Question

Activity A Duration 6 Predecessor - Crash weeks - Crashing cost per week - B 4...

Activity

A

Duration

6

Predecessor

-

Crash weeks

-

Crashing cost per week

-

B 4 A 2 $480
C 5 A 1 $380
D 6 A 3 $450
E 5 B 2 $430
F 4 B,C 3 $350
G 5 C,D 2 $410
H 6 D 2 $570
I 5 E,F 2 $540
J 6 E,F,G 2 $530
K 3 G,H 1 $550
L 4 I,J 1 $560
M 5 I,J,K - $620
N 6 H,K,J 1 $650
O 4 M,N -

- The time for each activity tocomplete, the possible weeks by which that time can be reduced and the cost per week to decrease the activity time. The cost to complete the project in normal time is $10,000 (crashing)

1. Draw the project network for this project?what are the slacks in the steps?

2. what is the minimum duration of the project? 3. what are the critical paths of this project? 4. How much will be the most economical way to complete the project in 27 weeks?

Homework Answers

Answer #1

1. Project Network and ES, EF, LS and LF are shown in the snapshot below:

Numbers notation on each node/activity:

Top Left - ES (Early Start)

Top Right: EF (Early Finish)

Bottom Left: LS (Late Start)

Bottom Right: LF (Late Finish)

Center: Activity Names

Bottom Middle: Activity times (in weeks)

Slack = (LF - EF) or (LS - ES)

All the above values can be tabulated and calculations can be done for Slack as shown below:

Activity Duration Predecessor Crash weeks Crashing cost per week ES EF LS LF Slack
Start 0 - - $0 0 0 0 0 0
A 6 - - $0 0 6 0 6 0 A
B 4 A 2 $480 6 10 8 12 2
C 5 A 1 $380 6 11 7 12 1
D 6 A 3 $450 6 12 6 12 0 D
E 5 B 2 $430 10 15 12 17 2
F 4 B,C 3 $350 11 15 13 17 2
G 5 C,D 2 $420 12 17 12 17 0 G
H 6 D 2 $570 12 18 14 20 2
I 5 E,F 2 $540 15 20 19 24 4
J 6 E,F,G 2 $530 17 23 17 23 0 J
K 3 G,H 1 $550 18 21 20 23 2
L 4 I,J 1 $560 23 27 25 29 2
M 5 I,J,K - $620 23 28 24 29 1
N 6 H,K,J 1 $650 23 29 23 29 0 N
O 4 M,N - $0 29 33 29 33 0 O
Finish 0 O - $0 33 33 33 33 0

2. Minimum duration of the project = 33 weeks

3. Critical Paths:

All those activities which have ZERO SLACK lie on the CRITICAL PATH. [That's the rule and definition of critical path, since activities on critical path HAVE TO BE started and finished on their scheduled times]

So, Critical Path activities are: A, D, G, J, N, O (as also highlighted in the snapshot below:

So, Critical Path is: A - D - G - J - N - O

Critical path time = 6 + 6 + 5 + 6 + 6 + 4 =

There can be only 1 critical path with those activities.

4. Crashing the non-critical activities will not have much impact. So, we should crash the critical activites and ensure that the non-critical activities don't become critical activities. Also, we crash starting with the least expensive activity to the most expensive.

Out of the critical activities, least expensive is G with $420 as crashing cost per week. So, we crash G by maximum weeks, i.e., by 2 weeks.

Now, Project Duration become = 33 - 2 = 31 weeks

Next candidate for crashing is D with $450 as crashing cost per week, So, we crash D by maximum weeks, i.e., by 3 weeks.

Now, Project Duration become = 31 - 3 = 28 weeks

Next candidate for crashing is J with $530 as crashing cost per week, So, we crash J by 1 week only since we need to complete the project in target 27 weeks which gets achieved by crashing J just by 1 week.

Now, project duration = 28 - 1 = 27 weeks.

So, New cost = Normal Cost + Crashing Cost

=> New Cost = $10,000 + $420*2 + $450*3 + $530*1 = $12,720

Know the answer?
Your Answer:

Post as a guest

Your Name:

What's your source?

Earn Coins

Coins can be redeemed for fabulous gifts.

Not the answer you're looking for?
Ask your own homework help question
Similar Questions
Following information is available about a project. Activity Activity Time (weeks) Immediate Predecessor(s) K 4 -...
Following information is available about a project. Activity Activity Time (weeks) Immediate Predecessor(s) K 4 - B 4 - C 5 - D 4 - E 6 K F 2 B,C,D G 4 E.F H 6 F Compute slack for each activity. Activity Slack K B C D E F G H
Use the following data for question below. Activity Normal Time (weeks) Crash Time (weeks) Normal Cost...
Use the following data for question below. Activity Normal Time (weeks) Crash Time (weeks) Normal Cost Total Cost with Crashing Pred 1 Pred 2 A 10 7 $200 $400 B 15 10 $250 $600 C 13 8 $600 $1,500 A B D 14 10 $800 $1,200 A B E 8 4 $1,000 $3,000 C D F 12 6 $1,200 $1,800 C D G 7 6 $700 $1,400 E F H 5 3 $500 $900 E F If the project must...
Activity Immediate Predecessor Optimistic Time Most-likely time Pessimistic Time A None 3 6 9 B A...
Activity Immediate Predecessor Optimistic Time Most-likely time Pessimistic Time A None 3 6 9 B A 3 5 7 C A 4 7 12 D B 4 8 10 E C 5 10 16 F D, E 3 4 5 G D, E 3 6 8 H F 5 6 10 I G 5 8 11 J H, I 3 3 3 (a). What is the expected time for each activity? (2 points) (b.) What is the variance for each...
Activities Predecessors Duration(weeks) Labour A 4 5 B A 3 5 C B 2 5 D...
Activities Predecessors Duration(weeks) Labour A 4 5 B A 3 5 C B 2 5 D C 1 5 E B 2 5 F E 8 5 G D 10 5 H B 2 5 I B 3 5 J F,G,I 3 5 K H 2 5 L J,K 3 5 M L 1 5 i.Construct an activity on the arrow network ii. Determine the Duration of the Critical Path; iii. Draw the corresponding Gantt chart iv. Draw the resource...
A partially solved PERT problem is detailed in the table below. Times are given in weeks....
A partially solved PERT problem is detailed in the table below. Times are given in weeks. Activity Immediate Predecessor(s) Optimistic Most Likely Pessimistic A -- 8 10 15 B -- 7 8 9 C A 5 6 10 D A 3 3 3 E B,D 1 5 9 F B,D 4 7 10 G C 3 8 10 H E 5 7 9 I E 4 5 8 J F 2 5 8 K H, I 1 3 6 a)...
Activity Immediate Predecessor(s) Normal Time (wks) Crash Time (wks) Normal Cost ($) Crash Cost ($) A...
Activity Immediate Predecessor(s) Normal Time (wks) Crash Time (wks) Normal Cost ($) Crash Cost ($) A — 4 1 5,000 8,000 B — 5 3 8,000 10,000 C A 1 1 4,000 4,000 D B 6 3 6,000 12,000 E B, C 7 6 4,000 7,000 F D 7 6 4,000 7,000 You are the manager of a project to improve a billing process at your firm. Table 3 contains the data you will need to conduct a cost analysis...
The project manager of a task force planning the construction of a domed stadium had hoped...
The project manager of a task force planning the construction of a domed stadium had hoped to be able to complete construction prior to the start of the next college football season. After reviewing construction time estimates, it now appears that a certain amount of crashing will be needed to ensure project completion before the season opener. Given the following time and cost estimates, determine a minimum-cost crashing schedule that will shave five weeks off the project length. Note: No...
AON The table given below contains the activity label, its respective duration (in weeks) and its...
AON The table given below contains the activity label, its respective duration (in weeks) and its precedents. Use critical path method to find the critical path and activities of this project. ACTIVITY DURATION (IN WEEKS) PRECEDENTS A 6 – B 4 – C 3 A D 4 B E 3 B F 10 – G 3 E, F H 2 C, D
The following activities are part of a project to be scheduled using CPM: ACTIVITY IMMEDIATE PREDECESSOR...
The following activities are part of a project to be scheduled using CPM: ACTIVITY IMMEDIATE PREDECESSOR TIME (WEEKS) A — 7 B A 6 C A 2 D C 4 E B D 3 F D 4 G E F 6 a. Draw the network b. What is the critical path c. How many weeks will it take to complete the project d. Identify the early start, early finish, late start, and late finish for each activity in the project...
Draw the Activity-on-Arrow (AoA) and Activity-on-Node (AoN) networks using the activity dependency table given below and...
Draw the Activity-on-Arrow (AoA) and Activity-on-Node (AoN) networks using the activity dependency table given below and find the critical path(s) Activities Predecessor duration A - 2 B - 10 C A 9 D A,B 7 E A,B 9 F B 5 G C 10 H D,E 1 I D,E,F 2 J F 7 K C,H,I 2 L I,J 2 M I 1 N G,K 5
ADVERTISEMENT
Need Online Homework Help?

Get Answers For Free
Most questions answered within 1 hours.

Ask a Question
ADVERTISEMENT