Question

Activity Immediate Predecessor(s) Normal Time (wks) Crash Time (wks) Normal Cost ($) Crash Cost ($) A...

Activity

Immediate Predecessor(s)

Normal Time (wks)

Crash Time (wks)

Normal Cost ($)

Crash Cost ($)

A

4

1

5,000

8,000

B

5

3

8,000

10,000

C

A

1

1

4,000

4,000

D

B

6

3

6,000

12,000

E

B, C

7

6

4,000

7,000

F

D

7

6

4,000

7,000

  1. You are the manager of a project to improve a billing process at your firm. Table 3 contains the data you will need to conduct a cost analysis of the project. Indirect costs are $1,600 per week, and penalty costs are $1,200 per week after week 12.
    1. What is the minimum-cost schedule for this project?
    2. What is the difference in total project costs between the earliest completion time of the project using “normal” times and the minimum-cost schedule you derived in part (a)? minimum- cost schedule derived in part A was = 15 weeks.

Homework Answers

Answer #1

a.

Activity Predecessor Normal time Crash time Normal cost Crash cost Cost/
week
A - 4 1 5000 8000 1000
B - 5 3 8000 10000 1000
C A 1 1 4000 4000 NA
D B 6 3 6000 12000 2000
E B,C 7 6 4000 7000 3000
F D 7 6 4000 7000 3000

Cost/week of crashing = (Crash cost-normal cost)/(normal time-crash time)

The network diagram is drawn as shown:

The paths with times are given below:

Paths Time
A-C-E 12
B-D-F 18
B-E 12

hence path B-D-F taking 18 weeks is the critical path

Cost for normal project time = normal total cost of 31000

plus 1600 per week indirect costs + 1200 per week penalty post week 12

Here project is taking 18 weeks; Hence 6 weeks penalty

So total costs = 31000 + 1600X18 + 6X1200 = 67000

For the minimum cost schedule let us work at reducing the time

For the critical path B-D-F, B has the lowest cost of 1000
hence crashing B by 2 units results in project time going to 16
Additional cost of 2000 is incurred and there is a saving of 1600X2 = 3200 in indirect cost
and penalty saving of 1200X2 = 2400

Hence net cost saving = 3200+2400-2000 = 3600

Next let us reduce the next activity i.e. D by 3 week costing 6000
Hence project duration becomes 13 weeks

And there is a saving of 3X1600 + 3X1200 - 6000 = 2400

Now if we reduce activity F by one week it will cost us 3000 whereas benefit will only be 1600+1200 = 2800. Hence we cannot reduce cost further

So minimum cost = 67000 - 3600 - 2400 = 61000

b. Difference = 67000 - 61000 = 6000

Know the answer?
Your Answer:

Post as a guest

Your Name:

What's your source?

Earn Coins

Coins can be redeemed for fabulous gifts.

Not the answer you're looking for?
Ask your own homework help question
Similar Questions
Swimming Pool Installation: You are the project manager working for Mack's Pool Co. Your project consists...
Swimming Pool Installation: You are the project manager working for Mack's Pool Co. Your project consists of installing a new swimming pool at the local country club before Memorial Day weekend (pool opening weekend). You would like to find the minimum cost schedule for your project. There is a $9,000 per week penalty for each week the project is delayed beyond week 9. In addition, your project team determined that indirect costs are $15,000 per week. ACTIVITY Immediate Predecessor (s)...
Activity A Duration 6 Predecessor - Crash weeks - Crashing cost per week - B 4...
Activity A Duration 6 Predecessor - Crash weeks - Crashing cost per week - B 4 A 2 $480 C 5 A 1 $380 D 6 A 3 $450 E 5 B 2 $430 F 4 B,C 3 $350 G 5 C,D 2 $410 H 6 D 2 $570 I 5 E,F 2 $540 J 6 E,F,G 2 $530 K 3 G,H 1 $550 L 4 I,J 1 $560 M 5 I,J,K - $620 N 6 H,K,J 1 $650 O...
Given the information below: (Use normal time to calculate original path) a) Which activity(s) should be...
Given the information below: (Use normal time to calculate original path) a) Which activity(s) should be crashed and what is the cost to reduce the project completion time from 22 to 21 days? b) Which activity(s) should be crashed and what is the cost to reduce the project completion time from 21 to 20 days? c) Which activity(s) should be crashed and what is the cost to reduce the project completion time from 20 to19 days? d) What is the...
Use the following data for question below. Activity Normal Time (weeks) Crash Time (weeks) Normal Cost...
Use the following data for question below. Activity Normal Time (weeks) Crash Time (weeks) Normal Cost Total Cost with Crashing Pred 1 Pred 2 A 10 7 $200 $400 B 15 10 $250 $600 C 13 8 $600 $1,500 A B D 14 10 $800 $1,200 A B E 8 4 $1,000 $3,000 C D F 12 6 $1,200 $1,800 C D G 7 6 $700 $1,400 E F H 5 3 $500 $900 E F If the project must...
The following activities are part of a project to be scheduled using CPM: ACTIVITY IMMEDIATE PREDECESSOR...
The following activities are part of a project to be scheduled using CPM: ACTIVITY IMMEDIATE PREDECESSOR TIME (WEEKS) A — 7 B A 6 C A 2 D C 4 E B D 3 F D 4 G E F 6 a. Draw the network b. What is the critical path c. How many weeks will it take to complete the project d. Identify the early start, early finish, late start, and late finish for each activity in the project...
Following information is available about a project. Activity Activity Time (weeks) Immediate Predecessor(s) K 4 -...
Following information is available about a project. Activity Activity Time (weeks) Immediate Predecessor(s) K 4 - B 4 - C 5 - D 4 - E 6 K F 2 B,C,D G 4 E.F H 6 F Compute slack for each activity. Activity Slack K B C D E F G H
Activity Immediate Predecessor Optimistic Time Most-likely time Pessimistic Time A None 3 6 9 B A...
Activity Immediate Predecessor Optimistic Time Most-likely time Pessimistic Time A None 3 6 9 B A 3 5 7 C A 4 7 12 D B 4 8 10 E C 5 10 16 F D, E 3 4 5 G D, E 3 6 8 H F 5 6 10 I G 5 8 11 J H, I 3 3 3 (a). What is the expected time for each activity? (2 points) (b.) What is the variance for each...
Consider the network described in the table below. Activity Immediate Predecessor(s) Pessimistic Probable Optimistic J --...
Consider the network described in the table below. Activity Immediate Predecessor(s) Pessimistic Probable Optimistic J -- 15 10 8 K -- 9 8 7 L J 10 6 5 M J 3 3 3 N K,M 9 5 1 O K,M 10 7 4 P L,N 10 8 3 a. Calculate the expected duration of each activity. b. Calculate the expected duration and variance of the critical path. c. Calculate the probability that the project will be completed in fewer...
The university IT team is working on the implementation of a new software system for enrollment.  Using...
The university IT team is working on the implementation of a new software system for enrollment.  Using the following table, complete the requested tasks: Activity Immediate Predecessor Normal Crash Normal Crash A - 6 5 $900 $1,000 B A 8 6 $300 $400 C A 4 3 $500 $600 D B 5 3 $900 $1,200 E C, D 8 5 $1,000 $1,600 a. Draw the network diagram noting normal and crash times. b. What is the critical path? c. What is...
Do the following crashing problem “from scratch” Develop the time reduction and cost per unit time...
Do the following crashing problem “from scratch” Develop the time reduction and cost per unit time columns in the table. Units: Time is in days, cost is in $. Activity Immediate predecessor(s) Time Cost Crash Time Crash Cost Time Reduction Cost to Crash A -- 10 5000 10 5000 B A 12 1200 11 1300 C A 11 3600 9 4800 D B 5 300 4 600 E C 8 1000 6 2000 F E 9 2400 7 5400 G...