the expected completion time of the critical path? What is the...
Activity Immediate Predecessor Optimistic Time Most-likely time Pessimistic Time A None 3 6 9 B A...
Activity Immediate Predecessor Optimistic Time Most-likely time Pessimistic Time A None 3 6 9 B A 3 5 7 C A 4 7 12 D B 4 8 10 E C 5 10 16 F D, E 3 4 5 G D, E 3 6 8 H F 5 6 10 I G 5 8 11 J H, I 3 3 3 (a). What is the expected time for each activity? (2 points) (b.) What is the variance for each...
ADVERTISEMENT
Need Online Homework Help?

Get Answers For Free
Most questions answered within 1 hours.

Ask a Question
ADVERTISEMENT