1. A landscaping upgrade project consists of following activities. Times are given in weeks.
Activity |
Immediate Predecessor |
Activity Time |
A |
- |
5 |
B |
A |
8 |
C |
A |
7 |
D |
- |
6 |
E |
B, D, C |
8 |
F |
D |
3 |
G |
D |
3 |
a. Draw the network diagram and find the ES, EF, LS, LF, and slack for each activity.
b. Construct an early-start-date Gantt chart for the project.
c. As a project manager, where would you focus your attention, given your analysis
c) As a manager, I would focus on getting the project completed as soon as possible as consider the critical path Activities. Other activities can be delayed for a greater amount of time, so it is required to use some resources and to shorten the duration of the completion time.
Get Answers For Free
Most questions answered within 1 hours.