Question

Problem L You work for a landscaping company. You need four poles and 2 cubic yards...

Problem L

You work for a landscaping company.

You need four poles and 2 cubic yards of mulch for every tree that is planted.

Calculate the Material Requirements Plan below.

The beginning inventory for each item has been given.

Week

Beg. Inv.

1

2

3

4

5

6

7

8

Quantity

72

65

30

64

Tree

Lead Time = 1 wk

Lot for Lot

Gross Requirements

Scheduled Receipts

Projected On-Hand

2

Net Requirements

Planned Order Receipts

Planned Order Releases

Poles

Lead Time = 1 wk

Lot Size of 12

Gross Requirements

Scheduled Receipts

Projected On-Hand

14

Net Requirements

Planned Order Receipts

Planned Order Releases

Mulch

(in cubic yards)

Lead Time = 1 wk

Lot-Size of 9

Gross Requirements

Scheduled Receipts

Projected On-Hand

9

Net Requirements

Planned Order Receipts

Planned Order Releases

Homework Answers

Answer #1

Find the MRP answer shown below.


We need to remember a few points.

  • The net requirement for a period is the gross requirement – on hand inventory of previous period.
  • The on hand inventory for current period is the planned order receipt + scheduled receipt – net requirement
  • Planned order receipt should be in multiple of lot size. The value should exceed the net requirement if it cannot match
  • Planned order release will be the lead time ahead of the planned order receipt.
Know the answer?
Your Answer:

Post as a guest

Your Name:

What's your source?

Earn Coins

Coins can be redeemed for fabulous gifts.

Not the answer you're looking for?
Ask your own homework help question
Similar Questions
Problem 12:9 Assume that you are the manager of a shop that assembles power tools. You...
Problem 12:9 Assume that you are the manager of a shop that assembles power tools. You have just received an order for 57 chain saws, which are to be shipped at the start of week 8. Pertinent information on the saws is Item Lead Time (weeks) On Hand Components Saw 2 15 A(2), B(1), C(4) A 1 10 E(3), D(1) B 2 5 D(2), F(3) C 2 65 E(2), D(2) D 1 20 E 1 10 F 2 30   ...
Question 18 Product D has gross requirements, on-hand inventory, and scheduled receipts as indicated in the...
Question 18 Product D has gross requirements, on-hand inventory, and scheduled receipts as indicated in the time-phased inventory status record below. Its lead time is 3 weeks. Item D 1 2 3 4 5 6 Gross Requirements 100 300 100 400 100 50 On Hand/ Scheduled Receipts 700 Net Requirements A Planned Order Releases B The value of entry A is: A. 100 B. 200 C. 300 D. 700 E. None of the above. Reset Selection Question 19 Product D...
Product Y is made from one component P, three components Q, and one 2 components R.  P...
Product Y is made from one component P, three components Q, and one 2 components R.  P is made from two parts S, Q is made from one S, and R is made from two part S and three part T.  Other data includes: Part                 Lead time             Lot size                   On hand                 Scheduled receipts         Safety Stock Y                         1                                 lot-for-lot               30                                              none                                          5 P                        2                                   40                              15                                              none                                          none Q                        2                                 100                               8                                               none                                          8 R                        3                                 120                             30                                              none                                          none S                         2                                 500                             20                                              500, week 1                          20 T                         2                                 600                           370                                             none                                          50 a.    Draw the BOM for product Y. b. Complete the MRP explosion for product Y.  Identify any problems, and discuss possible solutions Master Production Schedule Finished...
In 300 words or more answser the following questions: 1.  There are two basic Aggregate Planning Strategies:...
In 300 words or more answser the following questions: 1.  There are two basic Aggregate Planning Strategies: Level Capacity: Maintaining a steady rate of regular-time output while meeting variations in demand by a combination of options. Chase Demand: Matching capacity to demand; the planned output for a period is the expected demand for that period. Which of these two strategies do you recommend? Why? 2. Discuss the following MRP Processing components and their interrelationship. You may use different scenarios for Lot...
Consider the following requirements for a certain product. Period 1 2 3 4 5 6 7...
Consider the following requirements for a certain product. Period 1 2 3 4 5 6 7 8 Gross requirements 0 200 200 500 0 400 0 400 Beginning inventory = 500 units Setup cost = $500 per setup Lead time = 1 week Holding cost = $3 per unit per week a. Develop the lot-for-lot MRP table. b. Calculate the total relevant costs. Answer: Period 1 2 3 4 5 6 7 8 Gross requirements 0 200 200 500 0...
MRP IN MANUFACTURING 1. Each E subassembly is made up of 6 G parts, 20 H...
MRP IN MANUFACTURING 1. Each E subassembly is made up of 6 G parts, 20 H parts, and ONE J part. Draw the product structure tree diagram. Using the product structure tree diagram and the information provided below, Completeth e following MRP Report Transaction processing for PART E and PART G ONLY if the following information is provided: ( Do not order more quantity of any resources that are needed to maintain the production) E subassembly G part H part...
Given the following data, develop MRP tables and indicate the Planned order releases for all items....
Given the following data, develop MRP tables and indicate the Planned order releases for all items. A is an MPS item. A needs 2 C's and 3 F’s. F needs 3 C’s. (I eliminated scheduled receipts since the problem did not have scheduled receipts.) Period 6 7 8 GR-A 400 0 300 On hand inventory for all items is 200 and lead time for A is 1 period, and LT for all other items is 2 periods. Use lot-for-lot for...
Given the following data, develop MRP tables and indicate the Planned order releases for all items....
Given the following data, develop MRP tables and indicate the Planned order releases for all items. A is an MPS item. A needs 2 C's and 3 F’s. F needs 3 C’s. (I eliminated scheduled receipts since the problem did not have scheduled receipts.) Period 6 7 8 GR-A 400 0 300 On hand inventory for all items is 200 and lead time for A is 1 period, and LT for all other items is 2 periods. Use lot-for-lot for...
Given the following data, develop MRP tables and indicate the Planned order releases for all items....
Given the following data, develop MRP tables and indicate the Planned order releases for all items. A is an MPS item. A needs 4 C's, 2 F’s and 5 G’s. F needs 4 C’s and G needs 2 C’s. (I eliminated scheduled receipts since the problem did not have scheduled receipts.) Period 6 7 8 GR-A 0 100 900 On hand inventory for all items is 300 and lead time for A is 1 period, and LT for all other...
Given the following data, develop MRP tables and indicate the Planned order releases for all items....
Given the following data, develop MRP tables and indicate the Planned order releases for all items. A is an MPS item. A needs 4 C's, 2 F’s and 5 G’s. F needs 4 C’s and G needs 2 C’s. (I eliminated scheduled receipts since the problem did not have scheduled receipts.) Period 6 7 8 GR-A 0 100 900 On hand inventory for all items is 300 and lead time for A is 1 period, and LT for all other...
ADVERTISEMENT
Need Online Homework Help?

Get Answers For Free
Most questions answered within 1 hours.

Ask a Question
ADVERTISEMENT