Question

Question 18 Product D has gross requirements, on-hand inventory, and scheduled receipts as indicated in the...

Question 18

Product D has gross requirements, on-hand inventory, and scheduled receipts as indicated in the time-phased inventory status record below. Its lead time is 3 weeks.

Item D

1

2

3

4

5

6

Gross Requirements

100

300

100

400

100

50

On Hand/ Scheduled Receipts

700

Net Requirements

A

Planned Order Releases

B

The value of entry A is:

A. 100

B. 200

C. 300

D. 700

E. None of the above.

Reset Selection

Question 19

Product D has gross requirements, on-hand inventory, and scheduled receipts as indicated in the time-phased inventory status record below. Its lead time is 3 weeks.

Item D

1

2

3

4

5

6

Gross Requirements

100

300

100

400

100

50

On Hand/ Scheduled Receipts

700

Net Requirements

A

Planned Order Releases

B

The value of entry B is:

A. 50

B. 100

C. 200

D. 400

E. None of the above

Homework Answers

Answer #1

18. option B is the right answer. i.e. net requriements of 200 units.

the total units hold in hands are 700 units. the requirements and utilization for the first three slots are 100+ 300+100= 500.

in the 4th slot the gross requirements are 400 units, but the available units are 200. hence the net requirements (additional units) 200.

19. the additional requirements is for 350 units. as the lead time is 3 weeks, means it takes 3 weeks to deliver the product after order.

if we need to deliver the additional units on day 4, i.e. 200 units, and additional units on day 5 and 6, we need total of 350 units. or if we need to deliver only on day 5 and 6 we need 150 units.

but we do not have any of these options in the listed, hence option E is correct.

Know the answer?
Your Answer:

Post as a guest

Your Name:

What's your source?

Earn Coins

Coins can be redeemed for fabulous gifts.

Not the answer you're looking for?
Ask your own homework help question
Similar Questions
Problem L You work for a landscaping company. You need four poles and 2 cubic yards...
Problem L You work for a landscaping company. You need four poles and 2 cubic yards of mulch for every tree that is planted. Calculate the Material Requirements Plan below. The beginning inventory for each item has been given. Week Beg. Inv. 1 2 3 4 5 6 7 8 Quantity 72 65 30 64 Tree Lead Time = 1 wk Lot for Lot Gross Requirements Scheduled Receipts Projected On-Hand 2 Net Requirements Planned Order Receipts Planned Order Releases Poles...
Consider an item by the name of Z which has components 2X’s and one Y. Gross...
Consider an item by the name of Z which has components 2X’s and one Y. Gross Requirements for Z are 0, 35, 55, 60 respectively. The inventory status of each as well as lead times is as below. Find the 4 week MRP schedule for all components.                               On Hand              Lot Size                Lead Time Z                            100                        LFL                    1 X                               20                     100 +                  1 Y                               10                     150+                   1                                a. What is the On Hand Inventory of Z...
Solve the MRP Item                         LLC    Leadtime      Lot Sizing Rule
Solve the MRP Item                         LLC    Leadtime      Lot Sizing Rule Skate 1 1 Lot for Lot Lace 1 1 FOQ = 500 Box 1 2 FOQ = 500 Board 1 2 Lot for Lot Wheel Assembly 2 1 FOQ = 800 Body 2 2 Lot for Lot Axle 2 1 Lot for Lot Hardware 2 3 FOQ = 1500 BOM                                                                         Draw Product Structures Here Boxed Skates       Skates (2)             Body             Axle (2)             Hardware             Wheel Assembly (2)       Laces (2)       Box Skateboard       Board       Wheel Assembly (4)       Axle (2)...
Solve the MRP Item                         LLC    Leadtime      Lot Sizing Rule
Solve the MRP Item                         LLC    Leadtime      Lot Sizing Rule Skate 1 1 Lot for Lot Lace 1 1 FOQ = 500 Box 1 2 FOQ = 500 Board 1 2 Lot for Lot Wheel Assembly 2 1 FOQ = 800 Body 2 2 Lot for Lot Axle 2 1 Lot for Lot Hardware 2 3 FOQ = 1500 BOM                                                                         Draw Product Structures Here Boxed Skates       Skates (2)             Body             Axle (2)             Hardware             Wheel Assembly (2)       Laces (2)       Box Skateboard       Board       Wheel Assembly (4)       Axle (2)...
Product Y is made from one component P, three components Q, and one 2 components R.  P...
Product Y is made from one component P, three components Q, and one 2 components R.  P is made from two parts S, Q is made from one S, and R is made from two part S and three part T.  Other data includes: Part                 Lead time             Lot size                   On hand                 Scheduled receipts         Safety Stock Y                         1                                 lot-for-lot               30                                              none                                          5 P                        2                                   40                              15                                              none                                          none Q                        2                                 100                               8                                               none                                          8 R                        3                                 120                             30                                              none                                          none S                         2                                 500                             20                                              500, week 1                          20 T                         2                                 600                           370                                             none                                          50 a.    Draw the BOM for product Y. b. Complete the MRP explosion for product Y.  Identify any problems, and discuss possible solutions Master Production Schedule Finished...
Consider the following requirements for a certain product. Period 1 2 3 4 5 6 7...
Consider the following requirements for a certain product. Period 1 2 3 4 5 6 7 8 Gross requirements 0 200 200 500 0 400 0 400 Beginning inventory = 500 units Setup cost = $500 per setup Lead time = 1 week Holding cost = $3 per unit per week a. Develop the lot-for-lot MRP table. b. Calculate the total relevant costs. Answer: Period 1 2 3 4 5 6 7 8 Gross requirements 0 200 200 500 0...
Problem 12:9 Assume that you are the manager of a shop that assembles power tools. You...
Problem 12:9 Assume that you are the manager of a shop that assembles power tools. You have just received an order for 57 chain saws, which are to be shipped at the start of week 8. Pertinent information on the saws is Item Lead Time (weeks) On Hand Components Saw 2 15 A(2), B(1), C(4) A 1 10 E(3), D(1) B 2 5 D(2), F(3) C 2 65 E(2), D(2) D 1 20 E 1 10 F 2 30   ...
Given the following data, develop MRP tables and indicate the Planned order releases for all items....
Given the following data, develop MRP tables and indicate the Planned order releases for all items. A is an MPS item. A needs 2 C's and 3 F’s. F needs 3 C’s. (I eliminated scheduled receipts since the problem did not have scheduled receipts.) Period 6 7 8 GR-A 400 0 300 On hand inventory for all items is 200 and lead time for A is 1 period, and LT for all other items is 2 periods. Use lot-for-lot for...
Given the following data, develop MRP tables and indicate the Planned order releases for all items....
Given the following data, develop MRP tables and indicate the Planned order releases for all items. A is an MPS item. A needs 2 C's and 3 F’s. F needs 3 C’s. (I eliminated scheduled receipts since the problem did not have scheduled receipts.) Period 6 7 8 GR-A 400 0 300 On hand inventory for all items is 200 and lead time for A is 1 period, and LT for all other items is 2 periods. Use lot-for-lot for...
1.    A firm desires to control inventory levels so as to minimize the sum of holding...
1.    A firm desires to control inventory levels so as to minimize the sum of holding and order costs. It costs the firm $20 to place an order. The firm estimates its yearly inventory carrying costs at 20%. Weekly demand is 100 units, and there are 50 weeks in the work year. The item costs $10 per unit. The EOQ is approximately: A. 316 B. 224 C. 145 D. 45 E. 32 2.    One end item A requires three component...
ADVERTISEMENT
Need Online Homework Help?

Get Answers For Free
Most questions answered within 1 hours.

Ask a Question
ADVERTISEMENT