Question

Product Y is made from one component P, three components Q, and one 2 components R.  P...

Product Y is made from one component P, three components Q, and one 2 components R.  P is made from two parts S, Q is made from one S, and R is made from two part S and three part T.  Other data includes:

Part                 Lead time             Lot size                   On hand                 Scheduled receipts         Safety Stock

Y                         1                                 lot-for-lot               30                                              none                                          5

P                        2                                   40                              15                                              none                                          none

Q                        2                                 100                               8                                               none                                          8

R                        3                                 120                             30                                              none                                          none

S                         2                                 500                             20                                              500, week 1                          20

T                         2                                 600                           370                                             none                                          50

a.    Draw the BOM for product Y.

b. Complete the MRP explosion for product Y.  Identify any problems, and discuss possible solutions

Master Production Schedule

Finished Item Y

1

2

3

4

5

6

7

8

9

10

Finished Item Y MPS Start

30

30

30

30

30

30

30

30

Item Y                     Lead time = 1 week          Minimum order quantity = Lot for Lot Safety Stock = 5    

Week

1

2

3

4

5

6

7

8

9

10

Gross Requirements

Scheduled Receipts

Proj. ending inv.              30

Net Requirements

Planned Receipts

Planned Order Releases

Service Requirements

Homework Answers

Answer #1

a) BOM for product Y is following

b) MRP record for product Y and its components is following

There are following problems:

i) There is no safety stock of product Y in week 1

ii) Net requirement of components P, Q, S and T in week 1 and 2, cannot be satisfied until week 3, because of lead time of 2 weeks

iii) Net requirement of components R in week 1, 2 and 3, cannot be satisfied until week 4, because of lead time of 3 weeks.

Possible solution is purchase of these components from outside supplier.

Know the answer?
Your Answer:

Post as a guest

Your Name:

What's your source?

Earn Coins

Coins can be redeemed for fabulous gifts.

Not the answer you're looking for?
Ask your own homework help question
Similar Questions
Problem L You work for a landscaping company. You need four poles and 2 cubic yards...
Problem L You work for a landscaping company. You need four poles and 2 cubic yards of mulch for every tree that is planted. Calculate the Material Requirements Plan below. The beginning inventory for each item has been given. Week Beg. Inv. 1 2 3 4 5 6 7 8 Quantity 72 65 30 64 Tree Lead Time = 1 wk Lot for Lot Gross Requirements Scheduled Receipts Projected On-Hand 2 Net Requirements Planned Order Receipts Planned Order Releases Poles...
Solve the MRP Item                         LLC    Leadtime      Lot Sizing Rule
Solve the MRP Item                         LLC    Leadtime      Lot Sizing Rule Skate 1 1 Lot for Lot Lace 1 1 FOQ = 500 Box 1 2 FOQ = 500 Board 1 2 Lot for Lot Wheel Assembly 2 1 FOQ = 800 Body 2 2 Lot for Lot Axle 2 1 Lot for Lot Hardware 2 3 FOQ = 1500 BOM                                                                         Draw Product Structures Here Boxed Skates       Skates (2)             Body             Axle (2)             Hardware             Wheel Assembly (2)       Laces (2)       Box Skateboard       Board       Wheel Assembly (4)       Axle (2)...
Solve the MRP Item                         LLC    Leadtime      Lot Sizing Rule
Solve the MRP Item                         LLC    Leadtime      Lot Sizing Rule Skate 1 1 Lot for Lot Lace 1 1 FOQ = 500 Box 1 2 FOQ = 500 Board 1 2 Lot for Lot Wheel Assembly 2 1 FOQ = 800 Body 2 2 Lot for Lot Axle 2 1 Lot for Lot Hardware 2 3 FOQ = 1500 BOM                                                                         Draw Product Structures Here Boxed Skates       Skates (2)             Body             Axle (2)             Hardware             Wheel Assembly (2)       Laces (2)       Box Skateboard       Board       Wheel Assembly (4)       Axle (2)...
Product A is made from components B and C. Item​ B, in​ turn, is made from...
Product A is made from components B and C. Item​ B, in​ turn, is made from D and E. Item C also is an intermediate​ item, made from F and H.​ Finally, intermediate item E is made from H and G. Note that item H has two parents. The following are item lead​ times: Item A B C D E F G H Lead Time​ (weeks) 1 1 2 2 6 4 4 6 a. What lead time​ (in weeks)...
Question 18 Product D has gross requirements, on-hand inventory, and scheduled receipts as indicated in the...
Question 18 Product D has gross requirements, on-hand inventory, and scheduled receipts as indicated in the time-phased inventory status record below. Its lead time is 3 weeks. Item D 1 2 3 4 5 6 Gross Requirements 100 300 100 400 100 50 On Hand/ Scheduled Receipts 700 Net Requirements A Planned Order Releases B The value of entry A is: A. 100 B. 200 C. 300 D. 700 E. None of the above. Reset Selection Question 19 Product D...
Problem 12:9 Assume that you are the manager of a shop that assembles power tools. You...
Problem 12:9 Assume that you are the manager of a shop that assembles power tools. You have just received an order for 57 chain saws, which are to be shipped at the start of week 8. Pertinent information on the saws is Item Lead Time (weeks) On Hand Components Saw 2 15 A(2), B(1), C(4) A 1 10 E(3), D(1) B 2 5 D(2), F(3) C 2 65 E(2), D(2) D 1 20 E 1 10 F 2 30   ...
Will’s Welded Widgets (WWW) makes its Q Model from components R, S and T. Component R...
Will’s Welded Widgets (WWW) makes its Q Model from components R, S and T. Component R is made from two units of component X and one unit of component Y. Component T is made from one unit of component V and 3 units of component Z. Using the WWW given information, calculate the replenishment lead time for the Q Model assuming that you have no beginning inventories.
TASK:   Complete the MRP record for component C as it would appear at the beginning of...
TASK:   Complete the MRP record for component C as it would appear at the beginning of week 2. MRP record for component C as it would appear at the beginning of week 1. Week 1 2 3 4 5 6 Gross Requirements 15 30 25 25 10 20 Scheduled Receipts 40 0 0 0 0 0 Projected Available Balance 50 20 35 10 0 20 Planned Order Receipts 0 0 40 0 0 40 Planned Order Releases 40 0 0...
Assume that Product Z is made up of four units of A and two units of...
Assume that Product Z is made up of four units of A and two units of C and two units of D. A is made of three units of D. The total demand for Z is 2000 units Additional information is the following:                                     Item Z A C D On hand 750 500 460 2,000 Safety stock 0 120 140 200 Allocated 0 80 160 200 Scheduled Receipts -- 500 in Week 1 1,500 in Week 1 -- Provide the...
Consider the following requirements for a certain product. Period 1 2 3 4 5 6 7...
Consider the following requirements for a certain product. Period 1 2 3 4 5 6 7 8 Gross requirements 0 200 200 500 0 400 0 400 Beginning inventory = 500 units Setup cost = $500 per setup Lead time = 1 week Holding cost = $3 per unit per week a. Develop the lot-for-lot MRP table. b. Calculate the total relevant costs. Answer: Period 1 2 3 4 5 6 7 8 Gross requirements 0 200 200 500 0...