Question

You are the project manager for a new multimillion-dollar building renovation for your organization. The company...

You are the project manager for a new multimillion-dollar building renovation for your organization. The company needs to maximize the space that it has, and the best approach is to do a staggered build-out in order to better maximize the space in the existing building. You feel that the best approach was to negotiate with multiple contractors on a fixed-price contract. Different contractors discussed other contracts with you, particularly ones to address the current market fluctuations in the raw materials market. You ignore those other companies and settle on an agreement with a local company that is willing to accept your terms for a fixed-price contract. You find out a few weeks into a 4-month project that raw materials have increased by 250%. The contractor meets with you to discuss a price increase for the project. You have already committed a fixed price to the company and there is no contingency in the budget. The contractor advises that he will go bankrupt if he is forced to finish the project at this price and so the contractor sends you notification that he is stopping work on the project. Word of the work stoppage flies through your company and your boss calls you to his office for an update. You explain what has happened, but he feels that you are responsible for allowing this to get to this point. You are told by your boss to work something out with the contractor and to go into the negotiation with a good plan on how to mitigate the costs. Upon reflection of this situation, consider the below questions and how this situation might have been different with a different contract approach. • Why was putting too much risk on another company a negative thing? • If one is paying for risk mitigation, then why not outsource all risk? • In the big picture, what is the role of insurance in risk mitigation?

Homework Answers

Answer #1

Answer: It is not wise to mitigate risk by putting more risk on another company as it will ultimately harm the interests of the company itself. Illogical burden on any company may cause the company to take a negative approach for solving the problem. In this case itself it is evident that by completely transferring the risk of raw material fluctuation on the contractor company ultimately resulted in the stoppage of the project. So if a company is working in cooperation with another company it is important that risk is mitigated by a rational sharing of risks. When total risk is transferred to any one partner it is both irrational as well as unethical decision. Thus putting too much risk to another company is a negative thing. Even if one is paying for risk mitigation, one should understand that entire risk cannot be mitigated by outsourcing. Therefore a rational approach it required in risk mitigation. The tools like insurance can definitely help in risk mitigation as it helps in sharing of the risk. But at the same time it cannot be ignored that even insurance has its limitations and it only reduces risks but does not eliminates it completely.

Know the answer?
Your Answer:

Post as a guest

Your Name:

What's your source?

Earn Coins

Coins can be redeemed for fabulous gifts.

Not the answer you're looking for?
Ask your own homework help question
Similar Questions
A building contractor is preparing a bid on a new construction project. Two other contractors will...
A building contractor is preparing a bid on a new construction project. Two other contractors will be submitting bids for the same project. Based on past bidding practices, bids from the other contractors can be described by the following probability distributions: Contractor Probability Distribution of Bid A Uniform probability distribution between $570,000 and $770,000 B Normal probability distribution with a mean bid of $670,000 and a standard deviation of $47,000 If required, round your answers to three decimal places. If...
Problem 12-18 (Algorithmic) A building contractor is preparing a bid on a new construction project. Two...
Problem 12-18 (Algorithmic) A building contractor is preparing a bid on a new construction project. Two other contractors will be submitting bids for the same project. Based on past bidding practices, bids from the other contractors can be described by the following probability distributions: Contractor Probability Distribution of Bid A Uniform probability distribution between $600,000 and $800,000 B Normal probability distribution with a mean bid of $700,000 and a standard deviation of $50,000 If required, round your answers to three...
Problem 12-18 (Algorithmic) A building contractor is preparing a bid on a new construction project. Two...
Problem 12-18 (Algorithmic) A building contractor is preparing a bid on a new construction project. Two other contractors will be submitting bids for the same project. Based on past bidding practices, bids from the other contractors can be described by the following probability distributions: Contractor Probability Distribution of Bid A Uniform probability distribution between $530,000 and $730,000 B Normal probability distribution with a mean bid of $630,000 and a standard deviation of $43,000 If required, round your answers to three...
4a)  A fellow project manager has approached you for advice to manage risk in the procurement of...
4a)  A fellow project manager has approached you for advice to manage risk in the procurement of IT services without a well -defined specification. According to the fellow project manager, he and his team does not want to entertain any risk, hence his decision in choosing a Fixed Price Contract. Are there any inherent risks in the selected contract type? Critically evaluate the situation and bring out all the inherent risks you foresee. 4b) How can organizations use weighted scoring model...
You are evaluating a project for your company. The initial outlay for the project is $5,000,000,...
You are evaluating a project for your company. The initial outlay for the project is $5,000,000, and free cash flows for the project are $1,000,000, $3,000,000, $3,000,000, $4,000,000 and $4,000,000.  For risk analysis, you utilize the Payback and Discounted Payback methods to trigger increased risk scrutiny.  Your standard is, any project that goes longer than 3 years under either metric will go through these increased risk tests.  If your required rate is 12%, does this project qualify for increased scrutiny? Any problems with...
As the manager of a new website project for your company, you need to decide whether...
As the manager of a new website project for your company, you need to decide whether to create a new web application in-house or send the project out to a developer. The developer has quoted a project cost of $175,000. Based on previous work with this developer, you are 85 percent certain they will finish the work on time. Your in-house development team has quoted a project cost of $165,000. Based on previous work with the in-house team, you are...
A. You are a project manager working on a new residential building. The work is getting...
A. You are a project manager working on a new residential building. The work is getting delayed for some technical reasons. B. Write an email to your client/customer apologising for the delay and request him to extend the deadline for one month.
You are the project manager for an upgrade of computers in your company. You need to...
You are the project manager for an upgrade of computers in your company. You need to upgrade 30 systems, including 10 desktops (for office personnel) and 20 laptops (for remote workers). Each system must access the company network, as well as a common installation of software, security components, and so forth. You must submit your risk identification in a summary that will be used during a presentation for the CIO. In a 3–5 page document, complete the following: Identify four...
You are the project manager of a complicated construction project, which involves building highways in the...
You are the project manager of a complicated construction project, which involves building highways in the whole state of North Carolina. You have several groups working with you in the project. To plan resources for this project and determine connection between individuals you should preferably use: Staffing pool description Staffing management plan Responsibility assignment matrix (RAM) Organization matrix You are the project manager of a project team that includes several new recruits. You notice that most of the team members...
Assume that your company sells portable housing to both general contractors and the government. It sells...
Assume that your company sells portable housing to both general contractors and the government. It sells jobs to contractors on a bid basis. A contractor asks for three bids from different manufacturers. The combination of low bid and high quality wins the job. However, jobs sold to the governments are bid on a cost-plus basis. This means price is determined by adding all costs plus a profit based on cost at a specified percent, such as 10%. You observe that...
ADVERTISEMENT
Need Online Homework Help?

Get Answers For Free
Most questions answered within 1 hours.

Ask a Question
ADVERTISEMENT