Question

Activity Immediate Predecessor Optimistic Time Most-likely time Pessimistic Time A None 3 6 9 B A...

Activity

Immediate

Predecessor

Optimistic Time

Most-likely time

Pessimistic Time

A

None

3

6

9

B

A

3

5

7

C

A

4

7

12

D

B

4

8

10

E

C

5

10

16

F

D, E

3

4

5

G

D, E

3

6

8

H

F

5

6

10

I

G

5

8

11

J

H, I

3

3

3

(a). What is the expected time for each activity? (2 points)

(b.) What is the variance for each activity? (2 points)

Use both the longest path method and ES/EF; LS/LF method for the following questions

(c) What is the expected project completion time? (2 point)

(d) What are the critical activities? (1 points)

(e) What are the slack values for non-critical activities? (4 points)

(f) What is the probability that the project will be completed in 38 weeks? (2 points)

(g) What is the probability that the project will be completed in 42 weeks? (2 points)

Homework Answers

Answer #1

Expected Duration = (Optimistic time + 4* Most likely time + Pessimistic time) / 6

Variance= ((Pessimistic time - Optimistic time)/ 6 )2

Standard Deviation = square root of Variance

For Activity A,

Expected duration = (3+4*6+9) / 6 = 6 weeks

Variance = ((9-3)/6)2 = 1

Stadndard Deviation = square root (1) = 1

Remaining calculation are as below

Activity Immediate Predecessor Optimistic Time Most-likely time Pessimistic Time Expected mean time Variance Std Dev ES EF LS LF Slack Critical
(1) (2) (3) (4) (5) (6) = [(3)+4(4)+(5)]/6 (7)=[[(5)-(3)]/6]^2 (8)=(7)^0.5 (9) (10)=(9)+(6) (11)=(12)-(6) (12)
A None 3 6 9 6 1 1 0 6 0 6 0 Yes
B A 3 5 7 5 0.444444444 0.666666667 6 11 10.83333333 15.83333 4.833333 No
C A 4 7 12 7.333333333 1.777777778 1.333333333 6 13.33333333 6 13.33333 0 Yes
D B 4 8 10 7.666666667 1 1 11 18.66666667 15.83333333 23.5 4.833333 No
E C 5 10 16 10.16666667 3.361111111 1.833333333 13.33333 23.5 13.33333333 23.5 0 Yes
F D, E 3 4 5 4 0.111111111 0.333333333 23.5 27.5 26.83333333 30.83333 3.333333 No
G D, E 3 6 8 5.833333333 0.694444444 0.833333333 23.5 29.33333333 23.5 29.33333 0 Yes
H F 5 6 10 6.5 0.694444444 0.833333333 27.5 34 30.83333333 37.33333 3.333333 No
I G 5 8 11 8 1 1 29.33333 37.33333333 29.33333333 37.33333 0 Yes
J H, I 3 3 3 3 0 0 37.33333 40.33333333 37.33333333 40.33333 0 Yes
Critical Path A-C-E-G-I-J
Critical duration 40.33 weeks

f) Probability that project will be completed in 38 weeks

Variance along critical path = 1+1.7778+3.3611+0.69444+1+0 = 7.8333

Std Dev along critical path = 7.8333^0.5 = 2.79888

Z = (x- ) / = (38-40.33) / 2.7988 = -0.8325

Prob = Norm.s.dist(-0.8325,1) = 0.2056 = 20.56%

g) Probability that project will be completed in 42 weeks

Variance along critical path = 1+1.7778+3.3611+0.69444+1+0 = 7.8333

Std Dev along critical path = 7.8333^0.5 = 2.79888

Z = (x- ) / = (42-40.33) / 2.7988 = 0.59669

Prob = Norm.s.dist(0.59669,1) = 0.72464 = 72.46%

Know the answer?
Your Answer:

Post as a guest

Your Name:

What's your source?

Earn Coins

Coins can be redeemed for fabulous gifts.

Not the answer you're looking for?
Ask your own homework help question
Similar Questions
Given the following information for a project, answer the following questions: Activity Predecessor Activity Time (days)...
Given the following information for a project, answer the following questions: Activity Predecessor Activity Time (days) A - 6 B - 8 C A, B 5 D B 4 E C 7 F C, D 3 G D 6 H E, F, G 5 Fill in the following table. Activity ES EF LS LF Slack CP A 0 No B Yes C Yes D No E Yes F No G 18 14 20 No H 25 20 25 Yes Draw...
Activity Depends on Optimistic Duration (Days) Most Likely Duration (days) Pessimistic Duration (Days) A - 7...
Activity Depends on Optimistic Duration (Days) Most Likely Duration (days) Pessimistic Duration (Days) A - 7 10 18 B A 3 8 14 C B 10 14 22 D A 2 5 9 E B,D 7 9 15 F C,D 4 9 19 G B 10 15 29 H C,E,F 2 8 19 I G,H 1 2 7 J I 3 9 18 Refer to the information above: Determine the following for each activity: Expected Duration (round to the nearest...
A partially solved PERT problem is detailed in the table below. Times are given in weeks....
A partially solved PERT problem is detailed in the table below. Times are given in weeks. Activity Immediate Predecessor(s) Optimistic Most Likely Pessimistic A -- 8 10 15 B -- 7 8 9 C A 5 6 10 D A 3 3 3 E B,D 1 5 9 F B,D 4 7 10 G C 3 8 10 H E 5 7 9 I E 4 5 8 J F 2 5 8 K H, I 1 3 6 a)...
1. A landscaping upgrade project consists of following activities. Times are given in weeks. Activity Immediate...
1. A landscaping upgrade project consists of following activities. Times are given in weeks. Activity Immediate Predecessor Activity Time A - 5 B A 8 C A 7 D - 6 E B, D, C 8 F D 3 G D 3 a. Draw the network diagram and find the ES, EF, LS, LF, and slack for each activity. b. Construct an early-start-date Gantt chart for the project. c. As a project manager, where would you focus your attention, given...
Consider the network described in the table below. Activity Immediate Predecessor(s) Pessimistic Probable Optimistic J --...
Consider the network described in the table below. Activity Immediate Predecessor(s) Pessimistic Probable Optimistic J -- 15 10 8 K -- 9 8 7 L J 10 6 5 M J 3 3 3 N K,M 9 5 1 O K,M 10 7 4 P L,N 10 8 3 a. Calculate the expected duration of each activity. b. Calculate the expected duration and variance of the critical path. c. Calculate the probability that the project will be completed in fewer...
A future construction project has the following activity relationships and activity time estimates (in days): Activity...
A future construction project has the following activity relationships and activity time estimates (in days): Activity Immediate Predecessor To Tm Tp A None 4 5 6 B None 3 6 21 C B 1 4 7 D A 2 5 8 E C, D 3 9 27 F C 3 6 15 G E, F 2 4 6 H F, G 2 2 2 Leave 2-decimal if not exact, do not round up, for example, 4.3268... will be kept as...
Refer to the information below: Depends On Optimistic Duration(days) Most Likely Duration(days) Pessimistic Duration(days) A -...
Refer to the information below: Depends On Optimistic Duration(days) Most Likely Duration(days) Pessimistic Duration(days) A - 7 10 18 B A 3 8 14 C B 10 14 22 D A 2 5 9 E B,D 7 9 15 F C,D 4 9 19 G B 10 15 29 H C,E,F 2 8 19 I G,H 1 2 7 J I 3 9 18 Determine the following for each activity: Expected Duration (round to the nearest whole number) Early Start...
Following information is available about a project. Activity Activity Time (weeks) Immediate Predecessor(s) K 4 -...
Following information is available about a project. Activity Activity Time (weeks) Immediate Predecessor(s) K 4 - B 4 - C 5 - D 4 - E 6 K F 2 B,C,D G 4 E.F H 6 F Compute slack for each activity. Activity Slack K B C D E F G H
Fill out the charts with the correct information. Activity Optimistic Most Probable Pessimistic A 3 8...
Fill out the charts with the correct information. Activity Optimistic Most Probable Pessimistic A 3 8 13 B 5 7 9 C 5 12 19 D 2 5 8 E 5 9 19 F 4 8 18 G 9 15 21 H 4 6 14 If required, round your answers to two decimal places. A.) Find the critical path. Activity Expected Time Variance A B C D E F G H Earliest Latest Earliest Latest Critical Activity Start Start Finish...
The following activities are part of a project to be scheduled using CPM: ACTIVITY IMMEDIATE PREDECESSOR...
The following activities are part of a project to be scheduled using CPM: ACTIVITY IMMEDIATE PREDECESSOR TIME (WEEKS) A — 7 B A 6 C A 2 D C 4 E B D 3 F D 4 G E F 6 a. Draw the network b. What is the critical path c. How many weeks will it take to complete the project d. Identify the early start, early finish, late start, and late finish for each activity in the project...
ADVERTISEMENT
Need Online Homework Help?

Get Answers For Free
Most questions answered within 1 hours.

Ask a Question
ADVERTISEMENT