An amateur race car driver needs to prepare for the next race season. He has the following tasks that he needs to finish in 15 weeks:
Activity |
Immediate Predecessors |
Normal Time (weeks) |
Crash Time (weeks) |
Normal Cost ($) |
Crash Cost ($) |
A |
- |
8 |
4 |
4800 |
5400 |
B |
C,E |
7 |
4 |
3900 |
4800 |
C |
A |
7 |
2 |
5100 |
6600 |
D |
G |
4 |
2 |
1200 |
2400 |
E |
A |
9 |
3 |
3600 |
4800 |
F |
C,D |
9 |
3 |
3300 |
6000 |
G |
A |
7 |
3 |
2700 |
3900 |
a. Which activity has the most expensive crash cost?
b.How much is his total project cost?
c.How much would he save if the deadline were removed?
a. Most expensive crash cost is D 600
b.Total project cost =29550
c. Normal cost is 24600, He can save (29550-24600)=4950