Question

A. You are a project manager working on a new residential building. The work is getting...

A. You are a project manager working on a new residential building. The work is getting delayed for some technical reasons.

B. Write an email to your client/customer apologising for the delay and request him to extend the deadline for one month.

Homework Answers

Answer #1

Dear [Boss, Client, or Co-Worker Name],

I’m reaching out because, unfortunately, I won’t be able to submit [project] in [number of] hours as promised. I take full responsibility for underestimating how long it would take, and for not reaching out sooner.

Attached, I’ve included [notes, a rough draft, ballpark figures, or an outline]. While this is not ready to be shared with [team/clients], I want to give you a sense of where it’s headed.

Now that I know how long it takes to [run the numbers/work with this new program/draw conclusions from findings], I feel confident I can have this finished in [extremely realistic amount of time]. I will have the finished project to you by [new time] on [day].

I sincerely apologize for the inconvenience and want to assure you this won’t happen again.

Best,
[Your Name]

Know the answer?
Your Answer:

Post as a guest

Your Name:

What's your source?

Earn Coins

Coins can be redeemed for fabulous gifts.

Not the answer you're looking for?
Ask your own homework help question
Similar Questions
You are a Project Manager of a project to build a ten-story building. At the beginning...
You are a Project Manager of a project to build a ten-story building. At the beginning of the project you were targeted to build one floor per month. The planned cost per floor is €500,000. It is now month 8 and you have completed 9 floors and the total costs to date are €4,750,000. Calculate the following: CV; SV; CPI; EAC;
You are the project manager of a complicated construction project, which involves building highways in the...
You are the project manager of a complicated construction project, which involves building highways in the whole state of North Carolina. You have several groups working with you in the project. To plan resources for this project and determine connection between individuals you should preferably use: Staffing pool description Staffing management plan Responsibility assignment matrix (RAM) Organization matrix You are the project manager of a project team that includes several new recruits. You notice that most of the team members...
You are the project manager for a new multimillion-dollar building renovation for your organization. The company...
You are the project manager for a new multimillion-dollar building renovation for your organization. The company needs to maximize the space that it has, and the best approach is to do a staggered build-out in order to better maximize the space in the existing building. You feel that the best approach was to negotiate with multiple contractors on a fixed-price contract. Different contractors discussed other contracts with you, particularly ones to address the current market fluctuations in the raw materials...
You have been hired as construction manager for a building construction project. Highlight some key aspects...
You have been hired as construction manager for a building construction project. Highlight some key aspects of your anticipated role.
You are working in a team of three on a new social media plan for your...
You are working in a team of three on a new social media plan for your company. You and one other team member are working well together, and have really cool ideas. The third team member doesn't seem to understand the project direction, his ideas don't really work, and only shows up to about half of the scheduled meetings. Your manager has requested that you present your team's work to her, and to three other members of management. PLEASE WRITE...
You are working for a contractor that has a contract for construction of a new residential...
You are working for a contractor that has a contract for construction of a new residential building. As part of the project, you need to remove the soil for the construction of the basement and foundation for a parking garage. From the project plans you know that 7,500 bank cubic yards must be excavated and that 1200 compacted cubic yards will be required to backfill the completed foundation. You plan to stockpile the soil needed for backfill on site and...
You are getting ready to start a new project that will incur some cleanup and shutdown...
You are getting ready to start a new project that will incur some cleanup and shutdown costs when it is completed. The project costs $5.32 million up front and is expected to generate $1.15 million per year for 10 years and then have some shutdown costs at the end of year 11. Use the MIRR approach to find the maximum shutdown costs you could incur and still meet your cost of capital of 14.8% on this project.
You are the supervising manager at an engineering firm. A client has requested your firm work...
You are the supervising manager at an engineering firm. A client has requested your firm work on a project that is handled frequently by your employees. The standard hours for projects of this nature is 36 hours for one engineer. You have decided to hand this incoming project to a brand new hire who just graduated with her engineering degree. What should your expectation be regarding the standard of 36 hours for this particular project? Why?
Project Management Fundamentals Questions Only A project team is discussing the benefits and drawbacks of working...
Project Management Fundamentals Questions Only A project team is discussing the benefits and drawbacks of working on projects within their organization now that it has become project-oriented. They can agree on many advantages for the team and for the organization, but also agree there are some drawbacks, relative to the strong matrix structure the organization used to have. In a project-oriented organization the project team: ANSWER Will not always have a "home" Reports to the functional manager Has no loyalty...
Assume that you are the project manager for an upcoming new information systems project designed to...
Assume that you are the project manager for an upcoming new information systems project designed to replace your organization's old inventory management system. The server and database will also be upgraded. Name one risk of project derailment or failure that you might anticipate? How might you mitigate this risk?
ADVERTISEMENT
Need Online Homework Help?

Get Answers For Free
Most questions answered within 1 hours.

Ask a Question
ADVERTISEMENT