Product Y is made from one component P, three components Q, and one 2 components R. P is made from two parts S, Q is made from one S, and R is made from two part S and three part T. Other data includes:
Part Lead time Lot size On hand Scheduled receipts Safety Stock
Y 1 lot-for-lot 30 none 5
P 2 40 15 none none
Q 2 100 8 none 8
R 3 120 30 none none
S 2 500 20 500, week 1 20
T 2 600 370 none 50
a. Draw the BOM for product Y.
b. Complete the MRP explosion for product Y. Identify any problems, and discuss possible solutions
Master Production Schedule |
|||||||||||
Finished Item Y |
1 |
2 |
3 |
4 |
5 |
6 |
7 |
8 |
9 |
10 |
|
Finished Item Y MPS Start |
30 |
30 |
30 |
30 |
30 |
30 |
30 |
30 |
Item Y Lead time = 1 week Minimum order quantity = Lot for Lot Safety Stock = 5
Week |
1 |
2 |
3 |
4 |
5 |
6 |
7 |
8 |
9 |
10 |
Gross Requirements |
||||||||||
Scheduled Receipts |
||||||||||
Proj. ending inv. 30 |
||||||||||
Net Requirements |
||||||||||
Planned Receipts |
||||||||||
Planned Order Releases |
||||||||||
Service Requirements |
a) BOM for product Y is following
b) MRP record for product Y and its components is following
There are following problems:
i) There is no safety stock of product Y in week 1
ii) Net requirement of components P, Q, S and T in week 1 and 2, cannot be satisfied until week 3, because of lead time of 2 weeks
iii) Net requirement of components R in week 1, 2 and 3, cannot be satisfied until week 4, because of lead time of 3 weeks.
Possible solution is purchase of these components from outside supplier.