In 2016 the ole construction corp began construction work under a 3 year contract. The contract price was $1,600,000. The Job was completed in 2018.
2016 2017 2018
Costs incurred to date 400000 935000 1070000
Estimated costs to complete 700000 165000 0
Billings to date 300000 900000 1600000
Collections to date 270000 810000 1525000