Question

Consider the following requirements for a certain product. Period 1 2 3 4 5 6 7...

Consider the following requirements for a certain product.

Period

1

2

3

4

5

6

7

8

Gross requirements

0

200

200

500

0

400

0

400

Beginning inventory = 500 units

Setup cost = $500 per setup

Lead time = 1 week

Holding cost = $3 per unit per week

a. Develop the lot-for-lot MRP table.

b. Calculate the total relevant costs.

Answer:

Period

1

2

3

4

5

6

7

8

Gross requirements

0

200

200

500

0

400

0

400

Projected on hand

500

Net Requirement

Planned Reciept

Planned Order

Setup Cost=

Holding Cost=

Total Cost =

Kindly, Explain the methods used in details !

Homework Answers

Answer #1
Item   Period 1 2 3 4 5 6 7 8
Gross requirements 0 200 200 500 0 400 0 400
Scheduled receipts 0 0 0 0 0 0 0 0
Projected on hand 500 500 300 100 0 0 0 0 0
Net requirements 0 0 0 400 0 400 0 400
Planned order receipts 0 0 0 400 0 400 0 400
Planned order releases 0 0 400 0 400 0 400 0

Avg inventory ( ending inventory) = 900

Inventory cost = 900*3 =2700

Number of set ups = 3

Set up cost = 3*500=1500

Total cost = 4200

Know the answer?
Your Answer:

Post as a guest

Your Name:

What's your source?

Earn Coins

Coins can be redeemed for fabulous gifts.

Not the answer you're looking for?
Ask your own homework help question
Similar Questions
Solve the MRP Item                         LLC    Leadtime      Lot Sizing Rule
Solve the MRP Item                         LLC    Leadtime      Lot Sizing Rule Skate 1 1 Lot for Lot Lace 1 1 FOQ = 500 Box 1 2 FOQ = 500 Board 1 2 Lot for Lot Wheel Assembly 2 1 FOQ = 800 Body 2 2 Lot for Lot Axle 2 1 Lot for Lot Hardware 2 3 FOQ = 1500 BOM                                                                         Draw Product Structures Here Boxed Skates       Skates (2)             Body             Axle (2)             Hardware             Wheel Assembly (2)       Laces (2)       Box Skateboard       Board       Wheel Assembly (4)       Axle (2)...
Solve the MRP Item                         LLC    Leadtime      Lot Sizing Rule
Solve the MRP Item                         LLC    Leadtime      Lot Sizing Rule Skate 1 1 Lot for Lot Lace 1 1 FOQ = 500 Box 1 2 FOQ = 500 Board 1 2 Lot for Lot Wheel Assembly 2 1 FOQ = 800 Body 2 2 Lot for Lot Axle 2 1 Lot for Lot Hardware 2 3 FOQ = 1500 BOM                                                                         Draw Product Structures Here Boxed Skates       Skates (2)             Body             Axle (2)             Hardware             Wheel Assembly (2)       Laces (2)       Box Skateboard       Board       Wheel Assembly (4)       Axle (2)...
The MRP gross requirements for Item X are shown here for the next 10 weeks. Lead...
The MRP gross requirements for Item X are shown here for the next 10 weeks. Lead time for A is two weeks, and setup cost is $9. There is a carrying cost of $0.02 per unit per week. Beginning inventory is 75 units. WEEK 1 2 3 4 5 6 7 8 9 10 Gross requirements 20 10 15 45 10 30 90 20 45 160 Use the least total cost lot-sizing method to determine the quantity to order with...
The time-phased net requirements for the base assembly in a table lamp over the next six...
The time-phased net requirements for the base assembly in a table lamp over the next six weeks are: Week 1 2 3 4 5 6 Requirements 335 240 180 340 320 200 The setup cost for the construction of the base assembly is $200, and the holding cost is $0.30 per assembly per week. What lot sizing do you obtain from the EOQ formula? Determine the lot sizes using the Silver–Meal heuristic. Determine the lot sizes using the least unit...
The MRP gross requirements for Item A are shown here for the next 10 weeks. Lead...
The MRP gross requirements for Item A are shown here for the next 10 weeks. Lead time for A is three weeks and setup cost is $10. There is a carrying cost of $0.010 per unit per week. Beginning inventory is 85 units. WEEK 1 2 3 4 5 6 7 8 9 10 Gross requirements 20 55 10 22 70 87 19 63 210 58 Use the least total cost and the least unit cost lot-sizing methods to determine...
Period Forecast 1 200 2 500 3 300 4 400 5 200 6 200 Regular time:...
Period Forecast 1 200 2 500 3 300 4 400 5 200 6 200 Regular time: $20 per unit (maximum of 280 units per period) Overtime:    $30 per unit (maximum of 40 units per period) Subcontracting:    Not available Beginning inventory:   None Carrying cost: $10 per unit per period Backorder cost: $50 per unit per period What is the first period in which overtime should be scheduled in order to minimize total cost for the aggregate plan?
Calculate the cost of operating under the different MRP lot sizing techniques: Lot-for-Lot (L4L) Economic Order...
Calculate the cost of operating under the different MRP lot sizing techniques: Lot-for-Lot (L4L) Economic Order Quantity (EOQ) Least Total Cost (LTC) Least Unit Cost (LUC) Compare your results and state which method is the most cost efficient in this situation. Consider the following MRP lot sizing problem: Cost per item $50 Order/setup cost $75 Inventory carrying cost per item per week $1 Weekly net requirements: 1 2 3 4 5 6 7 8 75 90 100 90 80 95...
Problem L You work for a landscaping company. You need four poles and 2 cubic yards...
Problem L You work for a landscaping company. You need four poles and 2 cubic yards of mulch for every tree that is planted. Calculate the Material Requirements Plan below. The beginning inventory for each item has been given. Week Beg. Inv. 1 2 3 4 5 6 7 8 Quantity 72 65 30 64 Tree Lead Time = 1 wk Lot for Lot Gross Requirements Scheduled Receipts Projected On-Hand 2 Net Requirements Planned Order Receipts Planned Order Releases Poles...
Product Y is made from one component P, three components Q, and one 2 components R.  P...
Product Y is made from one component P, three components Q, and one 2 components R.  P is made from two parts S, Q is made from one S, and R is made from two part S and three part T.  Other data includes: Part                 Lead time             Lot size                   On hand                 Scheduled receipts         Safety Stock Y                         1                                 lot-for-lot               30                                              none                                          5 P                        2                                   40                              15                                              none                                          none Q                        2                                 100                               8                                               none                                          8 R                        3                                 120                             30                                              none                                          none S                         2                                 500                             20                                              500, week 1                          20 T                         2                                 600                           370                                             none                                          50 a.    Draw the BOM for product Y. b. Complete the MRP explosion for product Y.  Identify any problems, and discuss possible solutions Master Production Schedule Finished...
MRP IN MANUFACTURING 1. Each E subassembly is made up of 6 G parts, 20 H...
MRP IN MANUFACTURING 1. Each E subassembly is made up of 6 G parts, 20 H parts, and ONE J part. Draw the product structure tree diagram. Using the product structure tree diagram and the information provided below, Completeth e following MRP Report Transaction processing for PART E and PART G ONLY if the following information is provided: ( Do not order more quantity of any resources that are needed to maintain the production) E subassembly G part H part...