The MRP gross requirements for Item X are shown here for the next 10 weeks. Lead time for A is two weeks, and setup cost is $9. There is a carrying cost of $0.02 per unit per week. Beginning inventory is 75 units.
WEEK |
||||||||||
1 | 2 | 3 | 4 | 5 | 6 | 7 | 8 | 9 | 10 | |
Gross requirements | 20 | 10 | 15 | 45 | 10 | 30 | 90 | 20 | 45 | 160 |
Use the least total cost lot-sizing method to determine the
quantity to order with the first order released and which periods'
requirements will be covered by that order. |
week | 1 | 2 | 3 | 4 | 5 | 6 | 7 | 8 | 9 | 10 |
Gross requirement | 20 | 10 | 15 | 45 | 10 | 30 | 90 | 20 | 45 | 160 |
Beginning stock | 75 | 55 | 45 | 30 | 0 | 0 | 0 | 0 | 0 | 0 |
Net requirement | 0 | 0 | 0 | 15 | 10 | 30 | 90 | 20 | 45 | 160 |
Carrying cost | ||||||||
Future requirement | In period | Cumulative order qty | Excess inventory | Weeks carried | Order cost | This period | Cumulative | Total cost |
15 | 4 | 15 | 0 | 0 | $9 | $0.00 | $0.00 | $9.0 |
10 | 5 | 25 | 10 | 1 | $9 | $0.20 | $0.20 | $9.2 |
30 | 6 | 55 | 30 | 2 | $9 | $1.20 | $1.40 | $10.4 |
90 | 7 | 145 | 90 | 3 | $9 | $5.40 | $6.80 | $15.8 |
20 | 8 | 165 | 20 | 4 | $9 | $1.60 | $8.40 | $17.4 |
45 | 9 | 210 | 45 | 5 | $9 | $4.50 | $12.90 | $21.9 |
160 | 10 | 370 | 160 | 6 | $9 | $19.20 | $32.10 | $41.1 |
Note that the cumulative carrying cost of 210 order size is $12.9 which is more than $9 i.e. the ordering cost.
So, we will stick to the previous order size i.e. 165.
So, 165 units should be ordered in the first order for periods 4, 5, 6, 7, and 8