Question

Use the following data for problems 34, 35, and 36 Activity Activity Predecessor Time (days) A...

Use the following data for problems 34, 35, and 36

Activity

Activity Predecessor

Time (days)

A

--

4

B

--

12

C

A, B

15

D

A, B

8

E

A, B

6

F

C, D, E

14

G

C, D, E

3

H

F, G

6

  1. The expected completion time for the project above is?
    1. 27 days
    2. 68 days
    3. 47 days
    4. 30 days
  2. The critical path for the project is?
    1. B, C, F, H
    2. B, C, F, G, H
    3. A, C, F, G
    4. A, C, E, H
  3. How much slack is there in activity G?
    1. 7 days
    2. 8 days
    3. 11 days
    4. 0 days (no slack)

Homework Answers

Answer #1

The activity diagram is as follows.

(1)

The expected completion time for the project above is (C) 47 days.

(2)

The critical path for the project is (A) B, C, F, H.

(3)

For activity G,

  • Earliest stating time (EST) = 27 days
  • Latest finish time (LFT) = 41 days
  • Duration (d) = 3 days

So, slack = LFT - EST - d = (41-27-3) days = 11 days

Hence, slack in activity G is (C) 11 days.

Know the answer?
Your Answer:

Post as a guest

Your Name:

What's your source?

Earn Coins

Coins can be redeemed for fabulous gifts.

Not the answer you're looking for?
Ask your own homework help question
Similar Questions
Given the following information for a project, answer the following questions: Activity Predecessor Activity Time (days)...
Given the following information for a project, answer the following questions: Activity Predecessor Activity Time (days) A - 6 B - 8 C A, B 5 D B 4 E C 7 F C, D 3 G D 6 H E, F, G 5 Fill in the following table. Activity ES EF LS LF Slack CP A 0 No B Yes C Yes D No E Yes F No G 18 14 20 No H 25 20 25 Yes Draw...
A future construction project has the following activity relationships and activity time estimates (in days): Activity...
A future construction project has the following activity relationships and activity time estimates (in days): Activity Immediate Predecessor To Tm Tp A None 4 5 6 B None 3 6 21 C B 1 4 7 D A 2 5 8 E C, D 3 9 27 F C 3 6 15 G E, F 2 4 6 H F, G 2 2 2 Leave 2-decimal if not exact, do not round up, for example, 4.3268... will be kept as...
Activity Immediate Predecessor Optimistic Time Most-likely time Pessimistic Time A None 3 6 9 B A...
Activity Immediate Predecessor Optimistic Time Most-likely time Pessimistic Time A None 3 6 9 B A 3 5 7 C A 4 7 12 D B 4 8 10 E C 5 10 16 F D, E 3 4 5 G D, E 3 6 8 H F 5 6 10 I G 5 8 11 J H, I 3 3 3 (a). What is the expected time for each activity? (2 points) (b.) What is the variance for each...
Following information is available about a project. Activity Activity Time (weeks) Immediate Predecessor(s) K 4 -...
Following information is available about a project. Activity Activity Time (weeks) Immediate Predecessor(s) K 4 - B 4 - C 5 - D 4 - E 6 K F 2 B,C,D G 4 E.F H 6 F Compute slack for each activity. Activity Slack K B C D E F G H
The following activities are part of a project to be scheduled using CPM: ACTIVITY IMMEDIATE PREDECESSOR...
The following activities are part of a project to be scheduled using CPM: ACTIVITY IMMEDIATE PREDECESSOR TIME (WEEKS) A — 7 B A 6 C A 2 D C 4 E B D 3 F D 4 G E F 6 a. Draw the network b. What is the critical path c. How many weeks will it take to complete the project d. Identify the early start, early finish, late start, and late finish for each activity in the project...
Consider the following information for a project to add a drive-thru window at Crestview Bank.       Activity...
Consider the following information for a project to add a drive-thru window at Crestview Bank.       Activity Activity Time​ (weeks) Immediate​ Predecessor(s) A 6 − B 1 − C 9 − D 3 ​A, B E 6 B F 4 ​D, C G 5 ​E, C H 9 ​F, G b. Specify the critical path. The critical path is _____ and the project duration is_____ c. Calculate the slack for activities A and D.
The following information is known about a project: a. Draw a network diagram b. Calculate the...
The following information is known about a project: a. Draw a network diagram b. Calculate the ES, EF, LS, LF and slack time and find the critical path for this project Activity Activity Time (days) Immediate Predecessor A 12 B 9 C 10 A D 10 A,B E 24 B F 10 A G 35 C H 40 D I 15 A J 4 E,G,H K 6 F,I,J
Activity Completion (Days) Immediate Precedence A. Architectural Design 3 - B. Clearing of Land 6 A...
Activity Completion (Days) Immediate Precedence A. Architectural Design 3 - B. Clearing of Land 6 A C. Fencing of project site 7 A D. Digging of foundation 5 A E. Completion of foundation work 13 B,C F. Raising of pillars and block work. 8 C,D G. Roofing 11 D,F H. Furnishing of the cathedral 6 G,E a. Redraw the network diagram for the construction of the National Cathedral by using the above information provided in the table to complete the...
Given the following network and activity time estimates, determine earliest and latest activity times, slack, the...
Given the following network and activity time estimates, determine earliest and latest activity times, slack, the expected project completion time and variance, and the probability that the project will be completed in 28 days or less. TIME ESTIMATES (DAYS) ACTIVITY ACTIVITY PREDECESSOR a m b A - 5  8 17 B - 7 10 13 C A 3  5  7 D A 1  3  5 E B, C 4  6  8 F B, C 3  3  3 G D,E 3  ...
Problem 5-7 The following activities are part of a project to be scheduled using CPM: ACTIVITY...
Problem 5-7 The following activities are part of a project to be scheduled using CPM: ACTIVITY IMMEDIATE PREDECESSOR TIME (WEEKS) A — 7 B A 6 C A 2 D C 4 E B D 3 F D 4 G E F 6 b. What is the critical path? A-C-D-F-G A-C-D-E-G A-B-E-G A-B-D-F-G c. How many weeks will it take to complete the project? Number of weeks             d. How much slack does activity B have? Slack of activity B             week(s)