Question

The MRP gross requirements for Item X are shown here for the next 10 weeks. Lead...

The MRP gross requirements for Item X are shown here for the next 10 weeks. Lead time for A is two weeks, and setup cost is $9. There is a carrying cost of $0.02 per unit per week. Beginning inventory is 75 units.

WEEK

1 2 3 4 5 6 7 8 9 10
Gross requirements 20 10 15 45 10 30 90 20 45 160

Use the least total cost lot-sizing method to determine the quantity to order with the first order released and which periods' requirements will be covered by that order.
Least total cost method indicates that  units should be ordered to cover the needs for periods (Click to select)4 through 104 through 94 through 74 through 8.

Homework Answers

Answer #1
week 1 2 3 4 5 6 7 8 9 10
Gross requirement 20 10 15 45 10 30 90 20 45 160
Beginning stock 75 55 45 30 0 0 0 0 0 0
Net requirement 0 0 0 15 10 30 90 20 45 160
Carrying cost
Future requirement In period Cumulative order qty Excess inventory Weeks carried Order cost This period Cumulative Total cost
15 4 15 0 0 $9 $0.00 $0.00 $9.0
10 5 25 10 1 $9 $0.20 $0.20 $9.2
30 6 55 30 2 $9 $1.20 $1.40 $10.4
90 7 145 90 3 $9 $5.40 $6.80 $15.8
20 8 165 20 4 $9 $1.60 $8.40 $17.4
45 9 210 45 5 $9 $4.50 $12.90 $21.9
160 10 370 160 6 $9 $19.20 $32.10 $41.1

Note that the cumulative carrying cost of 210 order size is $12.9 which is more than $9 i.e. the ordering cost.

So, we will stick to the previous order size i.e. 165.

So, 165 units should be ordered in the first order for periods 4, 5, 6, 7, and 8

Know the answer?
Your Answer:

Post as a guest

Your Name:

What's your source?

Earn Coins

Coins can be redeemed for fabulous gifts.

Not the answer you're looking for?
Ask your own homework help question
Similar Questions
The MRP gross requirements for Item A are shown here for the next 10 weeks. Lead...
The MRP gross requirements for Item A are shown here for the next 10 weeks. Lead time for A is three weeks and setup cost is $10. There is a carrying cost of $0.010 per unit per week. Beginning inventory is 85 units. WEEK 1 2 3 4 5 6 7 8 9 10 Gross requirements 20 55 10 22 70 87 19 63 210 58 Use the least total cost and the least unit cost lot-sizing methods to determine...
Calculate the cost of operating under the different MRP lot sizing techniques: Lot-for-Lot (L4L) Economic Order...
Calculate the cost of operating under the different MRP lot sizing techniques: Lot-for-Lot (L4L) Economic Order Quantity (EOQ) Least Total Cost (LTC) Least Unit Cost (LUC) Compare your results and state which method is the most cost efficient in this situation. Consider the following MRP lot sizing problem: Cost per item $50 Order/setup cost $75 Inventory carrying cost per item per week $1 Weekly net requirements: 1 2 3 4 5 6 7 8 75 90 100 90 80 95...
Solve the MRP Item                         LLC    Leadtime      Lot Sizing Rule
Solve the MRP Item                         LLC    Leadtime      Lot Sizing Rule Skate 1 1 Lot for Lot Lace 1 1 FOQ = 500 Box 1 2 FOQ = 500 Board 1 2 Lot for Lot Wheel Assembly 2 1 FOQ = 800 Body 2 2 Lot for Lot Axle 2 1 Lot for Lot Hardware 2 3 FOQ = 1500 BOM                                                                         Draw Product Structures Here Boxed Skates       Skates (2)             Body             Axle (2)             Hardware             Wheel Assembly (2)       Laces (2)       Box Skateboard       Board       Wheel Assembly (4)       Axle (2)...
Solve the MRP Item                         LLC    Leadtime      Lot Sizing Rule
Solve the MRP Item                         LLC    Leadtime      Lot Sizing Rule Skate 1 1 Lot for Lot Lace 1 1 FOQ = 500 Box 1 2 FOQ = 500 Board 1 2 Lot for Lot Wheel Assembly 2 1 FOQ = 800 Body 2 2 Lot for Lot Axle 2 1 Lot for Lot Hardware 2 3 FOQ = 1500 BOM                                                                         Draw Product Structures Here Boxed Skates       Skates (2)             Body             Axle (2)             Hardware             Wheel Assembly (2)       Laces (2)       Box Skateboard       Board       Wheel Assembly (4)       Axle (2)...
The time-phased net requirements for the base assembly in a table lamp over the next six...
The time-phased net requirements for the base assembly in a table lamp over the next six weeks are: Week 1 2 3 4 5 6 Requirements 335 240 180 340 320 200 The setup cost for the construction of the base assembly is $200, and the holding cost is $0.30 per assembly per week. What lot sizing do you obtain from the EOQ formula? Determine the lot sizes using the Silver–Meal heuristic. Determine the lot sizes using the least unit...
Consider the following requirements for a certain product. Period 1 2 3 4 5 6 7...
Consider the following requirements for a certain product. Period 1 2 3 4 5 6 7 8 Gross requirements 0 200 200 500 0 400 0 400 Beginning inventory = 500 units Setup cost = $500 per setup Lead time = 1 week Holding cost = $3 per unit per week a. Develop the lot-for-lot MRP table. b. Calculate the total relevant costs. Answer: Period 1 2 3 4 5 6 7 8 Gross requirements 0 200 200 500 0...
For a particular SKU, the lead time is 6 weeks, the average demand is 100 units...
For a particular SKU, the lead time is 6 weeks, the average demand is 100 units a week, and safety stock is 200 units. What is the average inventory if 10 weeks’ supply is ordered at one time? What is the order point? The standard deviation of demand during the lead time is 100 units. Calculate the safety stock required for the following service levels: 75%, 80%, 85%, 90%, 95%, and 99.99%. Calculate the change in safety stock required to...
An end item’s demand forecasts for the next 10 weeks are 30, 20, 35, 50, 25,...
An end item’s demand forecasts for the next 10 weeks are 30, 20, 35, 50, 25, 25, 0, 40, 0, and 50 units. The current on-hand inventory is 80 units. The order policy is to produce in lots of 100. The booked customer orders for the item, starting with week 1, are 22, 30, 15, 9, 0, 0, 5, 3, 7, and 0 units. At present, no MPS quantities are on-hand for this item. The lead time is 2 weeks....
Required information George Caloz & Frères, located in Grenchen, Switzerland, makes luxury custom watches in small...
Required information George Caloz & Frères, located in Grenchen, Switzerland, makes luxury custom watches in small lots. One of the company’s products, a platinum diving watch, goes through an etching process. The company has recorded etching costs as follows over the last six weeks: Week Units Total Etching Cost 1 14 $ 27 2 11 $ 20 3 16 $ 30 4 10 $ 20 5 12 $ 25 6 15 $ 28 78 $ 150 For planning purposes, management...
Exercise 5A-5 (Algo) Least-Squares Regression [LO5-11] George Caloz & Frères, located in Grenchen, Switzerland, makes luxury...
Exercise 5A-5 (Algo) Least-Squares Regression [LO5-11] George Caloz & Frères, located in Grenchen, Switzerland, makes luxury custom watches in small lots. One of the company’s products, a platinum diving watch, goes through an etching process. The company has recorded etching costs as follows over the last six weeks: Week Units Total Etching Cost 1 5 $ 22 2 7 21 3 10 25 4 5 20 5 16 28 6 17 32 60 $ 148 For planning purposes, management would...
ADVERTISEMENT
Need Online Homework Help?

Get Answers For Free
Most questions answered within 1 hours.

Ask a Question
ADVERTISEMENT