Question

17b-3) Use this info for questions 1 through 5.   Chuck’s Custom Boats (CCB) builds customer luxury...

17b-3) Use this info for questions 1 through 5.  

Chuck’s Custom Boats (CCB) builds customer luxury yachts. CCB has landed a contract with a mysterious New York real estate developer, Mr. T. Relevant data on the project are shown below. The complication is that Mr. T wants delivery in 30 weeks or he will impose a penalty of $200 for each week his yacht is late. Determine the lowest cost plan for crashing this project.

Note: All numbers are in thousands, but keep them that way (i.e., don't enter the last three zeros).

1. What is the expected project duration before crashing any activities?

2. What is the cost of the third crash?

3. What is the cost of the seventh crash?

4. What is the total cost of all crashes that should be done to minimize costs?

5. How much should be spent on penalties?

Activity Immediate Predecessor Normal Time (weeks) # Possible Crashes Crash Cost Per Week
J - 9 1 150
K J 8 2 65
L J 5 2 50
M K 4 2 60
N L 6 2 25
P M, N 5 2 265
Q P 8 2 40
Y P 7 1 75
Z Y 6 1 105

Homework Answers

Know the answer?
Your Answer:

Post as a guest

Your Name:

What's your source?

Earn Coins

Coins can be redeemed for fabulous gifts.

Not the answer you're looking for?
Ask your own homework help question
Similar Questions
The information for project X is shown below. What are the critical path and the completion...
The information for project X is shown below. What are the critical path and the completion time of the project? Crashing Costs Activity Preceding Normal Time 1st Week 2nd Week K — 8 weeks $4100 — L K 6 weeks 3250 — N K 1 week 450 450 M L 5 weeks 3000 3500 J N 4 weeks 500 — Q J,M 6 weeks 4000 4000 KLMQ, 25 weeks KLNMJQ: 25 weeks KNJQ, 25 weeks KNJQ, 30 weeks KLMQ, 30...
Activity A Duration 6 Predecessor - Crash weeks - Crashing cost per week - B 4...
Activity A Duration 6 Predecessor - Crash weeks - Crashing cost per week - B 4 A 2 $480 C 5 A 1 $380 D 6 A 3 $450 E 5 B 2 $430 F 4 B,C 3 $350 G 5 C,D 2 $410 H 6 D 2 $570 I 5 E,F 2 $540 J 6 E,F,G 2 $530 K 3 G,H 1 $550 L 4 I,J 1 $560 M 5 I,J,K - $620 N 6 H,K,J 1 $650 O...
The project manager of a task force planning the construction of a domed stadium had hoped...
The project manager of a task force planning the construction of a domed stadium had hoped to be able to complete construction prior to the start of the next college football season. After reviewing construction time estimates, it now appears that a certain amount of crashing will be needed to ensure project completion before the season opener. Given the following time and cost estimates, determine a minimum-cost crashing schedule that will shave five weeks off the project length. Note: No...
Mega Mart Store is a discount department store badly in need of renovation. To avoid loss...
Mega Mart Store is a discount department store badly in need of renovation. To avoid loss of sales and disruption of customer shopping habits, Mega Mart wants to complete this renovation without closing the store itself, by temporarily co-locating goods from one area of the store into another, creating open spaces for renovation and re-occupation. Mega Mart is divided into four basic areas of goods: Clothing, Electronics, House Wares and Foodstuffs. Each of these areas will need to be temporarily...
1. What is an ISP (Integrated Service Provider) for supply chains? (1 point) A. A consultant...
1. What is an ISP (Integrated Service Provider) for supply chains? (1 point) A. A consultant agency which integrates the supply chain for companies B. A 2 PL or a 3PL, but not a 4PL C. A company supplying transportation and warehousing services D. A logistics service company specialized in suppling VAS (value added services) 2. What characterizes a 4 PL? (1 point) A. They are non-asset based and provides integrated services primarily supplied by asset based providers, for example...
Please answer the following Case analysis questions 1-How is New Balance performing compared to its primary...
Please answer the following Case analysis questions 1-How is New Balance performing compared to its primary rivals? How will the acquisition of Reebok by Adidas impact the structure of the athletic shoe industry? Is this likely to be favorable or unfavorable for New Balance? 2- What issues does New Balance management need to address? 3-What recommendations would you make to New Balance Management? What does New Balance need to do to continue to be successful? Should management continue to invest...