Question

Use the following data for question below. Activity Normal Time (weeks) Crash Time (weeks) Normal Cost...

Use the following data for question below.

Activity

Normal Time (weeks)

Crash Time (weeks)

Normal Cost

Total Cost with Crashing

Pred 1

Pred 2

A

10

7

$200

$400

B

15

10

$250

$600

C

13

8

$600

$1,500

A

B

D

14

10

$800

$1,200

A

B

E

8

4

$1,000

$3,000

C

D

F

12

6

$1,200

$1,800

C

D

G

7

6

$700

$1,400

E

F

H

5

3

$500

$900

E

F

If the project must be completed in 40 weeks, which activities should be crashed?

A. activities: B 5 weeks and F 3 weeks

B. none, the project will be completed in 40 weeks with no crashing

C. activities: B 5 weeks, D 1 week and F 4 weeks

D. activity B 2 weeks

Homework Answers

Answer #1

The answer is:

A. activities: B 5 weeks and F 3 weeks

Activity Normal Time (weeks) Crash Time (weeks) Normal Cost Total Cost with Crashing Pred 1 Pred 2 Pred 3 Pred 4 Crash days
A 10 7 200 400 0
B 15 10 250 600 5
C 13 8 600 1,500 A B 0
D 14 10 800 1,200 A B 0
E 8 4 1,000 3,000 C D 0
F 12 6 1,200 1,800 C D 3
G 7 6 700 1,400 E F 0
H 5 3 500 900 E F 0

Please give me a thumbs-up if this helps you out. Thank you!

Know the answer?
Your Answer:

Post as a guest

Your Name:

What's your source?

Earn Coins

Coins can be redeemed for fabulous gifts.

Not the answer you're looking for?
Ask your own homework help question
Similar Questions
Given the information below: (Use normal time to calculate original path) a) Which activity(s) should be...
Given the information below: (Use normal time to calculate original path) a) Which activity(s) should be crashed and what is the cost to reduce the project completion time from 22 to 21 days? b) Which activity(s) should be crashed and what is the cost to reduce the project completion time from 21 to 20 days? c) Which activity(s) should be crashed and what is the cost to reduce the project completion time from 20 to19 days? d) What is the...
Activity Immediate Predecessor(s) Normal Time (wks) Crash Time (wks) Normal Cost ($) Crash Cost ($) A...
Activity Immediate Predecessor(s) Normal Time (wks) Crash Time (wks) Normal Cost ($) Crash Cost ($) A — 4 1 5,000 8,000 B — 5 3 8,000 10,000 C A 1 1 4,000 4,000 D B 6 3 6,000 12,000 E B, C 7 6 4,000 7,000 F D 7 6 4,000 7,000 You are the manager of a project to improve a billing process at your firm. Table 3 contains the data you will need to conduct a cost analysis...
Activity A Duration 6 Predecessor - Crash weeks - Crashing cost per week - B 4...
Activity A Duration 6 Predecessor - Crash weeks - Crashing cost per week - B 4 A 2 $480 C 5 A 1 $380 D 6 A 3 $450 E 5 B 2 $430 F 4 B,C 3 $350 G 5 C,D 2 $410 H 6 D 2 $570 I 5 E,F 2 $540 J 6 E,F,G 2 $530 K 3 G,H 1 $550 L 4 I,J 1 $560 M 5 I,J,K - $620 N 6 H,K,J 1 $650 O...
13. In critical path management, which is a general rule for crashing activities? A. Crash activities...
13. In critical path management, which is a general rule for crashing activities? A. Crash activities on the critical path B. Crash activities that are not on the critical path C. Crash activities having the greatest number of predecessor activities D. Crash activities having the greatest number of following activities E. Crash activities having the lowest crashing costs 14. Suppose a project has a crash time of 40 weeks. The normal cost of the project is $60,000, and the crash...
Development of Version 2.0 of a particular accounting software product is being considered by Jose​ Noguera's...
Development of Version 2.0 of a particular accounting software product is being considered by Jose​ Noguera's technology firm in Baton Rouge. The activities necessary for the completion of this project are listed in the following​ table: Activity Normal Time (weeks) Crash Time (weeks) Normal Cost Total Cost with Crashing Immediate Predecessors(s) A 4 3 $2,200 $2,850 --- B 2 1 $2,100 $2,700 --- C 3 3 $750 $750 --- D 8 4 $2,500 $2,800 A E 6 3 $800 $1,250...
Office Automation, Inc., developed a proposal for introducing a new computerized office system that will standardize...
Office Automation, Inc., developed a proposal for introducing a new computerized office system that will standardize the electronic archiving of invoices for a particular company. Contained in the proposal is a list of activities that must be accomplished to complete the new office system project. Use the following relevant information about the activities: Immediate Time (weeks) Cost ($1000s) Activity Description Predecessor(s) Normal Crash Normal Crash A Plan needs — 13 8 30 130 B Order equipment A 9 6 120...
All information needed to solve this problem is present Problem 9-24 (Algorithmic) Office Automation, Inc., developed...
All information needed to solve this problem is present Problem 9-24 (Algorithmic) Office Automation, Inc., developed a proposal for introducing a new computerized office system that will standardize the electronic archiving of invoices for a particular company. Contained in the proposal is a list of activities that must be accomplished to complete the new office system project. Use the following relevant information about the activities: Immediate Time (weeks) Cost ($1000s) Activity Description Predecessor(s) Normal Crash Normal Crash A Plan needs...
Activity Immediate Predecessor Optimistic Time Most-likely time Pessimistic Time A None 3 6 9 B A...
Activity Immediate Predecessor Optimistic Time Most-likely time Pessimistic Time A None 3 6 9 B A 3 5 7 C A 4 7 12 D B 4 8 10 E C 5 10 16 F D, E 3 4 5 G D, E 3 6 8 H F 5 6 10 I G 5 8 11 J H, I 3 3 3 (a). What is the expected time for each activity? (2 points) (b.) What is the variance for each...
A partially solved PERT problem is detailed in the table below. Times are given in weeks....
A partially solved PERT problem is detailed in the table below. Times are given in weeks. Activity Immediate Predecessor(s) Optimistic Most Likely Pessimistic A -- 8 10 15 B -- 7 8 9 C A 5 6 10 D A 3 3 3 E B,D 1 5 9 F B,D 4 7 10 G C 3 8 10 H E 5 7 9 I E 4 5 8 J F 2 5 8 K H, I 1 3 6 a)...
The information for project X is shown below. What are the critical path and the completion...
The information for project X is shown below. What are the critical path and the completion time of the project? Crashing Costs Activity Preceding Normal Time 1st Week 2nd Week K — 8 weeks $4100 — L K 6 weeks 3250 — N K 1 week 450 450 M L 5 weeks 3000 3500 J N 4 weeks 500 — Q J,M 6 weeks 4000 4000 KLMQ, 25 weeks KLNMJQ: 25 weeks KNJQ, 25 weeks KNJQ, 30 weeks KLMQ, 30...
ADVERTISEMENT
Need Online Homework Help?

Get Answers For Free
Most questions answered within 1 hours.

Ask a Question
ADVERTISEMENT