Consider the following information for a project to add a drive-thru window at Crestview Bank.
Activity |
Activity Time (weeks) |
Immediate Predecessor(s) |
A |
6 |
− |
B |
1 |
− |
C |
9 |
− |
D |
3 |
A, B |
E |
6 |
B |
F |
4 |
D, C |
G |
5 |
E, C |
H |
9 |
F, G |
b. Specify the critical path. The critical path is _____ and the project duration is_____
c. Calculate the slack for activities A and D.
(Note: please like the answer it will encourage me. Do comment if any correction required before disliking.)
Get Answers For Free
Most questions answered within 1 hours.