Consider an item by the name of Z which has components 2X’s and one Y. Gross Requirements for Z are 0, 35, 55, 60 respectively. The inventory status of each as well as lead times is as below. Find the 4 week MRP schedule for all components.
On Hand Lot Size Lead Time
Z 100 LFL 1
X 20 100 + 1
Y 10 150+ 1
a. What is the On Hand Inventory of Z at the beginning of Period 3?
b. What is the On Hand Inventory of Z at the beginning of Period 4?
c. What is the NET POQ for Z in Period 4?
d. What is the Gross requirements of X in Period 2?
e. What is the Gross requirements of Y in Period 2?
f. What is the Gross requirements of X in Period 3?
e. What is the Gross requirements of Y in Period 3?
f. What is the Planned orders of X in Period 2?
Below is the screenshot of the MRP schedule -
a. What is the On Hand Inventory of Z at the beginning of Period 3 - 65
b. What is the On Hand Inventory of Z at the beginning of Period 4 - 10
c. What is the NET POQ for Z in Period 4 - 50
d. What is the Gross requirements of X in Period 2- 0
e. What is the Gross requirements of Y in Period 2 - 0
f. What is the Gross requirements of X in Period 3 - 100
e. What is the Gross requirements of Y in Period 3 - 50
f. What is the Planned orders of X in Period 2 - 100