Question

Magnolia Construction [MBH] began work in 2014 under a two-year contract which was to pay them...

Magnolia Construction [MBH] began work in 2014 under a two-year contract which was to pay them $345,000,000. In 2014, MBH spent $135,000,000 on construction and estimated the project would require another $90,000,000 to complete. In 2015, MBH spent $120,000,000 on construction. The amount gross profit to record in 2015 was:

Homework Answers

Answer #1

The amount gross profit to record in 2015 was: $153,000,000

Working

2014 2015
A Contract Price $ 345,000,000 $ 345,000,000
B Cost Incurred to Date $ 135,000,000 $ 120,000,000
C Estimated cost yet to be incurred to complete the contract $ 90,000,000 $ 0
D = B+C Total Cost $ 225,000,000 $ 120,000,000
E = (D/B) x 100 % of Completion 60% 100%
F = A x E Revenue to date $ 207,000,000 $ 345,000,000
G Revenue of Previous year $ 0 $ 207,000,000
H = F - G Net Revenue this year $ 207,000,000 $ 138,000,000
I Cost to date $ 135,000,000 $ 120,000,000
J Cost to date of previous year $ 0 $ 135,000,000
K = I - J Net Cost for the year $ 135,000,000 -$ 15,000,000
L = H - K Gross Profits $ 72,000,000 $ 153,000,000
Know the answer?
Your Answer:

Post as a guest

Your Name:

What's your source?

Earn Coins

Coins can be redeemed for fabulous gifts.

Not the answer you're looking for?
Ask your own homework help question
Similar Questions
In 2016 the ole construction corp began construction work under a 3 year contract. The contract...
In 2016 the ole construction corp began construction work under a 3 year contract. The contract price was $1,600,000. The Job was completed in 2018.                                                                                 2016                       2017                       2018 Costs incurred to date                                    400000                  935000                  1070000 Estimated costs to complete                       700000                  165000                  0 Billings to date                                                  300000                  900000                  1600000 Collections to date                                           270000                  810000                  1525000 Compute the amount of Gross Profit to be recognized for 2016 and 2017 assuming that ole is required to recognize revenue overtime. Compute the...
Hardhat Contractors received a contract to construct a bridge for $4,500,000. Construction was begun in 2014...
Hardhat Contractors received a contract to construct a bridge for $4,500,000. Construction was begun in 2014 and completed in 2015. Cost and other data are presented below: 2014 2015 Costs incurred during the year 1,500,000 2,700,000 Estimated costs to complete 2,500,000 - Billings during the year 1,900,000 2,500,000 Cash collections during that year 1,700,000 2,600,000 Assume that Hardhat Contractors uses the percentage-of-completion method for revenue recognition. Compute the amount of gross profit recognized during 2014 and 2015. 2014 2015 Contract...
Ayayai Construction Company began operations on January 1, 2020. During the year, Ayayai Construction entered into...
Ayayai Construction Company began operations on January 1, 2020. During the year, Ayayai Construction entered into a contract with Lundquist Corp. to construct a manufacturing facility. At that time, Ayayai estimated that it would take 5 years to complete the facility at a total cost of $4,498,000. The total contract price for construction of the facility is $6,045,000. During the year, Ayayai incurred $1,184,040 in construction costs related to the construction project. The estimated cost to complete the contract is...
In 2013, Long Construction Corporation began construction work under a three-year contract. The contract price is...
In 2013, Long Construction Corporation began construction work under a three-year contract. The contract price is $2,400,000. Long uses the percentage-of-completion method for financial reporting purposes. The financial statement presentation relating to this contract at December 31, 2013, is as follows:   Balance Sheet   Accounts receivable (from construction progress billings) $ 38,000        Construction in progress $ 160,000        Less: Billings on construction contract (150,000 )        Cost of uncompleted contracts in excess of billings 10,000 Income Statement   Income (before tax) on the contract...
In 2018, Omega Construction began work on a contract with a price of $850,000 and estimated...
In 2018, Omega Construction began work on a contract with a price of $850,000 and estimated costs of $595,000. Data for each year of the contract are as follows: ​ ​ 2018 2019 2020 Costs incurred during the year $238,000 $319,600 $105,000 Estimated costs to complete 357,000 139,400 -0- Partial billings 260,000 210,000 380,000 Collections 240,000 200,000 410,000 Assuming the performance obligation is satisfied over time, what would be the gross profit in 2018? Group of answer choices $255,000 $425,000...
Big Wheel Construction had the following two construction projects which began in year​ 1: Project 1...
Big Wheel Construction had the following two construction projects which began in year​ 1: Project 1 Project 2 Contract price $690,000 $425,000 Costs incurred during year 1 200,000 225,000 Estimated costs to complete 400,000 225,000 Billed to customers during year 1 230,000 175,000 Received from customers during year 1 100,000 150,000 What amount of gross profit​ (loss) would Big Wheel report on its year 1 income​ statement? Percentage of Completion Completed Contract A. ​$17,500 ​$(12,500) B. ​$5,000 ​$(25,000) C. ​$5,000...
On January 1, Year 1, a contractor began work on a $3.2 million construction contract that...
On January 1, Year 1, a contractor began work on a $3.2 million construction contract that is expected to be completed in 3 years. The contractor concludes that it is appropriate to recognize revenue over time using the input method based on costs incurred (cost-to-cost method). At the inception date, the estimated cost of construction was $2.4 million. The following data relate to the actual and expected construction costs: Year 1 Year 2 Year 3 Cost incurred $720,000 $1,170,000 $1,110,000...
The Leto Construction Company began work on a $12,000 contract on 1/1/15. Planned completion was in...
The Leto Construction Company began work on a $12,000 contract on 1/1/15. Planned completion was in 2017. The Percentage-of Completion method is used. .......................................................................2015.................2016................2017...... costs incurred to date................................$2,500...............4,200................11,550.... estimated costs to complete......................$7500...............6300................0........... billing to date...............................................$4000................5100................12,000.... collection to date........................................3800..................5000................11900.... The Gross Profit or (loss) recognized in 2017 is: Select one: a. $(150) b. $150 c. $450 d. $(450)
Martinez Construction Company began work on a $419,500 construction contract in 2020. During 2020, Martinez incurred...
Martinez Construction Company began work on a $419,500 construction contract in 2020. During 2020, Martinez incurred costs of $282,500, billed its customer for $232,500, and collected $181,000. At December 31, 2020, the estimated additional costs to complete the project total $164,140. Prepare Martinez’s journal entry to record profit or loss, if any, using (a) the percentage-of-completion method and (b) the completed-contract method. (Credit account titles are automatically indented when amount is entered. Do not indent manually. If no entry is...
Larkspur Construction Company began work on a $403,500 construction contract in 2020. During 2020, Larkspur incurred...
Larkspur Construction Company began work on a $403,500 construction contract in 2020. During 2020, Larkspur incurred costs of $263,000, billed its customer for $209,500, and collected $172,000. At December 31, 2020, the estimated additional costs to complete the project total $160,510. Prepare Larkspur’s journal entry to record profit or loss, if any, using (a) the percentage-of-completion method and (b) the completed-contract method. (Credit account titles are automatically indented when amount is entered. Do not indent manually. If no entry is...