Development of Version 2.0 of a particular accounting software product is being considered by Jose Noguera's technology firm in Baton Rouge. The activities necessary for the completion of this project are listed in the following table:
Activity | Normal Time (weeks) | Crash Time (weeks) | Normal Cost | Total Cost with Crashing | Immediate Predecessors(s) |
---|---|---|---|---|---|
A | 4 | 3 | $2,200 | $2,850 | --- |
B | 2 | 1 | $2,100 | $2,700 | --- |
C | 3 | 3 | $750 | $750 | --- |
D | 8 | 4 | $2,500 | $2,800 | A |
E | 6 | 3 | $800 | $1,250 | B |
F | 3 | 2 | $3,200 | $4,400 | C |
G | 4 | 2 | $1,400 | $1,800 | D, E |
a) Based on the given information regarding the activities for the project, the project length = _______ weeks ?
b) The total cost required for completing this project on normal time = _______ ?
c) If you wish to reduce the time required to complete this project by 1 week, which activity should be crashed, and how much will this increase the total cost?
The critical path with the longest length through the project is _______ ?
Path and Duration are:
ADG = 16
BEG = 12
CF = 6
a) Project length = 16 weeks
b) Total cost = 200+2100+750+2500+800+3200+1400 = 12,950 $
c) To reduce project length by 1 week, need to reduce from path ADG.
Cost of crashing per week = (Crash cost-Normal cost)/(Normal time-Crash time)
Crashing cost of A = (2850-2200)/(4-3) = 650
Crashing cost of D = (2800-2500)/(8-4) = 75
Crashing cost of G = (1800-1400)/(4-2) = 200
So, Crash D by 1 week with increase in cost by 75$ in the Total cost of 12950$
The critical path with longest length is ADG