Question

Consider the following information for a project to add a drive-thru window at Crestview Bank.       Activity...

Consider the following information for a project to add a drive-thru window at Crestview Bank.      

Activity

Activity Time​ (weeks)

Immediate​ Predecessor(s)

A

6

B

1

C

9

D

3

​A, B

E

6

B

F

4

​D, C

G

5

​E, C

H

9

​F, G

b. Specify the critical path. The critical path is _____ and the project duration is_____

c. Calculate the slack for activities A and D.

Homework Answers

Answer #1

(Note: please like the answer it will encourage me. Do comment if any correction required before disliking.)

Know the answer?
Your Answer:

Post as a guest

Your Name:

What's your source?

Earn Coins

Coins can be redeemed for fabulous gifts.

Not the answer you're looking for?
Ask your own homework help question
Similar Questions
Problem 5-7 The following activities are part of a project to be scheduled using CPM: ACTIVITY...
Problem 5-7 The following activities are part of a project to be scheduled using CPM: ACTIVITY IMMEDIATE PREDECESSOR TIME (WEEKS) A — 7 B A 6 C A 2 D C 4 E B D 3 F D 4 G E F 6 b. What is the critical path? A-C-D-F-G A-C-D-E-G A-B-E-G A-B-D-F-G c. How many weeks will it take to complete the project? Number of weeks             d. How much slack does activity B have? Slack of activity B             week(s)
The activities described by the following table are given for the Howard Corporation in​ Kansas: Activity  ...
The activities described by the following table are given for the Howard Corporation in​ Kansas: Activity   Time (in weeks)   Immediate Predecessor(s)   Activity   Time (in weeks)   Immediate Predecessor(s)   Activity   Time (in weeks)   Immediate Predecessor(s) A 10 - D 6 B G 6 E, F B 6 A E 10   B H 6 D C 3 A F 10 C I 2 G, H b) The activities on the critical path are
Following information is available about a project. Activity Activity Time (weeks) Immediate Predecessor(s) K 4 -...
Following information is available about a project. Activity Activity Time (weeks) Immediate Predecessor(s) K 4 - B 4 - C 5 - D 4 - E 6 K F 2 B,C,D G 4 E.F H 6 F Compute slack for each activity. Activity Slack K B C D E F G H
The following activities are part of a project to be scheduled using CPM: ACTIVITY IMMEDIATE PREDECESSOR...
The following activities are part of a project to be scheduled using CPM: ACTIVITY IMMEDIATE PREDECESSOR TIME (WEEKS) A — 7 B A 6 C A 2 D C 4 E B D 3 F D 4 G E F 6 a. Draw the network b. What is the critical path c. How many weeks will it take to complete the project d. Identify the early start, early finish, late start, and late finish for each activity in the project...
Given the following information for a project, answer the following questions: Activity Predecessor Activity Time (days)...
Given the following information for a project, answer the following questions: Activity Predecessor Activity Time (days) A - 6 B - 8 C A, B 5 D B 4 E C 7 F C, D 3 G D 6 H E, F, G 5 Fill in the following table. Activity ES EF LS LF Slack CP A 0 No B Yes C Yes D No E Yes F No G 18 14 20 No H 25 20 25 Yes Draw...
The following information is known about a project: a. Draw a network diagram b. Calculate the...
The following information is known about a project: a. Draw a network diagram b. Calculate the ES, EF, LS, LF and slack time and find the critical path for this project Activity Activity Time (days) Immediate Predecessor A 12 B 9 C 10 A D 10 A,B E 24 B F 10 A G 35 C H 40 D I 15 A J 4 E,G,H K 6 F,I,J
Activity Immediate Predecessor Optimistic Time Most-likely time Pessimistic Time A None 3 6 9 B A...
Activity Immediate Predecessor Optimistic Time Most-likely time Pessimistic Time A None 3 6 9 B A 3 5 7 C A 4 7 12 D B 4 8 10 E C 5 10 16 F D, E 3 4 5 G D, E 3 6 8 H F 5 6 10 I G 5 8 11 J H, I 3 3 3 (a). What is the expected time for each activity? (2 points) (b.) What is the variance for each...
Use the following data for problems 34, 35, and 36 Activity Activity Predecessor Time (days) A...
Use the following data for problems 34, 35, and 36 Activity Activity Predecessor Time (days) A -- 4 B -- 12 C A, B 15 D A, B 8 E A, B 6 F C, D, E 14 G C, D, E 3 H F, G 6 The expected completion time for the project above is? 27 days 68 days 47 days 30 days The critical path for the project is? B, C, F, H B, C, F, G, H...
Consider a project having the following six activities:                                  
Consider a project having the following six activities:                                                      Immediate                                                  Max        Crash cost             Activity                           Predecessors           Time (weeks)             Crash*    per week                   A                                none                                    6                          6                N/A                   B                                none                                    5                          2               $500                   C                                A                                       3                          2             $1000                   D                                A, B                                    4                          2             $2000                   E                                 C, D                                    5                          2             $1250                   F                                D                                       6                          2             $1000                                                                                                 *Shortest possible time for the task Draw the project network and list the...
AON The table given below contains the activity label, its respective duration (in weeks) and its...
AON The table given below contains the activity label, its respective duration (in weeks) and its precedents. Use critical path method to find the critical path and activities of this project. ACTIVITY DURATION (IN WEEKS) PRECEDENTS A 6 – B 4 – C 3 A D 4 B E 3 B F 10 – G 3 E, F H 2 C, D
ADVERTISEMENT
Need Online Homework Help?

Get Answers For Free
Most questions answered within 1 hours.

Ask a Question
ADVERTISEMENT