Question

All information needed to solve this problem is present Problem 9-24 (Algorithmic) Office Automation, Inc., developed...

All information needed to solve this problem is present

Problem 9-24 (Algorithmic)

Office Automation, Inc., developed a proposal for introducing a new computerized office system that will standardize the electronic archiving of invoices for a particular company. Contained in the proposal is a list of activities that must be accomplished to complete the new office system project. Use the following relevant information about the activities:

Immediate Time (weeks) Cost ($1000s)
Activity Description Predecessor(s) Normal Crash Normal Crash
A Plan needs 9 8 30 50
B Order equipment A 8 6 120 150
C Install equipment B 10 7 100 160
D Set up training lab A 7 6 40 50
E Conduct training course D 10 8 50 75
F Test system C, E 3 3 60
  1. Which project network is correct?
    (i) (ii)
    (iii) (iv)
  2. Develop an activity schedule. If your answer is zero, enter “0”.
    Earliest Latest Earliest Latest Critical
    Activity Start Start Finish Finish Slack Activity (Yes or No)
    A
    B
    C
    D
    E
    F
  3. What are the critical activities, and what is the expected project completion time?

    Critical Path:  

    Expected project completion time = _____ weeks.
  4. Assume that the company wants to complete the project in six months or 26 weeks. What crashing decisions do you recommend to meet the desired completion time at the least possible cost? Work through the network and attempt to make the crashing decisions by inspection.
    Crash Activities Number of Weeks Cost ($1000s)
    A 1
    B 2
    C 1
    D 1
    E 1
  5. Develop an activity schedule for the crashed project. If your answer is zero, enter “0”.
    Earliest Latest Earliest Latest Critical
    Activity Start Start Finish Finish Slack Activity (yes or no)
    A
    B
    C
    D
    E
    F
  6. What added project cost is required to meet the six-month completion time?

    Total added cost due to crashing $  _______.

Homework Answers

Answer #1

Project Schedule

Activity EST LST EFT LFT Slack Critical Activity(Yes/No)

A 0 0 9 9 0 Yes

B 9 9 17 17 0 Yes

C 17 17 27 27 0 Yes

D 9 10 16 17 1 No

E 27 27 30 30 0 Yes

Critical Path is A-B-C-F

Total Project Completion Time is = 9+8+10+3=30 weeks

Cost Slope is:-

A (50-30/)/1 = 20 per day

B (150-120)/2= 15 per day

C (160-100)/3 =20 per day

D (50-40)/1 = 10 per day

E (75-50)/2 =12.5 per day

F -

Crashing Activity

1. First crash common activity A by 1 day

2. Then crash common activity F by 2 days

3. then crash B by 1 day.

Project Schedule(Revised)

Activity EST LST EFT LFT Slack Critical Activity(Yes/No)

A 0 0 8 8 0 Yes

B 8 8 15 15 0 Yes

C 15 15 25 25 0 Yes

D 8 8 15 15 0 Yes   

E 15 15 25 25 0 Yes

F 25 25 26 26 0 Yes

Revised Schedule=26 days

Total added cost of project= Crashing 1+2+3

= $ 20+$25+$15

= $60

Know the answer?
Your Answer:

Post as a guest

Your Name:

What's your source?

Earn Coins

Coins can be redeemed for fabulous gifts.

Not the answer you're looking for?
Ask your own homework help question
Similar Questions
Office Automation, Inc., developed a proposal for introducing a new computerized office system that will standardize...
Office Automation, Inc., developed a proposal for introducing a new computerized office system that will standardize the electronic archiving of invoices for a particular company. Contained in the proposal is a list of activities that must be accomplished to complete the new office system project. Use the following relevant information about the activities: Immediate Time (weeks) Cost ($1000s) Activity Description Predecessor(s) Normal Crash Normal Crash A Plan needs — 13 8 30 130 B Order equipment A 9 6 120...
Consider a project having the following six activities:                                  
Consider a project having the following six activities:                                                      Immediate                                                  Max        Crash cost             Activity                           Predecessors           Time (weeks)             Crash*    per week                   A                                none                                    6                          6                N/A                   B                                none                                    5                          2               $500                   C                                A                                       3                          2             $1000                   D                                A, B                                    4                          2             $2000                   E                                 C, D                                    5                          2             $1250                   F                                D                                       6                          2             $1000                                                                                                 *Shortest possible time for the task Draw the project network and list the...
Embassy Club Condominium, located on the west coast of Florida, is undertaking a summer renovation of...
Embassy Club Condominium, located on the west coast of Florida, is undertaking a summer renovation of its main building. The project is scheduled to begin May 1, and a September 1 (17-week) completion date is desired. The condominium manager identified the following renovation activities and their estimated times: Immediate Activity Predecessor Time A — 3 B — 4 C — 2 D A, B, C 2 E A, D 8 F C, D 7 G D, E 5 H F...
Given is a CPM project network diagram as shown below. Activity Start A B C D...
Given is a CPM project network diagram as shown below. Activity Start A B C D E F G H End days 0 2 6 8 3 4 2 3 2 0 a) The Project Completion time = ___ days. b) The Earliest Start time, ES, of Activity G = ____ days. c) The Latest Finish time, LF, of Acitivity C = ____ days. d) The critical activities are = ____ (ex. Fill in answer as: ABCD)
Given is a CPM project network diagram as shown below. Activity Start A B C D...
Given is a CPM project network diagram as shown below. Activity Start A B C D E F G H End days 0 2 6 8 3 4 2 3 2 0 a) The Project Completion time = ____ days. b) The Earliest Start time, ES, of Activity G = ____ days. c) The Latest Finish time, LF, of Acitivity C = ____ days. d) The critical activities are = ____ (ex. Fill in answer as: ABCD)
1. Given is a PERT project network diagram as shown below: Activity Start A B C...
1. Given is a PERT project network diagram as shown below: Activity Start A B C D E F G H I J K End Time 0 18 24 21 38 28 34 22 20 34 34 16 0    a) The Project Completion time =   b) The Earliest Start time, ES, of Activity F =   c) The Earliest Start time, ES, of Activity K =   d) The Latest Start time, LS, of Activity E =   e) The non-critical activities...
The following activities are part of a project to be scheduled using CPM: ACTIVITY IMMEDIATE PREDECESSOR...
The following activities are part of a project to be scheduled using CPM: ACTIVITY IMMEDIATE PREDECESSOR TIME (WEEKS) A — 7 B A 6 C A 2 D C 4 E B D 3 F D 4 G E F 6 a. Draw the network b. What is the critical path c. How many weeks will it take to complete the project d. Identify the early start, early finish, late start, and late finish for each activity in the project...
Q1. Which of the following statements regarding Critical Path Method (CPM) networks is true? A) There...
Q1. Which of the following statements regarding Critical Path Method (CPM) networks is true? A) There can be multiple critical paths on the same project, all with different durations. B) The early finish of an activity is the latest early start of all preceding activities. C) The late start of an activity is its late finish plus its duration. D) If a specific project has multiple critical paths, all of them will not have the same duration. E) B) and...
Sch.W Foundry, a metalwork plant in Quebec, has just decided to make a major investment in...
Sch.W Foundry, a metalwork plant in Quebec, has just decided to make a major investment in new air pollution control equipment. The plant, however, must be shut during this installation process. Sch.W’s board of directors estimates that the company can survive no more than 16 weeks without production in full swing. The managing partner wants to make sure the installation of the filtering system progresses smoothly and on time. The activities involved in the foundry project are presented in the...
Fill out the charts with the correct information. Activity Optimistic Most Probable Pessimistic A 3 8...
Fill out the charts with the correct information. Activity Optimistic Most Probable Pessimistic A 3 8 13 B 5 7 9 C 5 12 19 D 2 5 8 E 5 9 19 F 4 8 18 G 9 15 21 H 4 6 14 If required, round your answers to two decimal places. A.) Find the critical path. Activity Expected Time Variance A B C D E F G H Earliest Latest Earliest Latest Critical Activity Start Start Finish...