Question

The MRP gross requirements for Item A are shown here for the next 10 weeks. Lead...

The MRP gross requirements for Item A are shown here for the next 10 weeks. Lead time for A is three weeks and setup cost is $10. There is a carrying cost of $0.010 per unit per week. Beginning inventory is 85 units.

WEEK

1 2 3 4 5 6 7 8 9 10
Gross requirements 20 55 10 22 70 87 19 63 210 58

Use the least total cost and the least unit cost lot-sizing methods to determine the quantity to order with the first order released with each method and which periods' requirements will be covered by that order.

Quantity Ordered Periods Covered
  Least total cost         (Click to select)4 to 94 to 54 to 644 to 109 to 104 to 794 to 8       
  Least unit cost         (Click to select)4 to 84 to 94 to 54 to 104 to 694 to 79 to 104       

Homework Answers

Answer #1

Below is the screenshot of the formula applied -

Below is the screenshot of the result calculated -

Know the answer?
Your Answer:

Post as a guest

Your Name:

What's your source?

Earn Coins

Coins can be redeemed for fabulous gifts.

Not the answer you're looking for?
Ask your own homework help question
Similar Questions
The MRP gross requirements for Item X are shown here for the next 10 weeks. Lead...
The MRP gross requirements for Item X are shown here for the next 10 weeks. Lead time for A is two weeks, and setup cost is $9. There is a carrying cost of $0.02 per unit per week. Beginning inventory is 75 units. WEEK 1 2 3 4 5 6 7 8 9 10 Gross requirements 20 10 15 45 10 30 90 20 45 160 Use the least total cost lot-sizing method to determine the quantity to order with...
Calculate the cost of operating under the different MRP lot sizing techniques: Lot-for-Lot (L4L) Economic Order...
Calculate the cost of operating under the different MRP lot sizing techniques: Lot-for-Lot (L4L) Economic Order Quantity (EOQ) Least Total Cost (LTC) Least Unit Cost (LUC) Compare your results and state which method is the most cost efficient in this situation. Consider the following MRP lot sizing problem: Cost per item $50 Order/setup cost $75 Inventory carrying cost per item per week $1 Weekly net requirements: 1 2 3 4 5 6 7 8 75 90 100 90 80 95...
Given this net requirements schedule for a product for the next six weeks, if it cost...
Given this net requirements schedule for a product for the next six weeks, if it cost $3,000 to set up the production line to produce this product and it costs $6 to carry one unit of the product in inventory for one week, develop a schedule of completed production lots for the product and compute the cost of your schedule by using these methods: Week (Net Requirements) 1 (500 2 (700) 3 (500) 4 (700) 5 (400) 6 (600) a....
Solve the MRP Item                         LLC    Leadtime      Lot Sizing Rule
Solve the MRP Item                         LLC    Leadtime      Lot Sizing Rule Skate 1 1 Lot for Lot Lace 1 1 FOQ = 500 Box 1 2 FOQ = 500 Board 1 2 Lot for Lot Wheel Assembly 2 1 FOQ = 800 Body 2 2 Lot for Lot Axle 2 1 Lot for Lot Hardware 2 3 FOQ = 1500 BOM                                                                         Draw Product Structures Here Boxed Skates       Skates (2)             Body             Axle (2)             Hardware             Wheel Assembly (2)       Laces (2)       Box Skateboard       Board       Wheel Assembly (4)       Axle (2)...
Solve the MRP Item                         LLC    Leadtime      Lot Sizing Rule
Solve the MRP Item                         LLC    Leadtime      Lot Sizing Rule Skate 1 1 Lot for Lot Lace 1 1 FOQ = 500 Box 1 2 FOQ = 500 Board 1 2 Lot for Lot Wheel Assembly 2 1 FOQ = 800 Body 2 2 Lot for Lot Axle 2 1 Lot for Lot Hardware 2 3 FOQ = 1500 BOM                                                                         Draw Product Structures Here Boxed Skates       Skates (2)             Body             Axle (2)             Hardware             Wheel Assembly (2)       Laces (2)       Box Skateboard       Board       Wheel Assembly (4)       Axle (2)...
The time-phased net requirements for the base assembly in a table lamp over the next six...
The time-phased net requirements for the base assembly in a table lamp over the next six weeks are: Week 1 2 3 4 5 6 Requirements 335 240 180 340 320 200 The setup cost for the construction of the base assembly is $200, and the holding cost is $0.30 per assembly per week. What lot sizing do you obtain from the EOQ formula? Determine the lot sizes using the Silver–Meal heuristic. Determine the lot sizes using the least unit...
Question 5: Forecasting (8 p) The table below shows the demand (in units per quarter) of...
Question 5: Forecasting (8 p) The table below shows the demand (in units per quarter) of a specific product in the past three years. Quarter Year 1 2 3 4 2015 350 254 176 228 2016 367 258 169 236 2017 342 250 166 228 Predict demand in quarter 1 and quarter 2 of 2018, given that the demand forecast for the whole year is a total of 1,040 units. Question 6: DRP (8 p) A central DC supplies a...
21. A client who was admitted with pneumonia was complaining of abdominal pain from frequent non-...
21. A client who was admitted with pneumonia was complaining of abdominal pain from frequent non- productive coughing. When he does produce sputum, it is watery and yellowish-green. Which of the following are appropriate nursing interventions at this time? Select all that apply Give him a pillow for splinting Administer antitussive syrup, 30mg ordered prn. Place him in appropriate positions for postural drainage Encourage him to increase his oral fluid intake Request an order for increasing flow rate. 22. A...
In February 2012, the Pepsi Next product was launched into the US market. This case study...
In February 2012, the Pepsi Next product was launched into the US market. This case study provides students with an interesting insight into PepsiCo’s new product process and some of the challenging decisions that they faced along the way. Pepsi Next Case Study Introduction Pepsi Next was launched by PepsiCo into the US market in February 2012, and has since been rolled out to various international markets (for instance, it was launched in Australia in September 2012). The new product...
Delta airlines case study Global strategy. Describe the current global strategy and provide evidence about how...
Delta airlines case study Global strategy. Describe the current global strategy and provide evidence about how the firms resources incompetencies support the given pressures regarding costs and local responsiveness. Describe entry modes have they usually used, and whether they are appropriate for the given strategy. Any key issues in their global strategy? casestudy: Atlanta, June 17, 2014. Sea of Delta employees and their families swarmed between food trucks, amusement park booths, and entertainment venues that were scattered throughout what would...
ADVERTISEMENT
Need Online Homework Help?

Get Answers For Free
Most questions answered within 1 hours.

Ask a Question
ADVERTISEMENT