All information needed to solve this problem is present
Problem 9-24 (Algorithmic)
Office Automation, Inc., developed a proposal for introducing a new computerized office system that will standardize the electronic archiving of invoices for a particular company. Contained in the proposal is a list of activities that must be accomplished to complete the new office system project. Use the following relevant information about the activities:
Immediate | Time (weeks) | Cost ($1000s) | |||||||
Activity | Description | Predecessor(s) | Normal | Crash | Normal | Crash | |||
A | Plan needs | — | 9 | 8 | 30 | 50 | |||
B | Order equipment | A | 8 | 6 | 120 | 150 | |||
C | Install equipment | B | 10 | 7 | 100 | 160 | |||
D | Set up training lab | A | 7 | 6 | 40 | 50 | |||
E | Conduct training course | D | 10 | 8 | 50 | 75 | |||
F | Test system | C, E | 3 | 3 | 60 | — |
(i) | (ii) | ||
(iii) | (iv) |
Earliest | Latest | Earliest | Latest | Critical | ||||||||
Activity | Start | Start | Finish | Finish | Slack | Activity (Yes or No) | ||||||
A | ||||||||||||
B | ||||||||||||
C | ||||||||||||
D | ||||||||||||
E | ||||||||||||
F |
Crash Activities | Number of Weeks | Cost ($1000s) |
A | 1 | |
B | 2 | |
C | 1 | |
D | 1 | |
E | 1 | |
Earliest | Latest | Earliest | Latest | Critical | ||||||||
Activity | Start | Start | Finish | Finish | Slack | Activity (yes or no) | ||||||
A | ||||||||||||
B | ||||||||||||
C | ||||||||||||
D | ||||||||||||
E | ||||||||||||
F |
Project Schedule
Activity EST LST EFT LFT Slack Critical Activity(Yes/No)
A 0 0 9 9 0 Yes
B 9 9 17 17 0 Yes
C 17 17 27 27 0 Yes
D 9 10 16 17 1 No
E 27 27 30 30 0 Yes
Critical Path is A-B-C-F
Total Project Completion Time is = 9+8+10+3=30 weeks
Cost Slope is:-
A (50-30/)/1 = 20 per day
B (150-120)/2= 15 per day
C (160-100)/3 =20 per day
D (50-40)/1 = 10 per day
E (75-50)/2 =12.5 per day
F -
Crashing Activity
1. First crash common activity A by 1 day
2. Then crash common activity F by 2 days
3. then crash B by 1 day.
Project Schedule(Revised)
Activity EST LST EFT LFT Slack Critical Activity(Yes/No)
A 0 0 8 8 0 Yes
B 8 8 15 15 0 Yes
C 15 15 25 25 0 Yes
D 8 8 15 15 0 Yes
E 15 15 25 25 0 Yes
F 25 25 26 26 0 Yes
Revised Schedule=26 days
Total added cost of project= Crashing 1+2+3
= $ 20+$25+$15
= $60