Question

Consider a project to produce custom door moldings for GMC Acadia​ cross-over vehicles, described in the...

Consider a project to produce custom door moldings for GMC Acadia​ cross-over vehicles, described in the following table.

Activity   Activity Time (weeks)   Immediate Predecessor(s)
START   0   -
A   2   START
B   6   START
C   1   B
D   2   A
E   8   A, B
F   8   D, E
G   2   C, E
FINISH   0   F, G

You are interested in completing your project as soon as possible. You have only one option. Suppose you could assign Employee​ A, currently assigned to Activity​ G, to help Employee​ B, currently assigned to Activity F. Each week that Employee A helps Employee B will result in Activity G increasing its time by one week and Activity F reducing its time by one week. How many weeks should Employee A work on Activity​ F?

Employee A should work.   weeks on Activity F and the​ project's duration will be reduced t weeks.

​(Enter

your responses as

integers.​)

Homework Answers

Answer #1

ACTIVITY

DURATION

ES

EF

LS

LF

SLACK

CRITICAL

A

2

0

2

4

6

6 - 2 = 4

B

6

0

6

0

6

6 - 6 = 0

YES

C

1

6

7

19

20

20 - 7 = 13

D

2

2

4

12

14

14 - 4 = 10

E

8

6

14

6

14

14 - 14 = 0

YES

F

8

14

22

14

22

22 - 22 = 0

YES

G

2

14

16

20

22

22 - 16 = 6


ES = MAX(EF OF ALL PREDECESSORS); 0 FOR FIRST ACTIVITY

EF = ES + DURATION

LF = MIN(LS OF ALL SUCCESSOR ACTIVITIES); MAX EF AS LF FOR LAST ACTIVITY

LS = LF - DURATION

SLACK = LF- EF

CRITICAL PATH = LONGEST PATH WITH 0 SLACK:

CRITICAL PATH = B---E---F

DURATION OF PROJECT = 22


2. A SHOULD WORK ON F FOR 3 PERIODS FOR THE PROJECT TO HAVE THE LOWEST POSSIBLE SCHEDULE




ACTIVITY

DURATION

ES

EF

LS

LF

SLACK

CRITICAL

A

2

0

2

4

6

6 - 2 = 4

B

6

0

6

0

6

6 - 6 = 0

YES

C

1

6

7

13

14

14 - 7 = 7

D

2

2

4

12

14

14 - 4 = 10

E

8

6

14

6

14

14 - 14 = 0

YES

F

5

14

19

14

19

19 - 19 = 0

YES

G

5

14

19

14

19

19 - 19 = 0

YES

** Leaving a thumbs-up would really help me out. Let me know if you face any problems.

Know the answer?
Your Answer:

Post as a guest

Your Name:

What's your source?

Earn Coins

Coins can be redeemed for fabulous gifts.

Not the answer you're looking for?
Ask your own homework help question
Similar Questions
The following activities are part of a project to be scheduled using CPM: ACTIVITY IMMEDIATE PREDECESSOR...
The following activities are part of a project to be scheduled using CPM: ACTIVITY IMMEDIATE PREDECESSOR TIME (WEEKS) A — 7 B A 6 C A 2 D C 4 E B D 3 F D 4 G E F 6 a. Draw the network b. What is the critical path c. How many weeks will it take to complete the project d. Identify the early start, early finish, late start, and late finish for each activity in the project...
Consider a project having the following six activities:                                  
Consider a project having the following six activities:                                                      Immediate                                                  Max        Crash cost             Activity                           Predecessors           Time (weeks)             Crash*    per week                   A                                none                                    6                          6                N/A                   B                                none                                    5                          2               $500                   C                                A                                       3                          2             $1000                   D                                A, B                                    4                          2             $2000                   E                                 C, D                                    5                          2             $1250                   F                                D                                       6                          2             $1000                                                                                                 *Shortest possible time for the task Draw the project network and list the...
Problem 5-7 The following activities are part of a project to be scheduled using CPM: ACTIVITY...
Problem 5-7 The following activities are part of a project to be scheduled using CPM: ACTIVITY IMMEDIATE PREDECESSOR TIME (WEEKS) A — 7 B A 6 C A 2 D C 4 E B D 3 F D 4 G E F 6 b. What is the critical path? A-C-D-F-G A-C-D-E-G A-B-E-G A-B-D-F-G c. How many weeks will it take to complete the project? Number of weeks             d. How much slack does activity B have? Slack of activity B             week(s)
Embassy Club Condominium, located on the west coast of Florida, is undertaking a summer renovation of...
Embassy Club Condominium, located on the west coast of Florida, is undertaking a summer renovation of its main building. The project is scheduled to begin May 1, and a September 1 (17-week) completion date is desired. The condominium manager identified the following renovation activities and their estimated times: Immediate Activity Predecessor Time A — 3 B — 4 C — 2 D A, B, C 2 E A, D 8 F C, D 7 G D, E 5 H F...
Consider the following information for a project to add a drive-thru window at Crestview Bank.       Activity...
Consider the following information for a project to add a drive-thru window at Crestview Bank.       Activity Activity Time​ (weeks) Immediate​ Predecessor(s) A 6 − B 1 − C 9 − D 3 ​A, B E 6 B F 4 ​D, C G 5 ​E, C H 9 ​F, G b. Specify the critical path. The critical path is _____ and the project duration is_____ c. Calculate the slack for activities A and D.
1. A landscaping upgrade project consists of following activities. Times are given in weeks. Activity Immediate...
1. A landscaping upgrade project consists of following activities. Times are given in weeks. Activity Immediate Predecessor Activity Time A - 5 B A 8 C A 7 D - 6 E B, D, C 8 F D 3 G D 3 a. Draw the network diagram and find the ES, EF, LS, LF, and slack for each activity. b. Construct an early-start-date Gantt chart for the project. c. As a project manager, where would you focus your attention, given...
Office Automation, Inc., developed a proposal for introducing a new computerized office system that will standardize...
Office Automation, Inc., developed a proposal for introducing a new computerized office system that will standardize the electronic archiving of invoices for a particular company. Contained in the proposal is a list of activities that must be accomplished to complete the new office system project. Use the following relevant information about the activities: Immediate Time (weeks) Cost ($1000s) Activity Description Predecessor(s) Normal Crash Normal Crash A Plan needs — 13 8 30 130 B Order equipment A 9 6 120...
The project manager of a task force planning the construction of a domed stadium had hoped...
The project manager of a task force planning the construction of a domed stadium had hoped to be able to complete construction prior to the start of the next college football season. After reviewing construction time estimates, it now appears that a certain amount of crashing will be needed to ensure project completion before the season opener. Given the following time and cost estimates, determine a minimum-cost crashing schedule that will shave five weeks off the project length. Note: No...
Following information is available about a project. Activity Activity Time (weeks) Immediate Predecessor(s) K 4 -...
Following information is available about a project. Activity Activity Time (weeks) Immediate Predecessor(s) K 4 - B 4 - C 5 - D 4 - E 6 K F 2 B,C,D G 4 E.F H 6 F Compute slack for each activity. Activity Slack K B C D E F G H
A future construction project has the following activity relationships and activity time estimates (in days): Activity...
A future construction project has the following activity relationships and activity time estimates (in days): Activity Immediate Predecessor To Tm Tp A None 4 5 6 B None 3 6 21 C B 1 4 7 D A 2 5 8 E C, D 3 9 27 F C 3 6 15 G E, F 2 4 6 H F, G 2 2 2 Leave 2-decimal if not exact, do not round up, for example, 4.3268... will be kept as...
ADVERTISEMENT
Need Online Homework Help?

Get Answers For Free
Most questions answered within 1 hours.

Ask a Question
ADVERTISEMENT