Question

The information for project X is shown below. What are the critical path and the completion...

The information for project X is shown below. What are the critical path and the completion time of the project?

Crashing Costs

Activity

Preceding

Normal Time

1st Week

2nd Week

K

8 weeks

$4100

L

K

6 weeks

3250

N

K

1 week

450

450

M

L

5 weeks

3000

3500

J

N

4 weeks

500

Q

J,M

6 weeks

4000

4000

KLMQ, 25 weeks

KLNMJQ: 25 weeks

KNJQ, 25 weeks

KNJQ, 30 weeks

KLMQ, 30 weeks

The information for project X is shown below. What is your recommendation if the imposed penalty is $3500 for each week the project is late and dead line is week 24?

Crashing Costs

Activity

Preceding

Normal Time

1st Week

2nd Week

K

8 weeks

$4100

L

K

6 weeks

3250

N

K

1 week

450

450

M

L

5 weeks

3000

3500

J

N

4 weeks

500

Q

J,M

6 weeks

4000

4000

Crash activity M by one week.

Crash activity N by one week.

The project does not need to be crashed because it ends before the deadline.

Do not crash the project because the penalty cost is higher than the minimum crashing cost.

Crash activity L by one week.

Homework Answers

Answer #1

Answer: Critical path = K-L-M-Q ; Project duration = 25 weeks

Answer: Crash Activity M by one week

Know the answer?
Your Answer:

Post as a guest

Your Name:

What's your source?

Earn Coins

Coins can be redeemed for fabulous gifts.

Not the answer you're looking for?
Ask your own homework help question
Similar Questions
Activity A Duration 6 Predecessor - Crash weeks - Crashing cost per week - B 4...
Activity A Duration 6 Predecessor - Crash weeks - Crashing cost per week - B 4 A 2 $480 C 5 A 1 $380 D 6 A 3 $450 E 5 B 2 $430 F 4 B,C 3 $350 G 5 C,D 2 $410 H 6 D 2 $570 I 5 E,F 2 $540 J 6 E,F,G 2 $530 K 3 G,H 1 $550 L 4 I,J 1 $560 M 5 I,J,K - $620 N 6 H,K,J 1 $650 O...
17b-3) Use this info for questions 1 through 5.   Chuck’s Custom Boats (CCB) builds customer luxury...
17b-3) Use this info for questions 1 through 5.   Chuck’s Custom Boats (CCB) builds customer luxury yachts. CCB has landed a contract with a mysterious New York real estate developer, Mr. T. Relevant data on the project are shown below. The complication is that Mr. T wants delivery in 30 weeks or he will impose a penalty of $200 for each week his yacht is late. Determine the lowest cost plan for crashing this project. Note: All numbers are in...
The project manager of a task force planning the construction of a domed stadium had hoped...
The project manager of a task force planning the construction of a domed stadium had hoped to be able to complete construction prior to the start of the next college football season. After reviewing construction time estimates, it now appears that a certain amount of crashing will be needed to ensure project completion before the season opener. Given the following time and cost estimates, determine a minimum-cost crashing schedule that will shave five weeks off the project length. Note: No...
Consider the network described in the table below. Activity Immediate Predecessor(s) Pessimistic Probable Optimistic J --...
Consider the network described in the table below. Activity Immediate Predecessor(s) Pessimistic Probable Optimistic J -- 15 10 8 K -- 9 8 7 L J 10 6 5 M J 3 3 3 N K,M 9 5 1 O K,M 10 7 4 P L,N 10 8 3 a. Calculate the expected duration of each activity. b. Calculate the expected duration and variance of the critical path. c. Calculate the probability that the project will be completed in fewer...
Mega Mart Store is a discount department store badly in need of renovation. To avoid loss...
Mega Mart Store is a discount department store badly in need of renovation. To avoid loss of sales and disruption of customer shopping habits, Mega Mart wants to complete this renovation without closing the store itself, by temporarily co-locating goods from one area of the store into another, creating open spaces for renovation and re-occupation. Mega Mart is divided into four basic areas of goods: Clothing, Electronics, House Wares and Foodstuffs. Each of these areas will need to be temporarily...
A car dealership decided to add an annex to its sales office as a customer lounge....
A car dealership decided to add an annex to its sales office as a customer lounge. The project is divided into the activities listed in the following table. The immediate predecessor(s), times and costs, both normal and crashed, are given. To finish the project sooner, the dealership has to make time and cost tradeoffs. If the project needs to be finished in 25 weeks, you are required to formulate a linear programming model to decide about how much to crash...
1- Which study design(s) require collecting information about participants over time? (Select all that apply.) Cross-sectional...
1- Which study design(s) require collecting information about participants over time? (Select all that apply.) Cross-sectional Case-control Meta-analysis Cohort Experimental Ecological 2- For the following research question, identify the exposure, outcome and population. Does the number of parks in a neighborhood decrease crime rates within neighborhoods across the inland empire?       -       A.       B.       C.       D.    Exposure       -       A.       B.       C.   ...
Fill in the table below, using the information on this handout, based on what is best...
Fill in the table below, using the information on this handout, based on what is best for the client. Bill and Judy Dodge are married, and are each 35 years old. They have three children, with ages as of Dec. 31, 2019 as listed: Mary, age 5, Peter, age 2, and Lucy, age 4 months. Assume they did not itemize for their 2018 federal income tax return. The W2 table is for the 2019 income tax year. Assume tax laws...
a. 1/1/18 Office Supplies 350          Accounts Payable 350 To record on credit payment for office...
a. 1/1/18 Office Supplies 350          Accounts Payable 350 To record on credit payment for office supplies b. 1/1/18 Prepaid Insurance 1800          Cash 1800 To record purchase of 24-month insurance for cash c. 1/1/18 Computer Equipment 2100          Accounts Payable 2100 To record purache of computer equipment d. 1/5/18 Merchandise Inventory 1275          Accounts Payable 1275 To record purchase of merchandis for resale e. 1/8/18 Accounts Payble 2100         Sales Discount 42         Cash 2058 To record full payment...
1. What is an ISP (Integrated Service Provider) for supply chains? (1 point) A. A consultant...
1. What is an ISP (Integrated Service Provider) for supply chains? (1 point) A. A consultant agency which integrates the supply chain for companies B. A 2 PL or a 3PL, but not a 4PL C. A company supplying transportation and warehousing services D. A logistics service company specialized in suppling VAS (value added services) 2. What characterizes a 4 PL? (1 point) A. They are non-asset based and provides integrated services primarily supplied by asset based providers, for example...
ADVERTISEMENT
Need Online Homework Help?

Get Answers For Free
Most questions answered within 1 hours.

Ask a Question
ADVERTISEMENT