Use the following data for question below.
Activity |
Normal Time (weeks) |
Crash Time (weeks) |
Normal Cost |
Total Cost with Crashing |
Pred 1 |
Pred 2 |
A |
10 |
7 |
$200 |
$400 |
||
B |
15 |
10 |
$250 |
$600 |
||
C |
13 |
8 |
$600 |
$1,500 |
A |
B |
D |
14 |
10 |
$800 |
$1,200 |
A |
B |
E |
8 |
4 |
$1,000 |
$3,000 |
C |
D |
F |
12 |
6 |
$1,200 |
$1,800 |
C |
D |
G |
7 |
6 |
$700 |
$1,400 |
E |
F |
H |
5 |
3 |
$500 |
$900 |
E |
F |
If the project must be completed in 40 weeks, which activities should be crashed?
A. activities: B 5 weeks and F 3 weeks
B. none, the project will be completed in 40 weeks with no crashing
C. activities: B 5 weeks, D 1 week and F 4 weeks
D. activity B 2 weeks
The answer is:
A. activities: B 5 weeks and F 3 weeks
Activity | Normal Time (weeks) | Crash Time (weeks) | Normal Cost | Total Cost with Crashing | Pred 1 | Pred 2 | Pred 3 | Pred 4 | Crash days | |
A | 10 | 7 | 200 | 400 | 0 | |||||
B | 15 | 10 | 250 | 600 | 5 | |||||
C | 13 | 8 | 600 | 1,500 | A | B | 0 | |||
D | 14 | 10 | 800 | 1,200 | A | B | 0 | |||
E | 8 | 4 | 1,000 | 3,000 | C | D | 0 | |||
F | 12 | 6 | 1,200 | 1,800 | C | D | 3 | |||
G | 7 | 6 | 700 | 1,400 | E | F | 0 | |||
H | 5 | 3 | 500 | 900 | E | F | 0 |