Question

Development of Version 2.0 of a particular accounting software product is being considered by Jose​ Noguera's...

Development of Version 2.0 of a particular accounting software product is being considered by Jose​ Noguera's technology firm in Baton Rouge. The activities necessary for the completion of this project are listed in the following​ table:

Activity Normal Time (weeks) Crash Time (weeks) Normal Cost Total Cost with Crashing Immediate Predecessors(s)
A 4 3 $2,200 $2,850 ---
B 2 1 $2,100 $2,700 ---
C 3 3 $750 $750 ---
D 8 4 $2,500 $2,800 A
E 6 3 $800 $1,250 B
F 3 2 $3,200 $4,400 C
G 4 2 $1,400 $1,800 D, E

​a) Based on the given information regarding the activities for the​ project, the project length​ = _______ weeks ?

b) The total cost required for completing this project on normal time​ = _______ ?

​c) If you wish to reduce the time required to complete this project by 1​ week, which activity should be​ crashed, and how much will this increase the total​ cost?

The critical path with the longest length through the project is  _______ ?

Homework Answers

Answer #1

Path and Duration are:

ADG = 16

BEG = 12

CF = 6

a) Project length = 16 weeks

b) Total cost = 200+2100+750+2500+800+3200+1400 = 12,950 $

c) To reduce project length by 1 week, need to reduce from path ADG.

Cost of crashing per week = (Crash cost-Normal cost)/(Normal time-Crash time)

Crashing cost of A = (2850-2200)/(4-3) = 650

Crashing cost of D = (2800-2500)/(8-4) = 75

Crashing cost of G = (1800-1400)/(4-2) = 200

So, Crash D by 1 week with increase in cost by 75$ in the Total cost of 12950$

The critical path with longest length is ADG

Know the answer?
Your Answer:

Post as a guest

Your Name:

What's your source?

Earn Coins

Coins can be redeemed for fabulous gifts.

Not the answer you're looking for?
Ask your own homework help question
Similar Questions
Use the following data for question below. Activity Normal Time (weeks) Crash Time (weeks) Normal Cost...
Use the following data for question below. Activity Normal Time (weeks) Crash Time (weeks) Normal Cost Total Cost with Crashing Pred 1 Pred 2 A 10 7 $200 $400 B 15 10 $250 $600 C 13 8 $600 $1,500 A B D 14 10 $800 $1,200 A B E 8 4 $1,000 $3,000 C D F 12 6 $1,200 $1,800 C D G 7 6 $700 $1,400 E F H 5 3 $500 $900 E F If the project must...
The information for project X is shown below. What are the critical path and the completion...
The information for project X is shown below. What are the critical path and the completion time of the project? Crashing Costs Activity Preceding Normal Time 1st Week 2nd Week K — 8 weeks $4100 — L K 6 weeks 3250 — N K 1 week 450 450 M L 5 weeks 3000 3500 J N 4 weeks 500 — Q J,M 6 weeks 4000 4000 KLMQ, 25 weeks KLNMJQ: 25 weeks KNJQ, 25 weeks KNJQ, 30 weeks KLMQ, 30...
Given the information below: (Use normal time to calculate original path) a) Which activity(s) should be...
Given the information below: (Use normal time to calculate original path) a) Which activity(s) should be crashed and what is the cost to reduce the project completion time from 22 to 21 days? b) Which activity(s) should be crashed and what is the cost to reduce the project completion time from 21 to 20 days? c) Which activity(s) should be crashed and what is the cost to reduce the project completion time from 20 to19 days? d) What is the...
Office Automation, Inc., developed a proposal for introducing a new computerized office system that will standardize...
Office Automation, Inc., developed a proposal for introducing a new computerized office system that will standardize the electronic archiving of invoices for a particular company. Contained in the proposal is a list of activities that must be accomplished to complete the new office system project. Use the following relevant information about the activities: Immediate Time (weeks) Cost ($1000s) Activity Description Predecessor(s) Normal Crash Normal Crash A Plan needs — 13 8 30 130 B Order equipment A 9 6 120...
All information needed to solve this problem is present Problem 9-24 (Algorithmic) Office Automation, Inc., developed...
All information needed to solve this problem is present Problem 9-24 (Algorithmic) Office Automation, Inc., developed a proposal for introducing a new computerized office system that will standardize the electronic archiving of invoices for a particular company. Contained in the proposal is a list of activities that must be accomplished to complete the new office system project. Use the following relevant information about the activities: Immediate Time (weeks) Cost ($1000s) Activity Description Predecessor(s) Normal Crash Normal Crash A Plan needs...
A car dealership decided to add an annex to its sales office as a customer lounge....
A car dealership decided to add an annex to its sales office as a customer lounge. The project is divided into the activities listed in the following table. The immediate predecessor(s), times and costs, both normal and crashed, are given. To finish the project sooner, the dealership has to make time and cost tradeoffs. If the project needs to be finished in 25 weeks, you are required to formulate a linear programming model to decide about how much to crash...
An amateur race car driver needs to prepare for the next race season. He has the...
An amateur race car driver needs to prepare for the next race season. He has the following tasks that he needs to finish in 15 weeks: Activity Immediate Predecessors Normal Time (weeks) Crash Time (weeks) Normal Cost ($) Crash Cost ($) A - 8 4 4800 5400 B C,E 7 4 3900 4800 C A 7 2 5100 6600 D G 4 2 1200 2400 E A 9 3 3600 4800 F C,D 9 3 3300 6000 G A 7...
Consider a project having the following six activities:                                  
Consider a project having the following six activities:                                                      Immediate                                                  Max        Crash cost             Activity                           Predecessors           Time (weeks)             Crash*    per week                   A                                none                                    6                          6                N/A                   B                                none                                    5                          2               $500                   C                                A                                       3                          2             $1000                   D                                A, B                                    4                          2             $2000                   E                                 C, D                                    5                          2             $1250                   F                                D                                       6                          2             $1000                                                                                                 *Shortest possible time for the task Draw the project network and list the...
Activity A Duration 6 Predecessor - Crash weeks - Crashing cost per week - B 4...
Activity A Duration 6 Predecessor - Crash weeks - Crashing cost per week - B 4 A 2 $480 C 5 A 1 $380 D 6 A 3 $450 E 5 B 2 $430 F 4 B,C 3 $350 G 5 C,D 2 $410 H 6 D 2 $570 I 5 E,F 2 $540 J 6 E,F,G 2 $530 K 3 G,H 1 $550 L 4 I,J 1 $560 M 5 I,J,K - $620 N 6 H,K,J 1 $650 O...
17b-3) Use this info for questions 1 through 5.   Chuck’s Custom Boats (CCB) builds customer luxury...
17b-3) Use this info for questions 1 through 5.   Chuck’s Custom Boats (CCB) builds customer luxury yachts. CCB has landed a contract with a mysterious New York real estate developer, Mr. T. Relevant data on the project are shown below. The complication is that Mr. T wants delivery in 30 weeks or he will impose a penalty of $200 for each week his yacht is late. Determine the lowest cost plan for crashing this project. Note: All numbers are in...