Problem 12:9
Assume that you are the manager of a shop that assembles power
tools. You have just received an order for 57 chain saws, which are
to be shipped at the start of week 8. Pertinent information on the
saws is
Item | Lead Time (weeks) | On Hand | Components | |
Saw | 2 | 15 | A(2), B(1), C(4) | |
A | 1 | 10 | E(3), D(1) | |
B | 2 | 5 | D(2), F(3) | |
C | 2 | 65 | E(2), D(2) | |
D | 1 | 20 | ||
E | 1 | 10 | ||
F | 2 | 30 | ||
Develop the material requirements plan for component E using
lot-for-lot ordering. (Leave no cells blank - be certain to
enter "0" wherever required.)
Item: E(3) & E(2) LT = 1 wk. | Beg. Inv. | 1 | 2 | 3 | 4 | 5 | 6 | 7 | 8 |
Gross requirements | |||||||||
Scheduled receipts | |||||||||
Projected on hand | |||||||||
Net requirements | |||||||||
Planned order receipt | |||||||||
Planned order release | |||||||||
Following is the bill of material
Saw
Order received = 57
On-Hand inventory = 15
Balance Order = 57 – 15
= 42
Total saw required by the company is 42
No. of A component required = 2 x 42
= 84
On-Hand inventory = 10
Total A component required = 84 – 10
= 74
No. of E component required (Predecessor A) = 74 x 3
= 222
No. of C component required = 4 x 42
= 168
On-Hand inventory = 65
Total C component required = 168 – 65
= 103
No. of E component required (Predecessor C) = 103 x 2
= 206
The lead time of Saw is 2 week. Therefore, Saw must execute in week 6 so that it fully available in the week 8
The lead time of A is 1 week, so it must execute in 5th week to receive in 6th week. Similarly, lead time of C is 2 week and therefore it must execute in 4th week
Following is the MRP of the component E