Question

Given the information below: (Use normal time to calculate original path) a) Which activity(s) should be...

Given the information below: (Use normal time to calculate original path)

a) Which activity(s) should be crashed and what is the cost to reduce the project completion time from 22 to 21 days?

b) Which activity(s) should be crashed and what is the cost to reduce the project completion time from 21 to 20 days?

c) Which activity(s) should be crashed and what is the cost to reduce the project completion time from 20 to19 days?

d) What is the total cost to reduce the project from the original normal completion time to 19 days?


Activity Immediate Predecessors Normal time Crash time Normal cost Crash cost
A - 5 3 $3,000 $3,600
B - 6 4 $3,500 $4,300
C A 7 5 $3,300 $4,000
D B 5 4 $2,200 $2,400
E B 3 2 $1,700 $2,200
F D,E 5 3 $2,200 $3,600
G C,D 7 6 $1,900 $2,550
H F,G 3 2 $1,200 $1,750

Homework Answers

Answer #1

Crash cost per week for each activity is, (Crash Cost - Normal Cost) / (Normal time - Crash time)

For A, ($3600 - $3500) / (5-4) = $100

For B, ($4300 - $3500) / (6 - 4) = $400

For C, ($3900 - $3300) / (4 -2) = $300

For D, ($2900 - $2200) / (5 -4) = $700

For E, ($2200 - $1700) / (3 -2) = $500

For F, ($3600 - $2000) / (7 -5) = $800

For G, ($2550 - $1900) / (3-2) = $650

For H, ($1750 - $1200) / (4 -3) = $550

The path from the graph for project execution is,

A, C, G, H ( Total normal time = 5 + 4 + 3 + 4 = 16 days)

A, D, F, H ( Total normal time = 5 + 5 + 7 + 4 = 21 days)

B, D , F , H ( Total normal time = 6 + 5 + 7 + 4 = 22 days)

B, E, F, H ( Total normal time = 6 + 3 + 7 + 4 = 20 days)

So, the critical path is B, D , F , H with total normal time = 22 days

(a)

1. To reduce the project completion time from 22 to 21 days.

2. We need to reduce the time for any of the activity B, D , F , H.

3. Among B, D, F, H, the minimum Crash cost per week is for B ($400)

4. So activity B should be crashed and the total cost = $400

(b)

1. When Activity B is crashed, there are two critical paths - A, D, F, H and B, D , F , H with project completion time of 21 days.

2. To reduce the project completion time from 21 to 20 days, we need to crash atleast activity from both the critical paths.

3. Among A, D, F, H, the minimum Crash cost per week is for A ($100)

4. Among B, D, F, H, the minimum Crash cost per week is for B ($400) [Activity B can be crashed for one more day. (Difference between Normal and Crash time for B is 2 , so, B can be crashed for 2 days).]

So activity A and B should be crashed and the total cost = $100 + $400 = $500

(c)

1. When Activity A and B is crashed, there are three critical paths - A, D, F, H ; B, D , F , H and B, E, F, H with project completion time of 20 days.

2. To reduce the project completion time from 20 to 19 days, we need to crash at least one activity from all three critical paths.

3. Among A, D, F, H, the minimum Crash cost per week is for A ($100), but A has already been crashed and cannot be crashed for more than 1 day. (Difference between Normal and Crash time for A is 1)

4. After A, the next minimum Crash cost per week is for H ($550)

5. If H is crashed, then it will also apply for other critical paths , B, D , F , H and B, E, F, H

6. So activity H should be crashed and the total cost = $550

(d)

1. To reduce the project cost from 22 to 19 days, activity A and H should be crashed for 1 day and activity B should be crashed for 2 days.

2. Total project cost to reduce the project completion time (22 days) to 19 days = $400 + $500 + $550 = $1450

Please give an Up-vote; this will be quite encouraging for me, thank you! If you have any doubt, kindly comment. I would love to help you!!!

Know the answer?
Your Answer:

Post as a guest

Your Name:

What's your source?

Earn Coins

Coins can be redeemed for fabulous gifts.

Not the answer you're looking for?
Ask your own homework help question
Similar Questions
Use the following data for question below. Activity Normal Time (weeks) Crash Time (weeks) Normal Cost...
Use the following data for question below. Activity Normal Time (weeks) Crash Time (weeks) Normal Cost Total Cost with Crashing Pred 1 Pred 2 A 10 7 $200 $400 B 15 10 $250 $600 C 13 8 $600 $1,500 A B D 14 10 $800 $1,200 A B E 8 4 $1,000 $3,000 C D F 12 6 $1,200 $1,800 C D G 7 6 $700 $1,400 E F H 5 3 $500 $900 E F If the project must...
Development of Version 2.0 of a particular accounting software product is being considered by Jose​ Noguera's...
Development of Version 2.0 of a particular accounting software product is being considered by Jose​ Noguera's technology firm in Baton Rouge. The activities necessary for the completion of this project are listed in the following​ table: Activity Normal Time (weeks) Crash Time (weeks) Normal Cost Total Cost with Crashing Immediate Predecessors(s) A 4 3 $2,200 $2,850 --- B 2 1 $2,100 $2,700 --- C 3 3 $750 $750 --- D 8 4 $2,500 $2,800 A E 6 3 $800 $1,250...
Activity Immediate Predecessor(s) Normal Time (wks) Crash Time (wks) Normal Cost ($) Crash Cost ($) A...
Activity Immediate Predecessor(s) Normal Time (wks) Crash Time (wks) Normal Cost ($) Crash Cost ($) A — 4 1 5,000 8,000 B — 5 3 8,000 10,000 C A 1 1 4,000 4,000 D B 6 3 6,000 12,000 E B, C 7 6 4,000 7,000 F D 7 6 4,000 7,000 You are the manager of a project to improve a billing process at your firm. Table 3 contains the data you will need to conduct a cost analysis...
The information for project X is shown below. What are the critical path and the completion...
The information for project X is shown below. What are the critical path and the completion time of the project? Crashing Costs Activity Preceding Normal Time 1st Week 2nd Week K — 8 weeks $4100 — L K 6 weeks 3250 — N K 1 week 450 450 M L 5 weeks 3000 3500 J N 4 weeks 500 — Q J,M 6 weeks 4000 4000 KLMQ, 25 weeks KLNMJQ: 25 weeks KNJQ, 25 weeks KNJQ, 30 weeks KLMQ, 30...
Given the following network and activity time estimates, determine earliest and latest activity times, slack, the...
Given the following network and activity time estimates, determine earliest and latest activity times, slack, the expected project completion time and variance, and the probability that the project will be completed in 28 days or less. TIME ESTIMATES (DAYS) ACTIVITY ACTIVITY PREDECESSOR a m b A - 5  8 17 B - 7 10 13 C A 3  5  7 D A 1  3  5 E B, C 4  6  8 F B, C 3  3  3 G D,E 3  ...
A future construction project has the following activity relationships and activity time estimates (in days): Activity...
A future construction project has the following activity relationships and activity time estimates (in days): Activity Immediate Predecessor To Tm Tp A None 4 5 6 B None 3 6 21 C B 1 4 7 D A 2 5 8 E C, D 3 9 27 F C 3 6 15 G E, F 2 4 6 H F, G 2 2 2 Leave 2-decimal if not exact, do not round up, for example, 4.3268... will be kept as...
A car dealership decided to add an annex to its sales office as a customer lounge....
A car dealership decided to add an annex to its sales office as a customer lounge. The project is divided into the activities listed in the following table. The immediate predecessor(s), times and costs, both normal and crashed, are given. To finish the project sooner, the dealership has to make time and cost tradeoffs. If the project needs to be finished in 25 weeks, you are required to formulate a linear programming model to decide about how much to crash...
All information needed to solve this problem is present Problem 9-24 (Algorithmic) Office Automation, Inc., developed...
All information needed to solve this problem is present Problem 9-24 (Algorithmic) Office Automation, Inc., developed a proposal for introducing a new computerized office system that will standardize the electronic archiving of invoices for a particular company. Contained in the proposal is a list of activities that must be accomplished to complete the new office system project. Use the following relevant information about the activities: Immediate Time (weeks) Cost ($1000s) Activity Description Predecessor(s) Normal Crash Normal Crash A Plan needs...
Use the following data for problems 34, 35, and 36 Activity Activity Predecessor Time (days) A...
Use the following data for problems 34, 35, and 36 Activity Activity Predecessor Time (days) A -- 4 B -- 12 C A, B 15 D A, B 8 E A, B 6 F C, D, E 14 G C, D, E 3 H F, G 6 The expected completion time for the project above is? 27 days 68 days 47 days 30 days The critical path for the project is? B, C, F, H B, C, F, G, H...
London Fletcher of Fabriscan Diagnostic, is the project manager. He measured the following information with commutative...
London Fletcher of Fabriscan Diagnostic, is the project manager. He measured the following information with commutative completed times for four periods of the project. Completed% Activity ID Activity Predecessors Estimated Duration(Weeks) Budget ($) Actual Spend ($) 1 2 3 4 Crash time Crash cost$ A 7          7,000                       9,000 20 40 100 100 6             8,000 B A 2          5,000                       5,000 20 60 100 100 1             7,000 C A 4          9,000                       6,000 0 40...