Question

Pirmin's bike shop is behind on a custom bike and needs to crash 8 hours of...

Pirmin's bike shop is behind on a custom bike and needs to crash 8 hours of time from the 8-step project. Suppose Pirmin calls the customer and asks for a project extension, reducing the amount of time he needs to crash.

Activity

Normal

Duration (hr)

Normal

Cost ($)

Crash

Duration (hr)

Crash

Cost ($)

Immediate

Predecessors

A 2 10 2 N/A NONE
B 3 15 2 23 A
C 5 25 4 30 B
D 3 20 1 24 C
E 6 30 4 45 C
F 1 5 1 N/A C,E
G 7 35 6 50 F
H 10 50 7 80 D,G

A. Draw (with a computer application) the network diagram.

B. Calculate the maximum time-savings available on a $25 crash budget.

C. Calculate the cost to crash four hours of savings.

Homework Answers

Answer #1

The project network is as follows:

The network consists of 3 paths as follows:

A-B-C-D-H, duration is 23 days

A-B-C-F-G-H, duration is 28 days

A-B-C-E-F-G-H, duration is 34 days

Determine crashing cost per hour as follows:

Normal Duration (Hr.)

Normal Cost

Crash Duration

Crash Cost

Allowable crashing

Crashing cost per hour

Activity

NT

NC

CT

CC

CC - NC

NT - CT

(CC - NC)/(NT - CT)

A

2

$10

2

NA

$0

0

$0

B

3

$15

2

$23

$8

1

$8

C

5

$25

4

$30

$5

1

$5

D

3

$20

1

$24

$4

2

$2

E

6

$30

4

$45

$15

2

$7.5

F

1

$5

1

NA

$0

0

$0

G

7

$35

6

$50

$15

1

$15

H

10

$50

7

$80

$30

3

$10

TOTALS

$190

Crashing Sequence:

According to crashing principle, crash only critical path and crash the critical activities with lowest crashing cost per hour.

Crashing Sequence

0

1

2

3

4

Critical Paths

A-B-C-E-F-G-H

A-B-C-E-F-G-H

A-B-C-E-F-G-H

A-B-C-E-F-G-H

Lowest crashing cost per week activity (crashing cost)

C ($5/ hour)

E ($7.5/ hr)

E ($7.5/ hr)

B ($8/ hr)

Activity Crashed

None

C

E

E

B

Crashing Duration

0

1

1

1

1

Project duration

34

33

32

31

30

A-B-C-D-H

23

22

22

22

21

A-B-C-F-G-H

28

27

28

28

27

A-B-C-E-F-G-H

34

33

32

31

30

Crash cost

$0

$5

$7.5

$7.5

$8

Cum. Crash cost

$0

$5

$12.5

$20

$28

b.

Crashing activity B by 1 hour, the cumulative crashing cost is increases to $28. To obtain duration for $25 cumulative crashing cost, crash the activity B by fraction of hour. For $25 cost, crash duration = $5/$8 = 0.625 hours.

Thus, if the activity B is crashed by 0.625 hours the cost will increase by $5.

Total project duration will be 30.625 hours.

Maximum time saved for $25 crash budget = 34 hours – 30.625 hours = 3.375 hours

c.

To save four hours or to complete the project in 34 – 4 = 30 hours, the cumulative crash cost is $28. It requires to crash activities C, E, and B by 1, 2 and 1 hours respectively.

Know the answer?
Your Answer:

Post as a guest

Your Name:

What's your source?

Earn Coins

Coins can be redeemed for fabulous gifts.

Not the answer you're looking for?
Ask your own homework help question
Similar Questions
An amateur race car driver needs to prepare for the next race season. He has the...
An amateur race car driver needs to prepare for the next race season. He has the following tasks that he needs to finish in 15 weeks: Activity Immediate Predecessors Normal Time (weeks) Crash Time (weeks) Normal Cost ($) Crash Cost ($) A - 8 4 4800 5400 B C,E 7 4 3900 4800 C A 7 2 5100 6600 D G 4 2 1200 2400 E A 9 3 3600 4800 F C,D 9 3 3300 6000 G A 7...
Given the information below: (Use normal time to calculate original path) a) Which activity(s) should be...
Given the information below: (Use normal time to calculate original path) a) Which activity(s) should be crashed and what is the cost to reduce the project completion time from 22 to 21 days? b) Which activity(s) should be crashed and what is the cost to reduce the project completion time from 21 to 20 days? c) Which activity(s) should be crashed and what is the cost to reduce the project completion time from 20 to19 days? d) What is the...
17b-3) Use this info for questions 1 through 5.   Chuck’s Custom Boats (CCB) builds customer luxury...
17b-3) Use this info for questions 1 through 5.   Chuck’s Custom Boats (CCB) builds customer luxury yachts. CCB has landed a contract with a mysterious New York real estate developer, Mr. T. Relevant data on the project are shown below. The complication is that Mr. T wants delivery in 30 weeks or he will impose a penalty of $200 for each week his yacht is late. Determine the lowest cost plan for crashing this project. Note: All numbers are in...
Activity Immediate Predecessor(s) Normal Time (wks) Crash Time (wks) Normal Cost ($) Crash Cost ($) A...
Activity Immediate Predecessor(s) Normal Time (wks) Crash Time (wks) Normal Cost ($) Crash Cost ($) A — 4 1 5,000 8,000 B — 5 3 8,000 10,000 C A 1 1 4,000 4,000 D B 6 3 6,000 12,000 E B, C 7 6 4,000 7,000 F D 7 6 4,000 7,000 You are the manager of a project to improve a billing process at your firm. Table 3 contains the data you will need to conduct a cost analysis...
Consider a project having the following six activities:                                  
Consider a project having the following six activities:                                                      Immediate                                                  Max        Crash cost             Activity                           Predecessors           Time (weeks)             Crash*    per week                   A                                none                                    6                          6                N/A                   B                                none                                    5                          2               $500                   C                                A                                       3                          2             $1000                   D                                A, B                                    4                          2             $2000                   E                                 C, D                                    5                          2             $1250                   F                                D                                       6                          2             $1000                                                                                                 *Shortest possible time for the task Draw the project network and list the...
Activity A Duration 6 Predecessor - Crash weeks - Crashing cost per week - B 4...
Activity A Duration 6 Predecessor - Crash weeks - Crashing cost per week - B 4 A 2 $480 C 5 A 1 $380 D 6 A 3 $450 E 5 B 2 $430 F 4 B,C 3 $350 G 5 C,D 2 $410 H 6 D 2 $570 I 5 E,F 2 $540 J 6 E,F,G 2 $530 K 3 G,H 1 $550 L 4 I,J 1 $560 M 5 I,J,K - $620 N 6 H,K,J 1 $650 O...
A car dealership decided to add an annex to its sales office as a customer lounge....
A car dealership decided to add an annex to its sales office as a customer lounge. The project is divided into the activities listed in the following table. The immediate predecessor(s), times and costs, both normal and crashed, are given. To finish the project sooner, the dealership has to make time and cost tradeoffs. If the project needs to be finished in 25 weeks, you are required to formulate a linear programming model to decide about how much to crash...
Development of Version 2.0 of a particular accounting software product is being considered by Jose​ Noguera's...
Development of Version 2.0 of a particular accounting software product is being considered by Jose​ Noguera's technology firm in Baton Rouge. The activities necessary for the completion of this project are listed in the following​ table: Activity Normal Time (weeks) Crash Time (weeks) Normal Cost Total Cost with Crashing Immediate Predecessors(s) A 4 3 $2,200 $2,850 --- B 2 1 $2,100 $2,700 --- C 3 3 $750 $750 --- D 8 4 $2,500 $2,800 A E 6 3 $800 $1,250...
Use the following data for question below. Activity Normal Time (weeks) Crash Time (weeks) Normal Cost...
Use the following data for question below. Activity Normal Time (weeks) Crash Time (weeks) Normal Cost Total Cost with Crashing Pred 1 Pred 2 A 10 7 $200 $400 B 15 10 $250 $600 C 13 8 $600 $1,500 A B D 14 10 $800 $1,200 A B E 8 4 $1,000 $3,000 C D F 12 6 $1,200 $1,800 C D G 7 6 $700 $1,400 E F H 5 3 $500 $900 E F If the project must...
Consider a project to produce custom door moldings for GMC Acadia​ cross-over vehicles, described in the...
Consider a project to produce custom door moldings for GMC Acadia​ cross-over vehicles, described in the following table. Activity   Activity Time (weeks)   Immediate Predecessor(s) START   0   - A   2   START B   6   START C   1   B D   2   A E   8   A, B F   8   D, E G   2   C, E FINISH   0   F, G You are interested in completing your project as soon as possible. You have only one option. Suppose you could assign Employee​ A, currently assigned to...